The A3 Hindhead Tunnel was closed in both directions last night due to a technical fault.

The Highways Agency worked with contractors throughout the night and the tunnel reopened in time for this morning’s rush hour.

The agency said: “The tunnel was closed at approximately 5.30pm following the discovery of the fault and is expected to remain closed into the night.”

The £371m tunnel was built by Balfour Beatty and stretches for 1.2miles under the Devil’s Punchbowl.

It was opened in April 2011.

Talk to the Enquirer. To share your stories email Grant Prior or Aaron Morby... always off the record




hindhead

The closure caused traffic chaos last night. pic.twitter.com/xB453RtMGx