Retractable pitch tested at Spurs stadium site

Grant Prior 7 years ago
Share

Spurs have successfully tested their retractable grass pitch as Mace work flat out to finish the club’s new stadium in time for the start of the new season.

The club has released images of the hi-tech pitch trays being moved out from underneath the South Stand.

The system has been designed, engineered, built and installed by Sheffield-based specialist SCX.

The pitch will be made up of three sections in total with the east section set to be tested in the near future.

Once complete all three sections will slide out simultaneously in approximately 25 minutes, with the west and east sections moving laterally to connect with the centre section and create seamless joins in the grass playing surface.

The hydraulic sides were also tested over the weekend – weighing 480 tonnes these sides lift once the three pitch trays have connected in order to raise the touchlines so they are at the same level as the grass playing surface.

Nick Cooper Head of Moving Structures said: “This represented the first time we’ve moved the pitch trays out.

“To do that, we had to fix up the generators, the electrics, SCX brought down their design and mechanical engineers just in case anything happened and what I can report is that it worked first time exactly how we wanted it to work, which is great news.

“The hydraulic sides are enormous, a 120-metre truss that runs the full length of the pitch and it all moves up and raises together. In one side, there are eight moving bridges all operating concurrently.

“That is a tremendous achievement by the electrical engineers. The sides weigh 480 tonnes, so we’re lifting 480 tonnes up in a matter of minutes – and it all works beautifully.”

Danny Pickard, Senior Project Manager, SCX “It was all about the first movement from the garage area where we’ve assembled the pitch trays to bring them out into the bowl to see how smoothly it ran, to see how well the edges of the trays lined up and to also interface with the hydraulic pitch sides, so a test of what we’d call the big picture, how all the big pieces fit together.

“It took a lot of work by a lot of people to get it there, lots of late nights but the weekend went brilliantly.

“We’d done a lot of testing beforehand of all the smaller pieces but the size and scale of the overall project…there is a lot of weight, mechanisms, manufacturing tolerances and installation tolerances, so to have tested all that and for it all to have fitted together first time was a great achievement for everyone who has put it together.

“It was a massive milestone completed for us.”

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
3 hours ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
1 day ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
9 hours ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
9 hours ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
9 hours ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
9 hours ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
9 hours ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
2 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
1 day ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
2 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
1 day ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
1 day ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
2 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
1 day ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
2 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
2 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
2 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
2 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
3 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
2 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
2 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
3 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
3 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
3 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
3 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
4 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
4 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
4 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
4 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
6 days ago

Contractor services