Plan to dig up Cambridge guided busway to end dispute

Aaron Morby 2 years ago
Share

BAM Nuttall and Cambridgeshire County Council have agreed to fund an investigation into what has gone wrong with the ill-fated guided busway project.

The council planned to launch a £31m legal claim against the contractor over unresolved defects.

But it has agreed to wait for the outcome of a six-month probe, which will involving digging up sections of the busway at night to minimise disruption.

Last year a report by technical advisers for the council advised that BAM Nuttall should be held to account for fixing problems including shallow foundations and inadequate drainage. It has been estimated this could take three years to complete.

BAM has contested the findings, but would not comment on the proposed legal threat, which looked set to reopen old wounds for the contractor on the troubled project.

BAM Nuttall has already paid the county council £33m in an out-of-court settlement last year to cover defects and extra work.

The contractor was two years late in handing over the project and claimed the council owed them around £70m more than the £84m contract price, triggering a protracted legal dispute.

At the time, BAM Nuttall said the busway had cost it £152m to build and claimed it should receive an extra £43m on top of the £118m the authority had already paid them.

But in August 2013 after an on-going legal battle over the late delivery of the project, BAM agreed to pay back £33m bringing the price paid by the council back to the original contract value.

A joint statement said that Cambridgeshire County Council and BAM Nuttall now have agreed to carry out a series of surveys and investigations into the construction of the Cambridgeshire guided busway.

“The county council has raised a number of concerns with BAM Nuttall about the construction of the guided busway which centre around movement of the foundations and the joints between the guideway beams.

“In 2014, the county council gave notice to BAM Nuttall of its intention to commence legal action in regard to these concerns. The two parties have now agreed to jointly fund a series of investigations and surveys into the behaviour of the guideway.

“The county council have agreed to put their legal action on hold pending the outcome of the surveys. The investigations include testing of the guideway components both on-site and in laboratories, a series of surveys to monitor movements of the beams and foundations, and a complete walkover survey of the busway.

“The survey work has now commenced and will take six months to complete.”

 

 

Latest news

Balfour Beatty on track for 2-3% margin by late 2018.

Leo Quinn confident of paying down borrowings as they fall due in 2018
12 mins ago

Skanska and Multiplex eye £100m City fringe office job

Aldgate Developments prepares to start £100m phase 2 office complex
21 mins ago

Speller Metcalfe wins “non-confrontational” £16m contract

Contractor to start revamp of Derby Silk Mill next year using innovative procurement model
57 mins ago

Plans for new £80m library at University of Bristol

Design team appointed as construction set to start in summer of 2019
11 mins ago

Berkeley director’s wife sells £2.7m shares

Karen Ellis and John Armit cash in shares as Berkeley soars to record high
47 mins ago

Growing Geordie PRS firm plans Brum scheme

All Saints Living plans a string of build to rent projects
14 mins ago

February start for £70m Brentford FC stadium

Buckingham Group set to start work on scaled-down Bees ground in West London
1 day ago

Boost your online presence with the new Enquirer Directory

New site for suppliers and buyers will showcase their products, services and latest stories
1 month ago

Interserve appoints ‘transformation’ director

Sally Cabrini joins board from United Utilities as Interserve set to be streamlined
23 hours ago

Race on for £20m Luton Airport multi-storey car park

Bidding opens for a second major airport car park
23 hours ago

Developer chosen for trio of Woking towers

Mixed-use specialist Coplan aims to start work on town centre transformation in 2021
24 hours ago

Barhale achieves breakthrough on tunnel under the Thames

Civils specialist takes just three weeks to bore 330 metre tunnel for new gas pipes
23 hours ago

Construction outlook brightens despite output gloom

HS2 awards see record spike in orders figures during the third quarter
4 days ago

Contractors to benefit from prequal red tape cut

Revamp of PAS 91 will help buyers know more about suppliers
4 days ago

Berkeley to build modular homes factory

Construction set to start on new plant in Kent as profits continue to soar
4 days ago

Wales switches to project bank accounts

Education and Skills Funding Agency last central agency left to adopt PBAs
5 days ago

Forrest to make apprentices redundant

Shift to using subcontractors puts M&E apprentices at risk
4 days ago

Wolverhampton Uni to rebid £20m construction college

Wates was preferred bidder for the Springfield Brewery built environment college
4 days ago

Liverpool council to set up firm to build 10,000 homes

Foundations housing company will build on council land and refurb vacant stock
4 days ago

Plans for £75m student digs in Oxford

Developer Unite Students buys site for 885-bed scheme
4 days ago

Western Thermal buys Newcastle pipework specialist

Acoustic and insulation specialist doubles workforce to 250 with Henderson Site Services deal
5 days ago

BAM starts two Glasgow primary schools worth £18m

List of Scottish school wins grows with Blairdardie and Carntyne projects
5 days ago

Betting Spy: Bookies pay out on Man City title win

Punters get paid out early while the Manchester derby promises plenty of goals
5 days ago

R G Carter to rescue stalled tower in Ipswich

£20m funding deal agreed for waterfront scheme abandoned in the 2008 crash
5 days ago

Koreans rescue £15bn Moorside nuclear power station plan

West Cumbria project gets back on track but could be delayed by four years
5 days ago

T Clarke North West boss leaves after three months

Contracting head Steve Wallwork parts company with building services specialist
5 days ago

Gleeson housing completions set to jump by 20%

Northern house builder gears up to raise it active sites to 70
5 days ago

Tender race set to begin for £35m Wimbledon site

Clarion Housing Group has ambitious plans to transform Merton
6 days ago

BBC studio firm fined after electrician falls ten metres

Court hears how lack of edge protection left worker with a blood clot to the brain
5 days ago

Morgan Sindall BeMo tie-up wins £20m Tube train depot

Deal signed for 160m long train maintenance facility in West London
6 days ago

Contractor services