Crossrail can’t find enough managers to complete project

Grant Prior 5 years ago
Share

Crossrail bosses are struggling to find project managers to complete the delayed scheme.

A damning report from the National Audit Office has revealed that Crossrail currently has 143 unfilled vacancies at its central delivery team “including project delivery teams to work with main contractors to deliver the programme.”

There are also 33 further vacancies across the orgnaisation as it battles to hit a revised opening deadline of between October 2020 and March 2021.

Crossrail scaled down its central management team as the job approached its original December 2018 opening date.

The NAO report said: “In order to be able to manage programme risks and the complex contractual arrangements effectively, Crossrail Ltd needs to rebuild its capability and capacity in a number of disciplines.

“During 2018, Crossrail Ltd reduced the number of staff in its central functions, such as risk management, planning and contract and commercial management, as it pursued its demobilisation plans in accordance with its aim to meet the December 2018 deadline.

“All of these functions are critical to completing the programme efficiently and effectively.

“The company now recognises that it still needs skills and has started to recruit.

“It has hired a head of risk and plans to increase the team from one person to five, and has reinstated its audit and assurance committee, which it disbanded in 2018.

“It has increased the size of the planning team by 15 to 34. It is also re-establishing its external affairs team.

“Crossrail Ltd has, however, struggled to recruit the skills it needs. Its capacity to manage the programme effectively remains a key risk.”

The revelation is among a catalogue of management blunders highlighted in the NAO report which have resulted in the project running two years late and £2.8bn over budget.

It details how Crossrail chiefs lost control of contractors and made a series of operational mistakes in a desperate attempt to hit the doomed original deadline.

The report blames cost increases on:

  • Crossrail Ltd’s delivery and commercial strategy
  • the build-up of delays, dependencies and interfaces between contracts and projects
  • not changing course when there were clear signs that the programme was not on track

The NAO believes major problems were evident on the project as early as 2015 and resulted in changes required to the design and to contractors’ delivery schedules which increased costs on most of the 36 main contracts.

It said: “Between February 2017 and December 2018, for example, the forecast final cost of the contract to install track and key systems in the tunnels increased by 80% from £532 million to £956 million.

“Crossrail Ltd also made decisions that drove unnecessary cost.

“In early 2018, Crossrail Ltd began carrying out train testing and construction activity in alternating time periods, to allow for early sight of potential train and signalling system issues.

“However, this testing was of limited use and took any spare time and space from construction workers on site.

“Crossrail Ltd also reduced the size of its central programme and risk management teams during 2018, in anticipation of the programme reaching completion in December 2018.

“It is currently attempting to rehire these personnel. ”

NAO head Amyas Morse said: “There have been a number of choices made in the course of this project that have clearly damaged public value.”

The extent of cost increases on major contracts laid bare in the report:

Latest news

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
16 mins ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
17 mins ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
4 hours ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
3 hours ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
4 hours ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
4 hours ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
15 hours ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
21 hours ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
1 day ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
1 day ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
1 day ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
1 day ago

BAM signs Kent school contract at £42m

Sevenoaks school rebuild signed off at £8m more than first estimates
1 day ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
4 days ago

Geoffrey Osborne files administration notice

Contractor in talks to save parts of the business
4 days ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
4 days ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
4 days ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
4 days ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
4 days ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
5 days ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
5 days ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
6 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
5 days ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
5 days ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
5 days ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
6 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
5 days ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
6 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
6 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
6 days ago

Contractor services