See how the Tube was built 150 years ago

Grant Prior 5 years ago
Share

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

Hinkley chief buyer joins Murphy

Laing O'Rourke procurement head Ian Holcroft joins rival contractor
3 hours ago

O’Rourke firms fined £3.8m after concrete factory death

Court hears how worker was crushed by 11 tonne concrete panel
11 hours ago

Skanska schools director joins Wates

Martin Kramer joins Wates as Home Counties pre-construction director
7 hours ago

Architect trio advance £200m Gateshead Quay plan

Plan for conference and exhibition centre to be submitted by the end of next year
8 hours ago

Lendlease profit rebounds despite Scottish problems

UK construction business returns to strong profit
10 hours ago

McAlpine to start HMRC office at Cardiff central square

Work to start on fourth major office build at £400m city centre regen scheme
11 hours ago

Prime Minister summons house builders to strategy meeting

Theresa May looks to boost construction levels
11 hours ago

Muse leads £75m Dartford town regen scheme

Work to start in spring 2019 on Westgate mixed-use scheme
1 day ago

BAM submits £32m Jedburgh campus plan

Work to start in spring on borders all-through school campus
11 hours ago

Trio picked for Midlands multi-storey parking plan

Bourne Parking, Blackwells and Dawnus in line for multi-storey park and ride programme
1 day ago

Multiplex staff let go as sites run down

Site office teams broken up as schemes nearing completion
1 day ago

Bouygues set for £300m Cavendish physics lab

Cambridge University awards first contract under new framework
1 day ago

Murphy to install 60km underground power cable

Contractor to smash UK record for horizontal drilling
2 days ago

McMullen lands £11m cladding package from O’Rourke

Specialist to start on site in April at Liverpool cancer hospital
1 day ago

Bellway delivers 11% rise in home completions

Bellway plans to open new division in the north as demand surges
1 day ago

Mace seeks to boost transport consultancy

Mace makes two senior appointments to drive airport and highways work
1 day ago

Lidl to build its largest UK warehouse in Peterborough

New £80m warehouse is discount giant's 6th to be announced this year
2 days ago

Concrete problems hit Hinkley Point tunnels

Material needs to be replaced after failing quality checks at nuclear plant
2 days ago

Interserve lenders call in advisers amid cash crunch fears

Interserve says work underway to give greater clarity on current trading and provisions
2 days ago

Balfour/Mott seals £115m area 10 road upkeep extension

Highways England opts to extend Area 10 assets support contract
2 days ago

Morgan Sindall nets £16m fisheries HQ

Existing Cefas buildings in Lowestoft will be refurbished before new office is built
2 days ago

Construction growth to stagnate next year

Construction faces recession if promised infrastructure spend delayed
3 days ago

M+W wins £25m Newton’s apple tree lab job

Work to start in December on National Physical Laboratory measuring lab
2 days ago

Seven winners on £200m Manchester roads deal

Four-year framework starts in January for highways work across the city
2 days ago

Sisk clinches £190m Great Ormond Street phase 4

Sisk beats Skanska to major clinical building project at London children's hospital
6 days ago

Carillion in talks to sell healthcare business

Contractor approached by a number of serious potential buyers
6 days ago

Network Rail secures £48bn for 2019 – 2024 programme

Funding shake-up with new gateway system to avoid overspends on major projects
6 days ago

Virtual reality backpack allows site walk throughs

Wearable computer takes VR to all parts of buildings under construction
5 days ago

Interserve mobilises for £20m Barnsley sewage works

Contractor to start first job with Yorkshire Water under new relationship
5 days ago

BAM to build £33m Edinburgh spec office

Capital Square office development to start this month
5 days ago

Contractor services