Keltbray completed the latest major demolition job at the former Ferrybridge ‘C’ Power Station in West Yorkshire on Sunday.

A single ‘blowdown’ saw the removal of the two chimney stacks, the main boiler house, and Bunker Bay.

At 198-metres high, the two chimney stacks were the tallest structures at the Ferrybridge site. This blowdown follows the successful demolition of a cooling tower at the site in July 2019 and four further cooling towers in October of the same year.

Keltbray carried out the blowdown using controlled explosives, with a 250-metre exclusion zone being put in place to ensure safety. In addition, nearby homes were evacuated for a short time with Keltbray and site owner SSE engaging with residents throughout.

Bobby Ellis, Keltbray Senior Project Manager, Demolition & Construction said: “This morning’s blowdown was a success. The demolition was months in planning and marks another major milestone in history, not only in Ferrybridge but in the UK in general.

“Keltbray is committed to being considerate to the communities in which we operate. As well as engaging with local residents, we put in place comprehensive ground monitoring to ensure the surrounding structures were unaffected by the blowdown, and we’re pleased to report that the activity went ahead safely and efficiently.

“The demolition activities are part of SSE and Keltbray’s ongoing commitment to be low-carbon and focus on renewable energy, in line with the UK’s ambition for net zero carbon emissions by 2050. I’d like to say a massive well done and thanks to the project team for all their hard work. Also thanks to the local community for their patience and cooperation.”

SSE Group Energy and Commercial Director, Martin Pibworth said: “This blowdown represents a major milestone in our decommissioning of Ferrybridge ‘C’ and is another special and poignant moment for the local community, with the power station playing a major role in so many people’s lives.

“As the UK looks to lead by example in tackling climate change, SSE is committed to driving the transition to a net zero future with a core focus on renewable energy, backed up by cutting-edge, low-carbon power stations.

“This latest blowdown was many months in planning, and we have worked closely with local residents, Wakefield Council, West Yorkshire Police, the Highways Agency and the Civil Aviation Authority to ensure a safe and efficient demolition.”

Latest news

Applicant numbers nosedive for construction vacancies

Recruitment market gets even more competitive - how the Enquirer can help
31 mins ago

Housing association shuts in-house modular factories

Swan closes loss-making steel frame and cross-laminate timber factories
2 hours ago

350-homes approved around iconic London Tube station

Housing blocks to be built around Grade II-listed Hounslow West Tube station
2 hours ago

Domis set for £195m Boddingtons Brewery scheme

Developer Salboy buys Manchester site to kickstart long-awaited 556 homes project
4 hours ago

John Lewis £500m funding deal to build 1,000 rental homes

Deal to advance BTR flats at store sites in Bromley, West Ealing and Reading
17 hours ago

Esh launches new housing retrofit division

Esh Retrofit Solutions will target market to improve the energy performance of social rented homes
3 hours ago

Eric Wright wins tricky £52m Liverpool transformation

Contractor working with engineers at Ridge and Partners on "challenging" Stanley Lock Flight site
3 days ago

Investment giant buys Bristol M&E contractor

RDCP Infrastructure acquires Avon Combined Electrical Services
3 days ago

Demolition start for £50m Farnworth town centre rebuild

Caddick Construction is tipped for main works due to start in the spring
3 days ago

L&G Modular strikes deal to build 1,000 affordable homes

Modular homes business teams up with Hampshire's Vivid housing association
3 days ago

Former Erith operations director joins John F Hunt

Scott Exell named new operations director at demolition specialist John F Hunt
3 days ago

Green light for £135m Leeds twin tower resi scheme

Construction to start in New Year on 500 build-to-rent apartments
4 days ago

Mace hits 1m tonnes carbon saving target for clients

Present work pipeline betters 2026 carbon emission saving target
4 days ago

Plans in for £40m surf park at former Kent colliery

Seahive surf lagoon and health resort will be built near Deal
4 days ago

Crushed demolition worker vows to return to industry

Shannon Brasier hoping to return to construction following horror accident
4 days ago

Mount Anvil to start 900-home North London estate rebuild

Planning approval paves way for Barnsbury Estate rebuild in Islington
4 days ago

Green light for major laboratory campus in Cambridge

Developer BioMed to tender first building on 600,000 sq ft lab complex in the New Year
4 days ago

Belfast firm signs the biggest work deal yet under Project Gigabit

Fibrus to hook-up rural Cumbria to lightning-fast broadband under £108m deal
4 days ago

McLaren wins Leeds logistics park contract

Work to start imminently on warehouse complex for Firethorn Trust
5 days ago

Work restarts on £683m waste power plant after site death

Construction suspended for a week of investigations following fatality
5 days ago

Demolition starts on £135m Wigan Galleries scheme

Contractor BCEGI starts work on project to redevelop Wigan town centre
5 days ago

Amey CEO to step down following private equity buyout

Amanda Fisher to leave once business is transferred to new owners
5 days ago

New body set up to vet plant operator card schemes

Contractor trades bodies unite to tackle competency concerns over plant operator skills cards
5 days ago

Kier leads switch to hybrid battery generators

Battery units work alongside smaller generators cutting run times by nearly 60%
5 days ago

Plans in for first Leeds co-living scheme

Watkin Jones submits plan to convert old Direct Line HQ into 230 studio flats
5 days ago

Demolition worker crushed by excavator

Court hears 20-year-old woman was left with "life changing injuries"
6 days ago

Government pays £700m for 50% stake in Sizewell C

New body, Great British Nuclear, will be set up to develop pipeline of nuclear projects
6 days ago

Costain wins Heathrow Airport asset renewal deal

Firm takes early contractor involvement role in Terminal 2 baggage handling upgrade
6 days ago

Worker killed on £683m waste power plant site

Fatal collision involving heavy goods vehicle on giant north London site
7 days ago

HS2 JV shifts four Wembley Stadiums of earth in record time

EKFB team digs and hauls 15 million cu m of muck in 20 months
6 days ago

Contractor services