Crossrail tunnelling marathon shifts to final drives

Aaron Morby 2 years ago
Share

Crossrail’s train tunnels are three quarters complete following the breakthrough of the Victoria TBM into Whitechapel station.

tbm_victoria_breaks_through_into_whitechapel_134404

The 150m long machine broke into the huge underground space at Whitechapel where work is taking place 35 metres below the surface to create over a kilometre of new platform and passenger tunnels for the new Crossrail station.

The TBM began her journey at Limmo Peninsula in east London at the end of 2012 and will now push ahead to finish the longest of the TBM drives at Farringdon in the last quarter of this year.

The completion of this 8.3km drive will mark the end of tunnelling on the massive project.

Now the focus is shifting to the substantial job of fitting out the stations and tunnels.

Crossrail Chief Executive Andrew Wolstenholme said: “Our tunnelling marathon deep beneath the streets of the capital is continuing apace with the construction of the new rail tunnels now three quarters complete.

“Over the past two years, our huge machines have built more than 19 miles of tunnels and removed more than two million tonnes of earth.”

Tunnelling progress

tbm_tunnellingdrives_14mar14

Three of Crossrail’s boring machines have already retired, with a further five still in use.

In the west, the tunnels between the Royal Oak Portal and Farringdon are complete.

In the east, Victoria and Elizabeth have reached Whitechapel (Complete at Farringdon in fourth quarter of 2014); Ellie is heading towards Stepney Green (complete second quarter) and Jessica is being prepared to complete Crossrail’s shortest tunnel drive between Limmo Peninsula and Victoria Dock (complete fourth quarter).

On the south east section of the route, Sophia has finished her drive and Mary is heading under the Thames (complete second quarter 2014).

Latest news

Sir Robert McAlpine racks up £52m loss

Losses prompt restructuring with construction set to return to profit this year
4 hours ago

Plans go in for £185m Manchester towers

Twin resi towers and office block planned next to Victoria Station
14 hours ago

Baldwins facing legal action over Blackwall Tunnel chaos

Transport for London tries to reclaim cost of resurfacing road following leak from mobile crane
15 hours ago

Green light for £400m Kingston town centre revamp

Construction to start on Eden Walk scheme in early 2017.
15 hours ago

HGV drivers warned after road worker crushed by runaway vehicle

20-year-old crushed to death on A21 repair site after materials delivery goes horribly wrong
1 day ago

Contest starts for £15m Tameside Interchange

Transport for Greater Manchester expects to start work at the end of this year
13 hours ago

Bouygues Development rebrands as Linkcity

Renamed UK development business starts with a £1.3bn portfolio of schemes
15 hours ago

Kier wins £8m Gloucester bus station

Council hopes bus station will lead £60m development of the King's Quarter
15 hours ago

Barratt & Segro confirmed for £3.5bn Meridian Water site

Massive new housing scheme will create 10,000 construction jobs
2 days ago

Kier starts £19m home for last Concorde

New Filton Airfield museum will tell the story of Bristol’s aerospace industry from 1910
2 days ago

Plans unveiled for London Elephant & Castle town centre

Ambitious high-rise scheme to replace famous pink shopping centre and London College of Communication
2 days ago

Henry Boot dismisses talk of construction slowdown

More doubts cast over Government stats as business booming at construction division
2 days ago

Balfour Beatty bags £130m M20 lorry park job

3,600-space lorry park to ease congestion from queueing lorries when cross-Channel transport is disrupted.
2 days ago

BAM wins £41m Birmingham City Uni project

Work starts next month on the City South Campus in Edgbaston
2 days ago

Portakabin bags £8.2m worth of school rebuild jobs

Off-site techniques cut school build times in half
2 days ago

BAM Mott jv wins Devon and Yorkshire flood schemes

Work will start on the £32m next phase of the Exeter flood relief scheme in June
2 days ago

WSP swoops to buy rival consultant Sweett

£24m deal sees WSP continue on the acquisition trail
3 days ago

Swansea Tidal Lagoon developer dumps Chinese contractor

Swansea Tidal Lagoon developer to retender £300m sea wall contract
3 days ago

Cleveland Bridge UK returns to profit after four years of losses

New management team turns steelwork contractor around with £2.5m profit
3 days ago

Leaking mobile crane closes London Blackwall Tunnel

Traffic chaos across South London as contractors battle to resurface damaged road
3 days ago

GPE gears up for two more London starts despite Brexit fear

Gt Portland Estates warns over ‘unhelpful’ EU stalemate
3 days ago

Sixteen firms win national £1.5bn RE:FIT framework

National retrofitting scheme to lower public sector energy bills
3 days ago

J Murphy joins trade body Build UK

Abestos removal firms also sign up to newly-former contractors' association
3 days ago

Forrest to build £12.6m Manchester resi scheme

Construction to start this month on twelve-storey scheme
3 days ago

Didcot recovery operation hit by further delays

Bodies of disaster victims still not returned to their families after three months
3 days ago

Brexit fears send site wages soaring to £1,000 a week

Bricklayers now earning £25 an hour as skills shortages set to intensify if UK votes to leave Europe
4 days ago

Small companies being left behind by “BIM divide”

Smaller firms missing out on the benefits of computer modelling warns Morgan Sindall
3 days ago

Local contractors urged to chase £6bn schools deal

SME leaders encourage member firms to go for places on massive education framework
4 days ago

Renew hits acquisition trail as profits soar

Engineering services specialist delivers record results in first six months
4 days ago

Green light for £2.6bn Scottish windfarm

Construction to start this year on huge infrastructure investment
4 days ago

Contractor services