Five key safety breaches identified at Grenfell

Aaron Morby 3 months ago
Share

Deficiencies in the windows, cavity barriers and the cladding system allowed Grenfell tower to be rapidly engulfed in the blaze that saw 71 people lose their lives.

A leaked interim report for the Metropolitan Police offers the most detailed assessment yet of the failures in the refurbishment of the building.

It concludes that the fire would not have spread beyond flat 16 on the fourth floor and would not have claimed even a single life if the original facade of the building had not been over-clad between 2014 and 2016.

Parts of the building were also close to collapse at the height of the blaze, but thicker than presently required floor slabs and columns appeared to have saved the building.

According to the London Evening Standard, which has seen a leaked copy of the draft report produced by experts at BRE Global, the refurbishment of the building failed to meet fire safety standards on several counts.

There were gaps of 15cm between the window frames and concrete columns. These were plugged with a rubberised membrane, rigid foam insulation and uPVC lightweight plastic panels, the paper reported.

These materials provided a fuel that allowed the fire originally to spread to the facade and later penetrate other flats as it spread up the exterior of the building.

Cavity barriers failed to seal the void between the original concrete building fabric and the external aluminium composite material cladding during the fire. These fire blocks were often too small, or incorrectly installed found investigators.

This allowed fire to spread rapidly through a chimney effect, particularly up exterior column lines.

The BRE report also finds insulation fitted to the outside of the building was combustible, allowing fire to spread up and across sections of the facade.

ACM cladding panels had flammable polyethylene or plastic cores this allowed fire to spread upwards and across the building ,with burning droplets of polyethylene also falling and igniting combustible materials below.

Taken together the failings in the cladding system proved of greater significance taken together than in isolation.

The report also identifies a lack on door closers which meant that as tenants fled many were left open allowing smoke and fire to spread through corridors, impacting on residents escape down the single stairwell.

It also says that Grenfell should have been fitted with a wet riser main to aid firefighting rather than a dry riser and only enough room around the building for single fire engine to get close to supply water.

The report has not explicitly concluded whether the design or installation was at fault and whether works were approved or inspected.

Latest news

MPs slam building inspection and materials testing regimes

Construction under fire for "conflicts of interest that are pervasive throughout the industry"
2 hours ago

London council scraps £2bn Lendlease deal

Haringey rips-up agreement with developer to build 6,400 new homes
4 hours ago

Crane driver breaks back on Balfour Channel Tunnel site

Accident during £120m contract to install electricity cable between Great Britain and France
21 hours ago

Bid race takes-off for London City airport terminal

Key main terminal expansion substructure and concrete works up for grabs
22 hours ago

Kier fined £600,000 after concrete block hits worker

Court hears how lack of supervision led to accident on rail bridge site
13 hours ago

Graham wins £90m Congleton link road

Project includes a 85m bridge over the River Dane
1 day ago

SES lands £20m M&E deal at soft drinks bottling plant

Work to start this month powering major extension to Rugby factory
4 hours ago

Suppliers unable to contact demolition giant Cuddy Group

Calls to head office going unanswered
1 day ago

Over 1,000 staff still stranded at Carillion

Official Receiver investigators are sifting through 6bn rows of data
1 day ago

Balfour set for £60m Strathclyde Uni teaching hub

Firm lined up for first major job in £650m building programme
1 day ago

Boost your online presence – join the new Enquirer Directory

New site for suppliers and buyers will showcase their products, services and latest stories
3 months ago

60 jobs axed as Somerset building contractor sinks

Long-established R G Spiller enters administration
1 day ago

Nine in 10 councils breaking prompt payment rules

Findings emerge on six month anniversary of collapse of Carillion
2 days ago

Roadworks speed limit could be raised to 60mph

Motorway trials to test different limits through highways sites
2 days ago

McLaughlin & Harvey lands £50m Liverpool training centre

Construction to start in October on new academy
2 days ago

Plans in for final phase of £1bn Chelsea Barracks scheme

Last phase includes 126 affordable homes, and separate sports and medical centres
2 days ago

Joiners injured in temporary access platform collapse

Court hears how two workers plunged seven metres through unsafe platforms at hospital site
2 days ago

Green light for £50m Portsmouth Uni sports centre

Sports hub is the first project in a £400m University upgrade plan
2 days ago

Wates wins £161.5m Wembley resi blocks deal from Quintain

Latest deal is Wates largest ever award on a single site
5 days ago

Construction’s most considerate contractors win ultra site awards

Latest initiative rewards highest industry site standards and supply chain collaboration
2 days ago

Go-ahead for 37-storey Leeds student tower

Work to start before the end of this year on landmark student tower
5 days ago

Construction degrees come under fire from students

Students claim courses fail to prepare them for life in the industry
5 days ago

McAlpine to start £30m Manchester biomedical hub

Work to start in September on Citylabs 2.0 building project
6 days ago

Roofer in six metre plunge on to solid concrete floor

Court hears how worker suffered multiple fractures after plunge on refurbishment job
5 days ago

Cost of industry skills cards set to rise in September

CSCS leaders confirm 20% price rise per card to £36
6 days ago

£300m Bristol Uni campus approved

Work due to start on Temple Quarter Enterprise Campus early next year
5 days ago

Crossrail’s Sir Terry Morgan to lead HS2

Morgan replaces David Higgins as HS2 chairman next month
5 days ago

Shake-up in cladding fire tests to cut wait times

New testing service launched as current capacity swamped post-Grenfell
6 days ago

£25m A55 improvement scheme gets green light

Contractor to be named shortly for 2.2km stretch of the A55 at Abergwyngregyn
6 days ago

Galliford Try starts £43m central Birmingham resi job

Works starts on three blocks of luxury flats at Windmill Hill
6 days ago

Contractor services