BMM JV signs Leeds flood alleviation deal for £76m

Aaron Morby 4 months ago
Share

Leeds City Council has agreed a £76m price with BAM Nuttall and Mott MacDonald to deliver the next phase of the Leeds Flood Alleviation Scheme.

BMM completed phase one lifting weir works in 2017

Now work will start on site before the end of the year. BMM will build linear defences along an 8km stretch of the River Aire upstream of Leeds Station.

Three key areas will get improved defences in step one of phase two of the city flood defence project.

At Leeds Industrial Museum at Armley Mills, there will be new protective walls, a new higher bridge to improve water flow and two new control structures on the goit which can close when the river levels become too high.

A new structure will also be built at Kirkstall Abbey in front of Kirkabbey Sluice Gates which will limit the amount of water during high river levels going down the goit channel.

The proposal at Kirkstall Meadows is to transform 2.4 hectares into a wetland habitat and also feature kingfisher banks, otter holts and wetland scrapes for fish. A new flood embankment will reduce flood risk to the adjacent railway line.

Landscaping works will also be carried out to benefit the environment and wildlife, and to improve access to amenities. This will include two new bridges, improvements to footpaths and new natural areas.

Talks are continuing over securing the required funding needed to complete the £112m next element of the phase two scheme.

This will lift the whole scheme up from a one-in-100 year event to a one-in-200-year level of protection.

The £50m phase one of the scheme, featuring moveable weir technology to protect Leeds city centre and downstream to Woodlesford, was completed in 2017.

BAM Nuttall CEO Steve Fox said: “Our teams at BAM Nuttall and Mott MacDonald are proud to be awarded the contract for the second phase of Leeds Flood Alleviation Scheme, building on our strong partnership with Leeds City Council and the Environment Agency.”

Calverley attenuation area: New flood storage area and control structure.

Once the further funding has been secured and planning approval received for it, step two of the two-step approach would see the creation of a flood storage area near Calverley, with moveable weir technology used to allow water to be stored and then be released slowly back into the river in a controlled way.

Carrying out the second step would reduce the risk of flooding along the 20km stretch of the River Aire from the outer ring road to the west of the city, through the city centre and past Stourton.

Latest news

Construction braced for freelance tax disruption

Self-employed professionals face major contractor move back to PAYE
1 hour ago

Rain halts BAM’s Carlisle flood defence job until Spring

Wet weather in August and September blamed for pause on £25m scheme
1 hour ago

Bristol student tower block trio approved

Work expected to start at Temple Island midway through next year
2 hours ago

Atkins names ex-HS2 ops boss as UK chief executive

Richard Robinson will lead Atkins UK's 10,000 strong team
19 hours ago

Procurement bodies team up for new consultants framework

North West and Southern framework groups call up multi-disciplinary consultants
2 hours ago

Materials giant sees brick and block sales weaken

Bison precast business hit by contract delays
2 hours ago

Wates kicks off York council house building programme

£27m Lowfield Green scheme will see 140 homes built
2 hours ago

L&G commits to £750m affordable homes investment

Affordable homes division hires former Capco director to deliver 3,500-home pipeline
18 hours ago

ISG names new UK construction chief

Zoe Price promoted to chief operating officer for construction
1 day ago

Interserve set for £36m Walsall hospital A&E upgrade

Work to start in April next year at Walsall Manor Hospital
1 day ago

London council to overhaul £370m housing upkeep

Lambeth council to give residents say in policing delivery by contractors
1 day ago

Carpenter falls through gap in safety deck

Badly installed safety system did not cover whole work area
1 day ago

Fusion21 launches £250m energy efficiency framework race

Firms installing PV panels, cladding and LED lighting called up for new framework
1 day ago

Boost your online presence – join the Enquirer Directory

Site for suppliers and buyers showcases products, services and latest stories
1 year ago

Construction safety test cheats caught in police raids

Crooked test centres in answers for cash scandal
4 days ago

Demolition giants land places on £50m framework

Housing Association Notting Hill Genesis confirms eight winners
4 days ago

Green light for £79m “Mancunian” tower

Planners approve major city centre regeneration scheme
4 days ago

FEC starts £470m Isle of Dogs twin tower project

JRL starts piling work on 65 and 35-storey hotel and flats project
5 days ago

£200m Lancashire waste incinerator approved

Heysham Gateway energy recovery facility will create 350 construction jobs
4 days ago

Common prequal standard adopted for HS2 subcontract bids

Main works civils contractors adopt new PQQ system to cut supply chain costs
5 days ago

Westridge to restart stalled Brighton Dome revamp

Contractor wins race to replace Britain's oldest builder on £21m renovation job
5 days ago

Laing O’Rourke returns to profit

Britain's biggest private contractor returns a £33m profit after stemming losses in Canada
5 days ago

Vast Elizabeth House London scheme to start next year

HB Reavis gets planning go-ahead for 1.2m sq ft project beside Waterloo Station
6 days ago

Digger driver jailed after builder crushed by excavator bucket

Ten month sentence after worker killed in trench
5 days ago

Winvic margin falls as revenue jumps 29% to £628m

Pre-tax profit drops a third to £20m as shed builder boosts workforce for growth
4 days ago

Interserve signs off £13m Oldham cultural hub deal

Firm lands heritage and art centre project where Gilbert Ash held a pre-construction services agreement
6 days ago

William Birch lands York housing scheme from local charity

Construction to start later this year on apartments for visually impaired people
5 days ago

Winner picked for £250m ‘Harrods of Bayswater’ job

London's Whiteleys shopping centre to be redeveloped
6 days ago

No win no fee service launched for construction disputes

New service to create "level playing field" for smaller contractors considering adjudication claims
6 days ago

Alun Griffiths lands £85m Cornish link road

Construction could start next year on St Austell scheme
6 days ago

Contractor services