Queensferry Crossing to open five months late

Aaron Morby 3 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”

Latest news

Skanska wins £56m Derwent London office job

Old Street office scheme will look like four different buildings
7 hours ago

Industry steps-in to save stranded Shaylor trainees

Former rivals pledge to pay university fees for undergrads left with tuition bills by Shaylor
8 hours ago

Serial construction late payers could finally face fines

Industry sceptical as Government talks tough again over late payers
21 hours ago

Go-ahead for latest £54m London cycleway

Summer holiday working and longer hours in bid to cut construction traffic chaos
12 hours ago

Shaylor leaves trainees with unpaid university bills

Stunned staff discover their university fees have gone unpaid for more than a year
22 hours ago

Green light for £195m London student tower

Unite returns to central London with 900-bed Aldgate student complex
12 hours ago

Fulcrum Utility appoints former Byrne Group FD

Gas and electrical infrastructure contractor appoint Daren Harris as financial chief
12 hours ago

Boost your online presence – join the Enquirer Directory

Site for suppliers and buyers showcases products, services and latest stories
1 year ago

Atkins hires Morgan Sindall development boss

Nick Towe will drive expansion of Atkins' MetroHome business
21 hours ago

Shaylor owed subbies “more than £17m”

Supply chain left in the lurch again as anger rises over latest contractor failure
2 days ago

Restructure returns Sir Robert McAlpine to profit

McAlpine delivers £7m profit in turnaround year after £3.8m in redundancy pay-outs
2 days ago

Berkeley Homes ups major site starts despite 20% profit fall

Chairman Tony Pidgley says firm is entering a new investment phase targeted at longer-term regeneration sites
1 day ago

Severfield warns steelwork tender margins tightening

Steelwork contractor reports awakening bid activity in London office market
1 day ago

Plan to start £85m Eden Project North in 2020

Five giant mussel-shaped domes planned as Morecambe Bay seafront attraction
2 days ago

Bridge construction uses mountain building techniques

First steel sections installed at stunning Tintagel Castle bridge
2 days ago

L&G retirement homes arm boosts management team

Lovell director joins to oversee planned £2bn construction programme
1 day ago

27% of roof steel stripped from HS2 station design

Value engineers save £7m on Balfour Beatty/Vinci's Old Oak Common station project
2 days ago

Scape slashes firms on next generation Venture framework

Venture Framework contractors cut from 13 to six firms
3 days ago

Galliford Try Partnerships buys northern builder

£62m turnover Strategic Team Group to be renamed Galliford Try Partnerships Yorkshire
3 days ago

FRP Advisory appointed Shaylor administrator

Administrator confirms around 200 redundancies at collapsed Midlands contractor
3 days ago

Buckingham bags relief road for HS2 village

New route will spare Northamptonshire village from site traffic
3 days ago

Skills card scheme shuts safety test loophole

Tightening up of rules will see everyone sit a current CITB safety test
2 days ago

Kier cutting 1,200 jobs and selling housing arm

Contractor quitting non-core operations as debt levels rise again
4 days ago

Shaylor staff laid-off by Sunday morning email

Over 200 staff to be axed as directors confirm Shaylor is heading for administration
4 days ago

Willmott Dixon margin hits 2.8% as profit soars

Group builds cash reserve to weather further Brexit project delays
4 days ago

Multiplex brings profit back on track

Profit recovers to £18m on revenue of £1.1bn
3 days ago

Roof safety horror show lands contractor in court

Photos show roofers risking their lives after HSE had already served a stop notice
4 days ago

United Living wins £18m Poole tower blocks revamp

Project Admiral will see four housing tower blocks upgraded
4 days ago

Shaylor files notice of intent to appoint administrator

Subcontractors walk off sites as Midlands contractor seeks extra finance
6 days ago

Bidders day for £900m Heathrow rail tunnel project

Planned 6.5km rail link between the Great Western Main Line and London Heathrow Airport
7 days ago

Contractor services