Highways England delays 22 major road projects

Aaron Morby 3 years ago
Share

Twenty-two major road improvement projects in England have been delayed or face cancellation after Highways England revised its £15bn road improvement programme.

Highways England said that 16 projects were being put back by between three months and two years to reduce the impact of roadworks on motorists and minimise congestion while improvements take place.

They include four separate upgrades to the M25, work on the M60 in Greater Manchester, the M3 in Winchester and the A5 in Nuneaton, Warwickshire,

Six more projects may not happen at all after Highways England said they were being “paused for further review” to achieve an acceptable return on investment.

But the rescheduling programme outlined in the Supplementary Delivery Plan will see 10 schemes brought forward.

10 schemes being brought forward

  • A19 Testos
  • A19 Downhill Lane
  • M56 junctions 6-8 smart motorway
  • M6 junctions 21a – 26 smart motorway
  • M6 junction 22 upgrade
  • A500 Etruria
  • M6 junction 10
  • M4 Heathrow Slips
  • A47 Acle Straight -small scale improvement
  • A47 and A12 junction enhancement

16 schemes being re-scheduled

  • A5 Dodwells to Longshoot widening
  • M3 junction 9 improvement
  • A31 Ringwood
  • M27 junctions 4-11
  • A47 North Tuddenham to Easton
  • A47 Blofield to North Burlingham dualling
  • M25 junction 25 improvement
  • M25 junction 28 improvement
  • A1 Birtley to Coal House
  • M60 junctions 24-27 and junction 1-4 smart motorway
  • A47/A11 Thickthorn
  • A47 Wansford to Sutton
  • A47 Guyhirn Junction
  • A12 Chelmsford to A120 widening
  • M25 junction 10/A3 Wisley interchange
  • M25 junctions 10-16

Schemes on hold pending value for money review

  • A1 & A19 Technology enhancements
  • M11 junctions 8 to 14 technology upgrade
  • A12 whole-route technology upgrade
  • M53 junctions 5-11 smart motorway
  • A14 Junction 10a
  • M62/ M606 Chain Bar

Highways England said two further schemes – the M5 Bridgwater junction improvements and A50 Uttoxeter Project B growth corridor project – required rework to achieve value for money, but changes in local development plans mean that these schemes could be progressed, albeit pushed back  in the early stages of Road Period 2.

Jim O’Sullivan, Highways England Chief Executive said: “Our update today is a sensible and responsible way to deliver major national investment in road infrastructure. It will keep our roads moving, deliver a lasting legacy for the country and ensure best value for money for the taxpayer.

“We have assessed the value for money provided by each of the schemes in our plans and of their impact on road users, and have also looked at how each scheme fitted with the overall objectives of the RIS and its costs and benefits.

“This rigorous process identified a number of schemes which do not meet our targets for value for money. For many of these schemes we were able to develop options to improve their value for money. For the remaining schemes
we will continue to review other value for money options and consider scheduling these schemes as part of any future RIS.”

Details of revised start dates.

Latest news

BAM to make 150 staff redundant

Drop in demand set to impact 2021 revenue
14 hours ago

Bouygues to start on £240m Canning Town scheme

Phase three of Hallsville Quarter regeneration scheme gets green light
57 mins ago

“Builders stars of the economy” as construction rebounds

Latest buyers survey shows sharp turnaround in output as lockdown eases
20 hours ago

Smart motorways chief moves to Lower Thames Crossing job

Shaun Pidcock takes project director role on UK's longest road tunnel
12 mins ago

Lendlease gets nod to start Manchester town hall revamp

Council agrees to 5 month completion delay as notice to proceed agreed
26 mins ago

Flannery trials first electric tele at HS2 site

Skanska Costain Strabag JV to roll out more machines across HS2
19 hours ago

Morgan Sindall stars in £250m Glasgow Uni framework

University confirms nine construction partners
6 hours ago

Barratt uncovers weak concrete frames at seven high rises

House builder faces £70m bill to remediate high rise flats
23 hours ago

McAleer & Rushe starts £68m Birmingham resi tower

37-storey build to rent tower forms part of £120m Exchange Square 2 scheme
21 hours ago

CPUK went down owing suppliers more than £9m

Construction Partnership UK Limited brought down by bad debts and Covid-19
23 hours ago

Wates resumes full pay for all staff not on furlough

Chief praises staff for great professionalism in the most challenging of conditions
4 days ago

First net-zero carbon London office project approved

Mace advising on £160m project to expand and retrofit former BT HQ
24 hours ago

Interserve to start £27m Oldham school job

Work starts this month on Saddleworth secondary school
21 hours ago

Construction start date for latest Manchester resi scheme

Work to begin early next year at Bowler’s Yard
22 hours ago

£120m rescue package for stalled arts sites

Cultural rescue programme to restart work on theatres, galleries,museums and cinemas
1 day ago

Canary Wharf Contractors could cut 100 jobs

Another round of redundancies as projects come to an end with no replacements in pipeline
4 days ago

Tower crane lifts end long climb to work for operators

Laing O'Rourke trials mast climbing lifts for tower crane operators at London site
4 days ago

Keep the industry updated by joining the Enquirer Directory

Membership lets construction know you are open for business now or in the future
2 years ago

Government agrees £30m bailout for rebar giant

Emergency loan to Celsa secures rebar supplies to construction
4 days ago

Plans go in for 2,200-home Oxfordshire garden village

Sustainable scheme will also include new schools and manufacturing space
5 days ago

Winvic raids Graham Construction for civils boss

Rob Cook joins as civils and infrastructure director at Winvic
5 days ago

Work with the Enquirer to help your post Covid recovery

Promote your business now to grab a bigger market share as construction bounces back
3 weeks ago

HS2 rebids £300m overhead power system

Bidding starts for first overhead lines powering trains to operate at 360km/h
5 days ago

Sisk seals £150m Santander campus in Milton Keynes

Biggest building contract signed off during restricted covid working
5 days ago

Builder wanted for £35m Forth Bridge tourist attraction

Contract to build bridge walkways and viewing platforms to be awarded before the end of 2020
5 days ago

JCB powers up first hydrogen fuelled digger

JCB in race to lead the world on hydrogen-powered plant
5 days ago

Construction site death rates on the rise

Latest HSE figures show 40 construction fatalities last year
6 days ago

Construction firms urged to claim millions in tax rebates

Research and development tax credits available - find out if you can claim
5 days ago

Plans in for £150m South Kensington Tube station scheme

Native Land and TfL advance scheme to revamp west London Underground station site
5 days ago

Hotel plan for Lincoln department store aproved

Town centre House of Fraser will be demolished for a 150-room hotel
4 days ago

Contractor services