Roofer left paralysed in Wates site fall

Grant Prior 6 years ago
Share

Wates and its roofing subcontractor have been fined after a worker was left paralysed from the waist down when he fell four metres through a hole in a roof at a Swindon building site.

Giovanni Mastrodomenico, 56, from Swindon, fell through a waterproof membrane into the unguarded hole while working at the Marlborough Park development in the town on 31 August 2011.

His employer Tego Roofing Ltd, of Oxford, and principal contractor Wates Construction have been prosecuted following the incident.

Swindon Magistrates’ Court heard that Mastrodomenico was carrying out metalwork prior to the installation of a vent on the roof of the new apartment block. The hole he plunged through was where the vent was to be placed.

He fell four metres onto a concrete floor below, causing permanent injuries that have left him unable to walk and confined to a wheelchair.

An HSE investigation found that scaffolding under the hole inside the building had been removed because it was obstructing an emergency escape route, and that scaffolding planks had subsequently been placed over the hole instead.

But these planks were in turn removed to allow workmen to lay a waterproof membrane over the hole in preparation for the vent to be installed leaving nothing in place to prevent Mastrodomenico’s fall.

The court was told that the risk assessment and method statement for the work was unsuitable and insufficient because it failed to refer to the installation process for the vent.

There was confusion about who the site supervisor was when the incident happened and, although the site manager had seen the roofers working near the hole, he did not stop the work or ensure the scaffolding boards were replaced.

HSE established that Tego Roofing failed to provide adequate supervision or instruction to its employees while working on the roof.

Wates failed to plan, manage and monitor the work and did not ensure there was a risk assessment in place.

Tego Roofing Ltd, of Chalgrove, Oxford, was fined £10,000 and ordered to pay £9,460 in costs after pleading guilty to breaching CDM regulations.

Wates Construction of Leatherhead, Surrey, was fined £18,000 with costs of £11,127 after also pleading guilty to a separate breach of the same regulations.

Speaking after the hearing, HSE Inspector Keiron Jones, said: “Mr Mastrodomenico’s life and that of his family have been completely changed by the management failings on the site.

“Apart from the pain and suffering he has gone through, his employment opportunities are now restricted and he will never be able to walk again.

“Construction companies and their contractors must have proper plans in place to allow their employees to complete the job safely.

“As principal contractor, Wates failed to plan, manage and monitor the work, and ensure there was a risk assessment in place.

“Tego also failed in their duty to provide a risk assessment, ensure there was adequate supervision on-site and make sure there was a safe system of work for the installation of the vent.”

 

Latest news

Buyer deposits repaid as Manchester’s tallest tower axed

54-floor St John's Place residential tower pulled in face of cooling demand
1 hour ago

Billionaire Warren Buffett targets UK construction insurance

Berkshire Hathaway Specialty Insurance enters market as contractors struggle for cover
1 hour ago

Skilled trades pay rates hit £1000-a-week in Midlands

Self employed workers enjoyed wage rises of 6.7% last year
2 hours ago

Kier boss leaves to become Rydon construction head

Mark Norris leaves operations director role at Kier after 13 months
18 hours ago

Go-ahead for £60m Nottingham HMRC hub

Bowmer & Kirkland believed to be in line to build Unity Square offices
2 hours ago

Crooked bookkeeper stole £100k from cladding contractor

Court hears how mother and daughter used company cash to fund their lifestyles
17 hours ago

£50m stands approved for Lords cricket ground

Builder ISG to start in August on new Edrich and Compton stands
20 hours ago

Roof trusses fall on labourer

Darlington Council fined for poor site management
2 hours ago

Union demands “period dignity” on construction sites

Multiplex first contractor to sign-up with campaign for better site toilets
24 hours ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
9 months ago

Van Elle profit warning after “challenging” quarter

Lower margin contracts drag down performance as restructuring continues
1 day ago

Balfour boss in Brexit blast at Chancellor

Leo Quinn highlights construction's fears in conference call with ministers
1 day ago

Wates wins £90m post-Grenfell reclad job

Work to start this summer on five tower blocks at North London's Chalcots Estate
1 day ago

Construction forecasters bet on delayed soft Brexit

Crystal ball gazers believe UK will avoid workload fall with sluggish growth in 2019
1 day ago

Plan for £300m Lincolnshire power station

Czech power firm plans energy from waste plant next to South Humber Bank power station
1 day ago

Fitzgerald returns Bovis Homes to record profits

Margins restored and completions up 3% after 18-month turnaround
1 day ago

Late payment bill boosts calls for project bank accounts

Second reading due as MP fights to protect subcontractors from Carillion-style collapses
2 days ago

Plant hire giant Hawk falls into administration

Administrators pledge to keep kit working on site as they look for a buyer
3 days ago

HS2 forces firms to use least polluting trucks and plant

Rail project raises bar to exceed London emission standards
2 days ago

Watkin Jones hits record profits as pipeline grows

Firm enjoys three-year pipeline of 24 student rooms and build to rent sites
2 days ago

South Eastern Electrical went down owing £4m to suppliers

Contracts sold by administrators to associated company SEE Rail
2 days ago

Carey wins £16m Stratford Waterfront civils package

Cladding and mechanical packages will come up for bid in next three months
2 days ago

Mace confirmed for £350m Paddington Cube

Erith, Keltbray, J Coffey and Getjar chase basement contract
3 days ago

Skanska Costain JV starts Euston Station HS2 demolition works

McGee will demolish two office towers over 10 months
3 days ago

Forrest collapsed owing £28m to unsecured creditors

Administrator warns even secured creditor banks will lose much of £17m they are owed
3 days ago

Calls grow for Carillion action one year after collapse

Trades union claims regulators have failed to do their job and calls for a criminal investigation
3 days ago

Shareholders pushing for Kier chiefs to be ousted

Investors want changes at executive team
3 days ago

McL&H lands London’s longest river pier build

Piling to start this week for Thames Royal Wharf Pier
3 days ago

Kier to start £100m Ascot hospital

Construction to start on new Heatherwood Hospital
3 days ago

Collinson appoints ex Willmott Dixon boss as chairman

John Frankiewicz takes up new role at Preston based construction division
3 days ago

Contractor services