TfL slammed for £900m Tube upgrade cost overrun

Aaron Morby 1 year ago
Share

The London Assembly has blamed Transport for London for gross mismanagement of a signalling contract with Bombardier setting the Tube modernisation programme back five years.

Old London Underground signalling box

An investigation into the failed signalling contract said a catalogue of management failings and errors left the District, Circle, Metropolitan, Hammersmith & City line upgrade nearly £900m over budget.

TfL ultimately paid £85m to cancel the contract with Bombardier Transport in 2013, two years after appointment. The report estimates that £67m of the settlement was wasted expenditure.

A culmination of nearly three years’ work scrutinising TfL’s sub-surface upgrade programme, the budget and performance committee report highlights how poor commercial expertise and a lack of IT procurement skills left TfL ill-prepared to appoint a suitable contractor, and vulnerable enough to be duped into a contract which Bombardier was never able to deliver.

The critical report highlights a culture where TfL management was only interested in presenting good news and was in denial about the progress and effectiveness of the programme, allowing it to continue for much longer than it should have.

The committee concluded that neither TfL nor Bombardier’s management teams were up to the task of managing the programme.

John Biggs AM, Chairman of the Budget and Performance Committee, said: “What is most remarkable about this affair is that no-one in TfL has been held to account, and the Mayor, who chairs its board, serenely and indifferently acts as if a £900m increase to the budget isn’t an issue.

“In government, heads – political or official – would roll after such financial mismanagement.  At TfL the key players have been promoted and nobody was to blame. It is a scandal.”

Transport for London’s Signal Failure report

KPMG audit – Lessons learned

TfL’s procurement process was not well thought out. Most significantly, its scoring system for evaluating bids was flawed. This meant that by significantly underbidding its competition on price, Bombardier was almost certain to be taken forward, regardless of how it scored in the technical areas of the evaluation.

Furthermore, TfL seemed to change its procurement process as it went along. If TfL had followed the process as outlined in the tender notice, then neither Bombardier nor the firm that finished second would have made the cut. By the time the field had been narrowed to two bidders, Bombardier was offering a lot more and for a lot less. If Bombardier could deliver what it was offering, then the case for appointing Bombardier was compelling.

Unfortunately, as KPMG noted “the capability of the supplier to deliver these benefits had not been adequately demonstrated or interrogated”. TfL has openly admitted it agreed a “bad contract”. The payment and penalty regimes within the contract were aligned to spend, rather than progress. This meant that in ending the contract, TfL was required to pay Bombardier a sum based on how much it had spent on the programme and not on the value of the work it had produced.

Latest news

London’s Camden Council to strip cladding from five towers

Tests reveal Chalcots Estate fitted with polyethylene core cladding
14 hours ago

First tests reveal combustible cladding on other towers

Up to 600 towers need to be checked
18 hours ago

Two killed in crane collapse on Crewe construction site

Tower crane comes down on Seddon site
1 day ago

Berkeley cleared to fast-track scheme for Grenfell survivors

Homes and Communities Agency strike deal to buy Kensington Row luxury apartment scheme
2 days ago

Buckingham Group targets £500m revenue in 2018

Profits soar as firm eyes swelling pipeline of stadium projects.
1 day ago

Five more Edinburgh schools found with building defects

Investigation reveals more schools in Edinburgh suffered wall-tie defects
21 hours ago

Galliford/Lagan jv wins £135m RAF Marham hangar

New hangar will house a dozen F-35B vertical take-off jets
1 day ago

CIOB sets up commission to probe control of build quality

Paul Nash to lead urgent review into behaviour that undermines quality in construction
2 days ago

Barratt names new finance boss

Barratt promotes Jessica White to top financial executive
21 hours ago

Opinion: Construction must say never again to another Grenfell

The industry must break with its lowest cost culture
2 days ago

Profits soar at Berkeley despite housing market uncertainty

Berkeley worried about Brexit impact on skills as half its site labour comes from EU
2 days ago

Hewden sell-off raises £120m but trade creditors get pennies

More than £41m was owed to plant hire giant's trade creditors
2 days ago

New Bovis Homes boss buys extra £2m shares

Greg Fitzgerald raises his shareholding to around £3.2m
2 days ago

Kier and Bouygues look for London subcontractors

Major meet the buyer event in the capital next week: Register now
3 days ago

Croydon council to retrofit 25 towers with sprinklers

Council to start £10m sprinkler programme in tallest housing blocks
2 days ago

Yorkshire builder’s MBO deal sowed seeds of own demise

George Hurst & Sons never recovered from an MBO a decade ago saddling the business with debt
2 days ago

Queensferry Crossing to open on August 30

End in sight for contractors who have battled against high winds for six years
3 days ago

Councils ordered to check rainscreening on all buildings

Government to fund fire rating tests on all aluminium composite material clad buildings
4 days ago

Morgan Sindall infrastructure boss to join Lagan

Nick Fletcher to return to Lagan as Chief Operating Officer
3 days ago

Architect makes loss as construction market peaks

Aukett Swanke struggling for commissions as market hits "bottom of the cycle"
3 days ago

Final concrete poured on Mersey Gateway

Bridge project on course to be completed this autumn
3 days ago

Willmott Dixon wins £20m medical school

University works swell to £320m with new Anglia Ruskin School of Medicine in Chelmsford
3 days ago

Worker trapped between roof and work platform

Contractor Pyeroy fined £130,000 for lack of MEWP training
3 days ago

Bristol Uni plan for £300m Temple Meads campus

Construction work is scheduled to get underway on 900,000 sq ft scheme in 2019
4 days ago

Morgan Sindall secures Midlands power network deal

Western Power Distribution two year contract extension worth £60m
3 days ago

Specialists named for £290m SW highways work

21 firms awarded specialist works on new South West England asset delivery model
4 days ago

Vital Energi wins Ardmore package at Ram Brewery

Specialists latest success with main contractor
3 days ago

Experts focus on rapid fire spread up exterior clad columns

Building columns clad in 'flammable' rainscreening allowed Grenfell fire to spread rapidly
4 days ago

Bechtel posts £2.3m UK operating loss

Project management specialist hit by problem contracts
4 days ago

Third of firms dropped from £1bn-plus London housing deal

Notting Hill Housing Trust names 23-strong line-up of favoured contractors
4 days ago

Contractor services