See how the Tube was built 150 years ago

Grant Prior 5 years ago

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

Cladding specialist Cover Structure goes into administration

Robertson takes over from stricken subcontractor on Aberdeen conference centre
3 hours ago

Kier clinches £57m student village for Warwick Uni

Five student blocks to be demolished to make way for new buildings
4 hours ago

Clugston to start work on £25m Hull warehouse

Arco national distribution centre will be extended for extra 220,000 sq ft
4 hours ago

McAlpine JV wins pre-construction deal on £466m hospital

J3 Limited joint venture chosen for new Jersey hospital
9 hours ago

Lendlease and McLaren win £1bn Manchester St John’s scheme

Enabling work to start next month on St John's neighbourhood
8 hours ago

DNA research firm to build new plant in Oxfordshire

Oxford Nanopore reveals plans for new manufacturing centre after £100m cash injection
8 hours ago

Urban & Civic praises speedy planners

Developer gets green light in just 20 weeks for 2,800 new homes
8 hours ago

Mears chases £2bn bid pipeline after profits weaken

Mears suffers challenging year after Grenfell disaster and Middle East contract hits
8 hours ago

Stalled Angelgate site put up for sale

Land earmarked for blighted Manchester resi scheme to go under auctioneer's hammer
1 day ago

£36m Cardiff student block set for planning OK

Crosslane gets go-ahead for 384-bed scheme
1 day ago

Boost your online presence with the new Enquirer Directory

New site for suppliers and buyers will showcase their products, services and latest stories
3 weeks ago

Vinci UK profits soar despite £18m civils loss

Profit boost from land disposal offsets further losses at Taylor Woodrow
1 day ago

FRC launches probe into Carillion finance directors

Investigation into Richard Adam and Zafar Khan over preparation of financial accounts back to 2014
1 day ago

Kier set for £48m Pirbright animal virus research lab

Work due to start before end of 2018 on the high containment large animal facility
1 day ago

Wates sees order book swell to record £5.1bn

Contractor confident about future prospects as it offers new roles to former Carillion staff
1 day ago

Engie to start stripping cladding on East London tower blocks

Canning Town and Plaistow Tower housing blocks get reclad go-ahead
1 day ago

Passer-by raises safety alarm over solar panel contractor

Director and contractor fined after ignoring safety warnings
1 day ago

RSK buys ground investigation specialist

Central Alliance is latest deal in acquisition spree by consultant
4 days ago

Plans in for Cheesegrater’s big brother in London

Tapering skyscraper at 100 Leadenhall will tower over the Cheesegrater
4 days ago

Vast £1.6bn South London estate rebuild approved

Clapham Park to be built out with 2,500 homes in mid-rise blocks
5 days ago

BESA appoints David Frise as new chief executive

Former submariner takes the helm at the Building Engineering Services Association
4 days ago

ISG clinches £17.5m Bradford leisure centre

Sedbergh sports and leisure facility will contain a 25m pool, gym
4 days ago

Berkeley unable to boost construction of new homes

Housing giant blames market conditions as it predicts £3.3bn profit in five years to 2021
4 days ago

Balfour Beatty tipped for £200m London student/office scheme

Landmark Vine Street project could become Balfour's second major contract with Urbanest
4 days ago

VolkerWessels UK margins edge up to 3.2%

Profits and order book grow by 7% on back of rising infrastructure spend
4 days ago

Weston Homes submits 1.2m sq ft Norwich scheme

Anglia Square scheme will provide over 1,000 homes, 40 shops and a 200-bed hotel
4 days ago

Network Rail seeks two geotechnical firms for £190m north deal

Scottish and North East earthworks delivery places up for grabs
4 days ago

Search to start for £400m Southend regen partner

Council searching for development partner to build 1,300 homes
5 days ago

Kier lifted by McNicholas deal in first half

Kier says claims and final account still to be settled on challenging Mersey Gateway project
5 days ago

Betting Spy: Man City can win Champions League

City look a good bet at 3/1 to go all the way
5 days ago

Contractor services