Contractors chosen to build the ill-fated Garden Bridge were paid £21.4m before the project was finally binned.

Figures released by Transport for London detail payments to the Bouygues Travaux Publics and Cimolai SpA – Joint Venture.

Consultant Arup was also paid more than £12m in fees among a total of £53.5m wasted on the project.

The documents state the contractors were paid for “mobilising significant resources, systems, labour, supply chain and support networks to further refine the designs, create prototypes and samples, submit designs for approval by Arup, liaison with third parties to secure rights and consents over areas to erect the bridge and submit details to discharge the planning conditions.”

They were paid £5.1m for the Preconstruction Services Agreement period and £13.4m for the period between being awarded the £90m main contract and the project being scrapped.

A payment of £2.1m was also made for the ‘The demobilisation of staff, offices and repatriation of plant and labour upon suspending the contract.”


Alex Williams, Director of City Planning at Transport for London said: “As part of our continuing commitment to transparency, we have published the final financial breakdown for the Garden Bridge project, on behalf of the Trust, as well as all evidence sought as part of this review.

‘This formally ends our involvement with the project.”

Latest news

Competition probe launched into construction services

CMA says investigation into possible bid rigging is at a very early stage
3 hours ago

Burst pipe causes flash flood at Battersea Power Station site

Video: Watch dramatic footage of water pouring through major London project
15 hours ago

Wates trumpets record order book despite Brexit slowdown

9% fall in construction revenue offset by rise in residential and property services
8 hours ago

Vinci wins £100m UCL East student blocks deal

Firm secures Olympic Park twin student buildings
7 hours ago

Persimmon launches retention scheme for home buyers

New home owners can withhold cash until any build faults are sorted out
8 hours ago

Subcontractors wanted for South Coast sites

Work opportunities up for grabs at Meet the Buyer event: Register now
7 hours ago

Griffiths to restart Dawnus £14m Swansea road job

Welsh civils firm to take on Kingsway city centre scheme
1 day ago

Hunt for £6bn Meridian Water phase 2 developer

Up to 250 affordable homes to be built in Meridian Two scheme
1 day ago

BBC construction skills blasted over EastEnders set woes

Lack of project management skills leads to £27m cost over-run and five-year delay
1 day ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
11 months ago

Kier slumps to £35.5m loss as problem contracts continue

Workloads wobbling in highways, utilities and housing maintenance markets
1 day ago

Go-ahead for £175m Cumbrian deep coal mine

Plans advance for Britain's first deep coal mine for 30 years
2 days ago

Hi Vis site wear launched for pregnant women

Clothing designed to make life safer and more comfortable "from bump to baby"
1 day ago

Speedy buys powered access hirer for £9.6m

Lifterz deal allows Speedy to offer nationwide powered access equipment hire
1 day ago

Build to rent specialist plans Bolton urban village

Placefirst to use in-house contractor for £27.5m scheme
1 day ago

Water winners revealed for £2bn Severn Trent spend

More contractors win first lots on AMP7 as client revamps working practices
2 days ago

Stranded Carillion chief takes helm at Kier

Andrew Davies named new Kier chief executive
2 days ago

Interserve £170m prison project to be rebid

Ministry of Justice confirms Glen Parva to be tendered as a publicly funded project
2 days ago

Cabinet Office promises Interserve subbies will get paid

Parliamentary Secretary makes pledge in House of Commons debate
2 days ago

Sir Robert McAlpine commercial director exits

Martin Pitt steps down from board after four years at group
2 days ago

Lakehouse subbies plan showdown with Sureserve bosses

Suppliers owed millions to demand answers at company AGM
3 days ago

Tolent to build first homes at £400m Leeds scheme

Builder gets foot in the door with prototype homes for Kirkstall Forge
2 days ago

Interserve subcontractors told it’s business as usual

Outsourcers circle Interserve support services division
3 days ago

Morgan Sindall wins 20-year Sellafield civils deal

Four teams named for Sellafield decommissioning project partnership
3 days ago

Hunt for quartet to deliver £700m Birmingham Uni pipeline

University is preparing to deliver phase two of its estate masterplan
3 days ago

Stepnell wins £14m Northampton Vulcan works redevelopment

Historic factory to be refurbished for business start-ups
3 days ago

Hunt starts for developer on £200m South Shields scheme

South Tyneside Council looking for housing partner and remediation specialist
3 days ago

Revamp plans for Birmingham Moor Street station unveiled

Transfer deck across the top of station will connect to all platforms
3 days ago

Interserve workers told to report for work as usual

Interserve subsidiaries to trade solvently as PLC business pre-packed
6 days ago

Interserve to file for administration as rescue rejected

Shareholders vote down rescue plan
6 days ago

Contractor services