Two tonne temporary roof blown off scaffold

Grant Prior 9 years ago
Share

Specialist contractor Pyeroy has been fined £10,000 after the roof of a temporary extension at Lynemouth Power Station was blown off in high winds.

A 25-metre span of the roof, that was around six metres long and weighed two tonnes, was blown off its eight-metre high scaffolding end supports on 23 December 2012.

It struck the roof of an adjacent biomass shed before landing 50 metres away beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians.

Fortunately the timing of the incident just before Christmas meant that the normally busy road was deserted.

Bedlington Magistrates’ Court heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

In 2011 Pyeroy Ltd had been instructed by the owners of the power station to build a temporary extension to the biomass shed that was designed by an external scaffold design company.

This was dismantled in August 2011 once it was no longer required.

Then in May 2012, Pyeroy was asked to install another temporary extension, this time designed by its in-house design team. Although similar to the first structure, it was to be shorter and lower.

It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. But poor communication resulted in an incomplete design plan being used.

HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

Magistrates were told that on 22 December it was noted that the weather was worse than normal, with the winds picking up. This meant some of the sheeting on the structure needed to be re-tied.

The temporary roof was blown off its end supports early the following morning. It ended up straddling a safety barrier and a dry riser pipeline between the main delivery access road and the legs of an adjacent conveyor.

HSE inspectors concluded that Pyeroy had failed to ensure those involved in the construction of the extension had the necessary knowledge and experience to do the work.

The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

Pyeroy of Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to safety breaches.

After the case, HSE inspector Andrew Woodhall said: “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

“It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

“Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof.

“As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

Latest news

Director jailed for exposing workers to asbestos

Ten tonnes of asbestos insulating board stripped out by unqualified workers
10 seconds ago

Site labour rates start rising again

Industry's biggest payroll firm says "it feels like things could be turning round"
5 hours ago

Council finds extra £33m for Buckinghamshire link road

South East Aylesbury Link Road costs soar by nearly 30% to £147m
4 hours ago

Quartet win £490m North West & Central railway works deal

Skanska, Kier, Octavius Infrastructure and Story Contracting bag major projects deal
5 hours ago

Unite Students plans first major mixed-use scheme

Developer's first mixed BTR and PBSA project to be built in Edinburgh
20 hours ago

Galliford Try names new finance director

Rentokil's Kris Hampson joins contractor to replace Andrew Duxbury
6 hours ago

Council boss hits out at bat threat to £274m road job

Natural England could scupper scheme due to be built by Ferrovial
6 hours ago

Hydrogen-fuelled diggers to be allowed onto highways

Government to raise barrier to widespread use of hydrogen fuelled plant in construction
21 hours ago

Plans in for £118m Government hub in Darlington

Work pencilled to start later this year on new home for 1,450 civil servants
21 hours ago

New contractor highlights Henry Construction jobs on website

New firm lists jobs by failed contractor to show its experience
1 day ago

Contractors line up for £2.6bn Anglian Water AMP8 deal

Eight big names land places on pioneering @one Alliance
2 days ago

McAleer & Rushe bags first major later living project

Work to start this month on 167-flat Royal Tunbridge Wells project
1 day ago

Kier starts first all-electric prison houseblock job in Kent

Next-generation fully electric T60 prison houseblock to be built at HMP Elmley
1 day ago

Keepmoat sees better times ahead in housing market

Profits dip in 2023 despite construction of record number of new homes
1 day ago

Vistry signs partnership deals for 1,900 mixed tenure homes

West Sussex former airfield and Newmarket sites to break ground
2 days ago

Turnover at Wates tops £2bn for first time

Construction division exceeds £1bn turnover as average contract value hits record high of £48.3m
2 days ago

L&G looks to sell Cala Homes in exit from house building

Insurance giant reported to be preparing to offload 3,000 homes-a-year developer
3 days ago

Multiplex profit almost trebles as margin hits 5.5%

Revenue jumps 20% to £675m as big London scheme complete
2 days ago

TopHat puts plans to open huge Corby factory on hold

Advanced manufacturing facility was due to employ 1,000 people
2 days ago

Laing O’Rourke lands Calderdale hospital job

Enabling works to start by the end of this year at West Yorkshire site
2 days ago

Go-ahead for £475m Sunderland film and TV studios

Work to start this year on first phase Corwn Work studios
2 days ago

Willmott Dixon set for £20m Stockport Community Hub

Planning decision expected in June on Marple leisure and health clinic project
2 days ago

Police hunt for blundering dumper truck thief

Raider drove into a fence before getting stuck on a bank
2 days ago

Beattie Passive files administration notice

Passivhaus pioneer has been in business for more than ten years
3 days ago

McAlpine set for £50m space and tech centre

Northumbria Uni sign pre-con deal for new satellite research hub
3 days ago

VolkerFitzpatrick seals £34m Kent road viaduct

Work to start next year on Sturry Link Road near Canterbury
3 days ago

Eight win £600m Scottish civil engineering framework

Balfour, Farrans, Graham and Morgan Sindall win major works lot
3 days ago

Site engineer crushed to death by excavator

22-year-old victim died just months after graduating from university
5 days ago

NG Bailey fined £135,000 after hospital site death

Worker died after striking overhead beam while navigating a mobile elevating work platform
6 days ago

Kier lands £30m Mansfield Connect project

Construction to start in January 2025 on town centre regeneration scheme
3 days ago

Contractor services