Third of major rail enhancement projects stuck in sidings

Aaron Morby 1 year ago
Share

Around one-third of projects in the Government’s £10bn Rail Network Enhancements Pipeline have failed to advance in the three years since the 2019-2024 plan was published.

Growing concern about slippage of projects in Governments £10bn major rail enhancement project pipeline
Growing concern about slippage of projects in Governments £10bn major rail enhancement project pipeline

There is now deep concern among contractors and suppliers about slippage and a lack of official programme transparency.

Their trade body, the Rail Industry Association, has now taken the step of carrying out its own progress audit on the planned rolling programme of 58 enhancement projects, after the Department of Transport’s failure to publish annual progress updates as originally promised.

The Government initially committed £10.4bn for enhancements in CP6, but has since revised down this amount to £9.6bn. But the supply chain warns it is now operating in the dark about exactly which projects will progress and which will be delayed or cancelled.

The association warns that failure to publish any subsequent update has led to considerable rail supply sector uncertainty and concern.

RIA progress rating of 58 rail enhancement pipeline schemes


The RIA’s analysis shows that there has been significant progress on many of the RNEP schemes, with 18 progressing towards design, delivery or completion.

But it warns the 19 red and 21 amber entries highlight the significant uncertainty around the vital programme and the need for Government to issue an update on the status of these schemes.

RIA’s rough analysis shows that about £6bn has been spent or announced so far, including £2.9bn allocated for the Transpennine Route Upgrade but not the full £9bn-11.5bn estimated to be required for the entire project.

Association chief executive Darren Caplan said: “It’s three years since the first and last publication of the Rail Network Enhancements Pipeline, despite the Government committing to publish an annual update. This has led to a lack of visibility for rail suppliers, who are simply looking to plan and invest in their businesses and workforces to conduct the work.

“While we are all aware there are difficult economic times ahead, as well as increased pressure on public spending, RIA and our members are simply asking for visibility on what the Government is planning on rail enhancements projects – we are not lobbying on budgets.

“It is welcome that many RNEP projects are actually being completed or progressing, but a clear matter of concern that there has been no update on almost half of these schemes since 2019.”

 

Latest news

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
8 hours ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
12 hours ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
1 day ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
12 hours ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
10 hours ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
11 hours ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
1 day ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
11 hours ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
1 day ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
1 day ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
2 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
2 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
2 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
2 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
2 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
2 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
2 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
2 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
3 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
2 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
3 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
3 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
2 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
3 days ago

Wates-owned SES restructure delivers record profit and revenue

Building services contractor revenue soars to almost £300m
3 days ago

25 groundworks firms win £100m Places for People deal

M&J Evans, Carmac and Churngold Construction feature in housing association's line-up
3 days ago

Energy efficiency firms angry at lack of CITB support

SME contractors funding bid "does not meet the current criteria for supporting productivity or EDI"
3 days ago

£400m South Cambridge science park approved

Outline approval allows former sewage treatment works to be demolished
3 days ago

McLaren gets green light for 45-storey Leeds tower

Landmark Wellington Square scheme will see 464 flats built with 360,000 sq ft of offices
6 days ago

Heavy rain causes 1.9% construction output fall

Hopes remain undampened of a resi-led recovery this summer
6 days ago

Contractor services