Skanska Papworth hospital job fails cladding check

Aaron Morby 6 years ago
Share

Skanska has suffered a major setback on its £165m Papworth hospital project after flammable cladding was found fitted to the building.

The hospital was expected to open in September but this will be delayed for several months
The hospital was expected to open in September but this will be delayed for several months

The contractor was due to hand over the high-profile project next month but now this will be delayed for several months while the substandard cladding is replaced.

A spokesman for Royal Papworth Hospital said: “As an NHS Trust, we have a duty to uphold the highest safety standards for our patients and staff.

“As a result, Royal Papworth Hospital’s board of directors has taken the decision not to accept handover of the building until Skanska has completed remedial work in accordance with the trust’s original requirements. This will cause a delay to the opening of the hospital.

“The hospital is currently awaiting confirmation from Skanska with regards to how long this remedial work will take, but early indications suggest it will take a number of months. ”

In recent weeks, both Skanska and an independent tester have been checking the building to ensure it meets the specifications set out in the original contract.

During this period, Skanska informed the Trust that they had used insulation materials that did not meet original requirements in the lower part of the hospital building.

Stephen Posey, chief executive at Royal Papworth Hospital NHS Foundation Trust, said: “We are extremely disappointed that we will not be able to open our new hospital in September as planned.

“Our staff have been working extremely hard to prepare for the move, and it is incredibly frustrating to discover a problem with the building at this late stage. However, we must ensure that our new building meets our original requirements.

“We do not underestimate the impact that this news will have on our staff.”

A Skanska spokeswoman said: “We remain in discussions with the trust on this matter and we are working towards a resolution in order for the hospital to open as soon as possible.

“We share the trust’s aim to uphold the highest standards for patients and staff.”

Latest news

Geoffrey Osborne files administration notice

Latest accounts show £325m turnover and 800 staff
4 hours ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
1 hour ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
4 hours ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
4 hours ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
4 hours ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
4 hours ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
1 day ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
1 day ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
2 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
1 day ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
1 day ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
1 day ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
2 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
1 day ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
2 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
2 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
3 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
3 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
3 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
3 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
3 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
3 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
4 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
3 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
4 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
4 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
3 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
4 days ago

Contractor services