Plan to dig up Cambridge guided busway to end dispute

Aaron Morby 9 years ago
Share

BAM Nuttall and Cambridgeshire County Council have agreed to fund an investigation into what has gone wrong with the ill-fated guided busway project.

The council planned to launch a £31m legal claim against the contractor over unresolved defects.

But it has agreed to wait for the outcome of a six-month probe, which will involving digging up sections of the busway at night to minimise disruption.

Last year a report by technical advisers for the council advised that BAM Nuttall should be held to account for fixing problems including shallow foundations and inadequate drainage. It has been estimated this could take three years to complete.

BAM has contested the findings, but would not comment on the proposed legal threat, which looked set to reopen old wounds for the contractor on the troubled project.

BAM Nuttall has already paid the county council £33m in an out-of-court settlement last year to cover defects and extra work.

The contractor was two years late in handing over the project and claimed the council owed them around £70m more than the £84m contract price, triggering a protracted legal dispute.

At the time, BAM Nuttall said the busway had cost it £152m to build and claimed it should receive an extra £43m on top of the £118m the authority had already paid them.

But in August 2013 after an on-going legal battle over the late delivery of the project, BAM agreed to pay back £33m bringing the price paid by the council back to the original contract value.

A joint statement said that Cambridgeshire County Council and BAM Nuttall now have agreed to carry out a series of surveys and investigations into the construction of the Cambridgeshire guided busway.

“The county council has raised a number of concerns with BAM Nuttall about the construction of the guided busway which centre around movement of the foundations and the joints between the guideway beams.

“In 2014, the county council gave notice to BAM Nuttall of its intention to commence legal action in regard to these concerns. The two parties have now agreed to jointly fund a series of investigations and surveys into the behaviour of the guideway.

“The county council have agreed to put their legal action on hold pending the outcome of the surveys. The investigations include testing of the guideway components both on-site and in laboratories, a series of surveys to monitor movements of the beams and foundations, and a complete walkover survey of the busway.

“The survey work has now commenced and will take six months to complete.”

 

 

Latest news

Geoffrey Osborne files administration notice

Contractor in talks to save parts of the business
10 hours ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
7 hours ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
10 hours ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
10 hours ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
10 hours ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
10 hours ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
1 day ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
1 day ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
2 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
1 day ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
1 day ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
1 day ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
2 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
1 day ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
2 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
2 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
3 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
3 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
3 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
3 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
3 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
3 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
4 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
3 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
4 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
4 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
3 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
4 days ago

Contractor services