Queensferry Crossing to open five months late

Aaron Morby 3 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”


Latest news

Pay row set to escalate on HS2 enabling works site

Dispute set to intensify over rates paid by labour supplier
3 days ago

VINCI starts work on new £100m Birmingham hospital

Contractor gets underway on three-year build programme
2 days ago

Four civils firms scoop £2.6bn flood and coastal framework

Kier breaks into Environment Agency preferred contractors list
3 days ago

Costain making engineers redundant at tech centre

Contractor cutting jobs at technology division it bought for £17m in 2016
3 days ago

Dozen firms win £500m City of London deal

Morgan Sindall, Osborne and Speller Metcalfe among winners
3 days ago

New £3m fund to improve construction procurement

Companies invited to bid for cash grants in CITB-led efficiency drive
3 days ago

Green light for vast Nottingham Boots Island scheme

Developer Conygar plans to build a 2m sq ft mixed-use scheme
3 days ago

Goldman Sachs bankrolls Brum’s tallest resi project

Builder Sisk can now start work on 42-storey Broad Street skyscraper
3 days ago

SME contractors agree 2.75% pay deal for workers

Annual pay increase will see hourly craft rates rise to £12.79
4 days ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
12 months ago

Lakehouse subbie goes after Sureserve for cash

Specialist wins adjudication award after contractor goes bust
4 days ago

Firms on alert for M4 Newport £185m enabling works

Bidders day planned ahead of July invitation to tender
4 days ago

Robertson hires Laing O’Rourke infrastructure ops director

Bryan Glass will head Robertson's civil engineering business in Scotland
4 days ago

Wates starts £24m Shoreham flood defence

Enabling works to pave way for 540-home Free Wharf scheme
4 days ago

£400m Eastern Highways Framework up for renewal

Essex County Council to invite bids for third generation framework in June
4 days ago

Countryside chief operating officer exits

Rebecca Worthington steps down as Countryside reports strong first half trading
4 days ago

Willmott Dixon chalks up £20m Liverpool nursing school

Liverpool John Moores University Tithebarn building and library to be extended and refurbished
4 days ago

Boy, 12, falls from scaffold ladder on poorly guarded site

Ten metre fall inflicts life-changing injuries on boy
4 days ago

Galliford Try profit warning sparks construction arm review

Firm warns profits will be £40m below forecasts after Queensferry Crossing hit
5 days ago

Morgan Sindall boosts north west leadership team

Growth drive sees new directors appointed in Manchester and Liverpool
5 days ago

Walter Lilly wins £55m London medical HQ project

Renew Group building specialist signs preconstruction services agreement
5 days ago

Autumn start for Mount Anvil’s largest ever scheme

Green light for 800-home Royal Eden Docks scheme in East London
5 days ago

Laing O’Rourke strategy boss joins Royal BAM

Simon Finnie steered strategy at Laing O'Rourke and Kier over six years
5 days ago

New Structure Tone division lands first major deal

Detail & Build team bags fit-out for new owners of Heron House
5 days ago

New Kier chief sets out to streamline £4bn group

Andrew Davies launches strategic review to simplify business and improve cash flow
6 days ago

McAleer & Rushe closes in on £400m turnover

Hotel specialist delivers further growth and £17m pre-tax profit
6 days ago

Construction’s most considerate sites revealed

Best performing contractors confirmed: Full details
6 days ago

Infrastructure clients lead drive to eliminate site accidents

Major push to end injuries and illness caused by seven key site risks
6 days ago

Rogue roofer found guilty of fraud

Court hears "abysmal" repairs charged at £38,000 were worth just £250
1 week ago

Engie names new UK chief executive

Nicola Lovett takes helm at UK and Ireland business in May
6 days ago

Contractor services