Contractors fuming over Hinkley security delays

Grant Prior 9 months ago
Share

Workers looking to start on the Hinkley Point nuclear power plant are facing a wait of more than six weeks to get security clearance.

Contractors are fuming at the delays which they fear are putting off workers from joining the job.

One site source said: “I’ve worked on virtually every big nuclear site over the last few decades and it still took me eight weeks to get clearance.”

Security checks for site workers are carried out by independent agencies and administered by G4S under an £80m contract awarded by client EDF Energy.

Another source said: “The contractors are up in arms about this because the checks are taking so long.

“The whole process is a complete nightmare as they go through every tiny detail of your work history and background.

“It’s tough as it is getting enough workers to the site but things like this put people off.

“A lot of people hear about the delays and just go off to another job.”

EDF said:“The Government requires people working on nuclear sites to undergo security vetting.

“We’ve heard feedback from our contractors that the process is taking too long and we have been working with the regulator, the Office for Nuclear Regulation to address the issue.

“We have introduced a new level of access in August. For some groups of workers this is reducing the time needed to get clearance to just 24 hours. They will also undergo appropriate site inductions.”

Caroline Blackman, HR director for civils contractor Bouygues Laing O’Rourke said : “This new type of access has transformed the way our workers get onto site and means that you can be at work within days of getting a job rather than weeks.

“It’s a great example of how complex processes can be simplified without compromising standards.”

Latest news

27% of roof steel stripped from HS2 station design

Value engineers save £7m on Balfour Beatty/Vinci's Old Oak Common station project
17 mins ago

Scape slashes firms on next generation Venture framework

Venture Framework contractors cut from 13 to six firms
18 hours ago

Galliford Try Partnerships buys northern builder

£62m turnover Strategic Team Group to be renamed Galliford Try Partnerships Yorkshire
14 hours ago

FRP Advisory appointed Shaylor administrator

Administrator confirms around 200 redundancies at collapsed Midlands contractor
18 hours ago

Buckingham bags relief road for HS2 village

New route will spare Northamptonshire village from site traffic
46 mins ago

Skills card scheme shuts safety test loophole

Tightening up of rules will see everyone sit a current CITB safety test
16 mins ago

Kier cutting 1,200 jobs and selling housing arm

Contractor quitting non-core operations as debt levels rise again
24 hours ago

Boost your online presence – join the Enquirer Directory

Site for suppliers and buyers showcases products, services and latest stories
1 year ago

Shaylor staff laid-off by Sunday morning email

Over 200 staff to be axed as directors confirm Shaylor is heading for administration
1 day ago

Willmott Dixon margin hits 2.8% as profit soars

Group builds cash reserve to weather further Brexit project delays
1 day ago

Multiplex brings profit back on track

Profit recovers to £18m on revenue of £1.1bn
23 hours ago

Roof safety horror show lands contractor in court

Photos show roofers risking their lives after HSE had already served a stop notice
1 day ago

United Living wins £18m Poole tower blocks revamp

Project Admiral will see four housing tower blocks upgraded
1 day ago

Shaylor files notice of intent to appoint administrator

Subcontractors walk off sites as Midlands contractor seeks extra finance
4 days ago

Bidders day for £900m Heathrow rail tunnel project

Planned 6.5km rail link between the Great Western Main Line and London Heathrow Airport
4 days ago

Grenfell: 75% of unsafe blocks still to be reclad

Owners of 328 high rise blocks still need to complete remediation
4 days ago

Building products firm Alumasc issues profit warning

Problems at Levolux division cast shadow over upcoming results
4 days ago

Wooden football stadium plan rejected

Council rejects Forest Green Rovers plan for Zaha Hadid designed new ground
5 days ago

Flannery Plant Hire spends £30m on Cat machines

Huge deal signed at Plantworx exhibition
4 days ago

£1bn Stratford East Bank scheme clears final planning

Cultural and education centre in Olympic Park ready to go
5 days ago

Ringway wins £420m road maintenance deal

Highways England East Region contract could last 15 years
5 days ago

Hammerson unveils new Birmingham city quarter plan

1,300 homes and 1.4m sq ft of workspace planned for Martineau Galleries site
5 days ago

Planning row sees roads blocked on Persimmon site

Council blocks construction traffic to housing site
5 days ago

Tolent lands £84.5m Durham Milburngate contract

Contractor bags one of its biggest ever deals with main construction work set to start shortly
6 days ago

Government commits to net zero carbon by 2050

Industry must quickly rise to the challenge of improving the existing building stock
6 days ago

Extra week to put forward your favourite construction firms

Construction Enquirer Awards deadline extended: Enter online now
1 week ago

Wates ramps up FM offering with new business

Wates FM will target public sector work and wider spectrum of private clients
6 days ago

Worker killed by remote-controlled crane

Lift goes fatally wrong on National Grid site
6 days ago

Lendlease to start Manchester Potato Wharf phase 2

Castlefield scheme consists of two eight storey blocks
6 days ago

Wood drafted in for Hinkley Point C technical services

New Hinkley technical support deal to improve project delivery and commercial performance
6 days ago

Contractor services