Five key safety breaches identified at Grenfell

Aaron Morby 8 months ago
Share

Deficiencies in the windows, cavity barriers and the cladding system allowed Grenfell tower to be rapidly engulfed in the blaze that saw 71 people lose their lives.

A leaked interim report for the Metropolitan Police offers the most detailed assessment yet of the failures in the refurbishment of the building.

It concludes that the fire would not have spread beyond flat 16 on the fourth floor and would not have claimed even a single life if the original facade of the building had not been over-clad between 2014 and 2016.

Parts of the building were also close to collapse at the height of the blaze, but thicker than presently required floor slabs and columns appeared to have saved the building.

According to the London Evening Standard, which has seen a leaked copy of the draft report produced by experts at BRE Global, the refurbishment of the building failed to meet fire safety standards on several counts.

There were gaps of 15cm between the window frames and concrete columns. These were plugged with a rubberised membrane, rigid foam insulation and uPVC lightweight plastic panels, the paper reported.

These materials provided a fuel that allowed the fire originally to spread to the facade and later penetrate other flats as it spread up the exterior of the building.

Cavity barriers failed to seal the void between the original concrete building fabric and the external aluminium composite material cladding during the fire. These fire blocks were often too small, or incorrectly installed found investigators.

This allowed fire to spread rapidly through a chimney effect, particularly up exterior column lines.

The BRE report also finds insulation fitted to the outside of the building was combustible, allowing fire to spread up and across sections of the facade.

ACM cladding panels had flammable polyethylene or plastic cores this allowed fire to spread upwards and across the building ,with burning droplets of polyethylene also falling and igniting combustible materials below.

Taken together the failings in the cladding system proved of greater significance taken together than in isolation.

The report also identifies a lack on door closers which meant that as tenants fled many were left open allowing smoke and fire to spread through corridors, impacting on residents escape down the single stairwell.

It also says that Grenfell should have been fitted with a wet riser main to aid firefighting rather than a dry riser and only enough room around the building for single fire engine to get close to supply water.

The report has not explicitly concluded whether the design or installation was at fault and whether works were approved or inspected.

Latest news

Balfour Beatty delivers 2-3% construction margin goal

Leo Quinn hits phase two target of Build to Last turnaround plan
22 hours ago

Firms admit price-fixing of concrete drainage products

Precast firms took part in cartel for seven years
2 days ago

£300m Edgbaston mixed-use scheme advances

Phase one office project edges closer at New Garden Square regen scheme
22 hours ago

All JCB staff get £1000 Christmas bonus

Over 7,000 staff earn biggest Christmas bonus in a decade
21 hours ago

Robertson appoints Morgan Sindall director

Scott Wilson is now Robertson's business development director
2 days ago

Beeston leisure centre out to bid

Bidding starts on cinema project in £30m shops and 130 homes scheme
2 days ago

Scape MD to head Perfect Circle consortium

Victoria Bambini to lead AECOM, Pick Everard and Gleeds joint venture
2 days ago

EastEnders set rebuild soars £27m over budget

NAO slams BBC for planning failures and procurement delays
2 days ago

Spurs stadium delays continue into New Year

Man Utd match will be played at Wembley next month as contractors work through Christmas
2 days ago

Speedy buys construction training business for £9m

Plant hirer buys Glasgow-based Geason in construction training push
2 days ago

Summer start for £25m Carlisle flood defence plan

Flood defence plan to be revealed three years after storm Desmond hit
2 days ago

Amco wins Dunbar railway station upgrade

Work to start next summer on new platform and footbridge
2 days ago

Architects win post-Brexit talent deal

Designers win concessions but construction still in skills turmoil
3 days ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
8 months ago

Essex contractor collapses after posting record results

Bolt and Heeks Ltd in administratron with 55 job losses
3 days ago

Science park starts contractor hunt for £12m office scheme

Construction work up for grabs on trio of buildings near Liverpool
3 days ago

Hitachi to pull out of £14bn Anglesey nuclear power plant

Hitachi plans for Anglesey nuclear power plant now in doubt
3 days ago

M&E specialist Ameon replaces Imtech on Graham site

Subcontractor steps in to keep project on track
3 days ago

Marshalls to buy rival concrete brick maker

Marshalls to buy Edenhall for up to £17m
3 days ago

Argent gets go-ahead for major Tottenham Hale revamp

Contractor hunt to start soon with construction set to start next summer
4 days ago

Drylining boss banned for tax dodging

Insolvency Service investigators uncover huge CIS and VAT payment discrepancies
4 days ago

£2bn Elephant & Castle shopping centre scheme final go-ahead

Demolition to start after London mayor nods through vast scheme
4 days ago

Modular building specialist goes into administration

Timber accommodation pod maker Carbon Dynamic runs out of cash on major contract
4 days ago

Structural engineer crushed under scaffold tubes

Housing giant and scaffold contractor fined a total of £180,000
4 days ago

Consultant MHBC merges with Cumming

City of London based firm now part of global giant
4 days ago

Crossrail delayed again as costs rise by another £2bn

Mayor attacks previous management team who insisted project was "on time and on budget"
5 days ago

Top housing association hires Lendlease resi chief

Richard Cook will lead Clarion Group's ambitious development plans
5 days ago

UK’s tallest Premier Inn plan in Docklands

Premier Inn books in at 30-storey mixed resi and hotel scheme
4 days ago

Kier wins £45m Cambridge schools campus phase one

Northstowe education campus includes a new 1,800 pupil secondary
4 days ago

Ian Lawson to advise McLaren on growth plans

Former Severfield and Kier boss becomes consultant at expanding contractor
5 days ago

Contractor services