Queensferry Crossing to open five months late

Aaron Morby 8 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”

Latest news

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
7 hours ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
11 hours ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
1 day ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
12 hours ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
10 hours ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
10 hours ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
1 day ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
11 hours ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
1 day ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
1 day ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
1 day ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
1 day ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
2 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
2 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
2 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
2 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
2 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
2 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
3 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
2 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
3 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
3 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
2 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
3 days ago

Wates-owned SES restructure delivers record profit and revenue

Building services contractor revenue soars to almost £300m
3 days ago

25 groundworks firms win £100m Places for People deal

M&J Evans, Carmac and Churngold Construction feature in housing association's line-up
3 days ago

Energy efficiency firms angry at lack of CITB support

SME contractors funding bid "does not meet the current criteria for supporting productivity or EDI"
3 days ago

£400m South Cambridge science park approved

Outline approval allows former sewage treatment works to be demolished
3 days ago

McLaren gets green light for 45-storey Leeds tower

Landmark Wellington Square scheme will see 464 flats built with 360,000 sq ft of offices
6 days ago

Heavy rain causes 1.9% construction output fall

Hopes remain undampened of a resi-led recovery this summer
6 days ago

Contractor services