Building boss fined after roof collapse on resi conversion

Grant Prior 4 months ago
Share

The director of a construction company has been sentenced after the partial collapse of a building during roofing work.

Sheffield Magistrates’ Court heard that, on 24 February 2016, Jason Lycett, a director of principal contractor Brooke Ren Limited was responsible for constructing two, two storey blocks of flats in Barnsley following the demolition of a former public house.

Timber roof structures had been constructed for each block but had not been tiled in their entirety.

Three roofers had been working on the roof of Block B, transferring tiles from ground level using a tile hoist and distributing the tiles over the surface of the roof, when the tile hoist broke down.

Two roofers had alighted the roof and a third was descending a ladder from a scaffold when the roof structure collapsed, demolishing a small wall at eaves level and distorting the scaffold.

There were no injuries, but had it not been for the breakdown of the tile hoist, the workers would have been on the roof at the time of its collapse.

An HSE investigation found that the company had been informed during the pre-construction phase that the roof structure needed to be designed by a specialist, but this did not happen until after the incident.

At the time of the collapse, the structure was not able to withstand the loads which had been applied to it.

Brooke Ren Limited pleaded guilty to breaching CDM regulations and Jason Lycett of Sheffield was found guilty of safety breaches and was been fined £30,000 with £7026.58 in costs.

Companies House records show Brooke Ren went into liquidation in July.

Speaking after the hearing, HSE inspector Alan Sheldon said: “Principal Contractors have an important role in managing health and safety risks during the construction phase, so they must have the skills, knowledge, experience and, where relevant, organisational capability to carry out this work.

“Where directors are found to be negligent in carrying out their roles, they too may face legal proceedings associated with the same health and safety management failings.

“Although there were no injuries, matters could have been very different had the workers still been on the roof at the time of its collapse.”

Latest news

Kier slumps to £35.5m loss as problem contracts continue

Workloads wobbling in highways, utilities and housing maintenance markets
10 hours ago

Griffiths to restart Dawnus £14m Swansea road job

Welsh civils firm to take on Kingsway city centre scheme
4 hours ago

Hunt for £6bn Meridian Water phase 2 developer

Up to 250 affordable homes to be built in Meridian Two scheme
9 hours ago

BBC construction skills blasted over EastEnders set woes

Lack of project management skills leads to £27m cost over-run and five-year delay
8 hours ago

Go-ahead for £175m Cumbrian deep coal mine

Plans advance for Britain's first deep coal mine for 30 years
18 hours ago

Hi Vis site wear launched for pregnant women

Clothing designed to make life safer and more comfortable "from bump to baby"
10 hours ago

Speedy buys powered access hirer for £9.6m

Lifterz deal allows Speedy to offer nationwide powered access equipment hire
10 hours ago

Build to rent specialist plans Bolton urban village

Placefirst to use in-house contractor for £27.5m scheme
11 hours ago

Water winners revealed for £2bn Severn Trent spend

More contractors win first lots on AMP7 as client revamps working practices
1 day ago

Stranded Carillion chief takes helm at Kier

Andrew Davies named new Kier chief executive
1 day ago

Interserve £170m prison project to be rebid

Ministry of Justice confirms Glen Parva to be tendered as a publicly funded project
1 day ago

Cabinet Office promises Interserve subbies will get paid

Parliamentary Secretary makes pledge in House of Commons debate
1 day ago

Sir Robert McAlpine commercial director exits

Martin Pitt steps down from board after four years at group
1 day ago

Lakehouse subbies plan showdown with Sureserve bosses

Suppliers owed millions to demand answers at company AGM
2 days ago

Tolent to build first homes at £400m Leeds scheme

Builder gets foot in the door with prototype homes for Kirkstall Forge
1 day ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
11 months ago

Interserve subcontractors told it’s business as usual

Outsourcers circle Interserve support services division
2 days ago

Morgan Sindall wins 20-year Sellafield civils deal

Four teams named for Sellafield decommissioning project partnership
2 days ago

Hunt for quartet to deliver £700m Birmingham Uni pipeline

University is preparing to deliver phase two of its estate masterplan
2 days ago

Stepnell wins £14m Northampton Vulcan works redevelopment

Historic factory to be refurbished for business start-ups
2 days ago

Hunt starts for developer on £200m South Shields scheme

South Tyneside Council looking for housing partner and remediation specialist
2 days ago

Revamp plans for Birmingham Moor Street station unveiled

Transfer deck across the top of station will connect to all platforms
2 days ago

Interserve workers told to report for work as usual

Interserve subsidiaries to trade solvently as PLC business pre-packed
5 days ago

Interserve to file for administration as rescue rejected

Shareholders vote down rescue plan
5 days ago

Dawnus Group goes into administration

Grant Thornton now in charge of contractor which employed 700 staff
5 days ago

Bricklayer killed by collapsing wall

Court hands out £900,000 fine but contractor went into administration six months after tragedy
5 days ago

Dawnus collapse a “Welsh Carillion”

Subcontractors braced for huge losses as administrators poised to take control
5 days ago

Taylor Woodrow losses halve Vinci UK profits

Building operations trade profitably but Taylor Woodrow suffers fifth year in the red
5 days ago

Plans in for £70m Edinburgh botanic garden revamp

New glasshouse features in major overhaul plan
5 days ago

Mace to steer £350m Stevenage town centre revamp

Work set to begin on site next year
5 days ago

Contractor services