Giant HS2 viaduct deck slide breaks records: Video

Grant Prior 1 year ago
Share

HS2 has released new timelapse footage showing engineers completing the heaviest and longest single-stage viaduct deck slide on the project so far.

The four-day operation – which was completed on Sunday – involved sliding the 4,500 tonne deck across a road and railway line near Wendover in Buckinghamshire.

Stretching for 345m, the Small Dean viaduct is one of 50 major viaducts on the HS2 project.

Its concrete and steel deck was assembled to its full length before the slide began with most of the precast concrete deck slabs installed in advance of the launch. This increased the weight of the slide but will save time during the later stages of the project.

The whole operation was the heaviest and longest slide of a signal-stage viaduct deck on the HS2 project so far. The A413 was reopened at around 8.30pm on Friday, nine hours ahead of schedule.

During the slide, special pads covered in PTFE – a Teflon-like material usually found on the surface of a non-stick frying pan – were used to minimise friction between the deck and the temporary steel bearings on top of each of the piers. A cable system was used to slide the deck forward at speeds of up to 10 metres per hour.

HS2 Ltd Project Manager, Jason Bicknell said: “Small Dean is the longest continuous deck slide on the project and an amazing engineering achievement. But it would not have been possible without the huge amount of preparatory work put in over the last few years and I’d like to thank everyone involved. Two years ago, we set a target to install the deck in summer 2025 and it’s great that we came in ahead of schedule.”

Before the slide could begin, the team spent four years preparing the site, diverting utilities, realigning the road, building the abutments and six piers that support the viaduct and assembling the deck.

With the deck now in position, engineers can begin the challenging job of lowering it by 60cm onto the permanent bearings which will support the full weight of the viaduct. The two-month long operation will see it carefully lowered by 20cm at a time, pier-by pier, until the whole deck settles into its final position.

The viaduct is one of only two places in the Chilterns where the HS2 route will be above ground level, with the underside of the viaduct just 6m above the road, supported by the huge Y-shaped piers.

Like the nearby Wendover Dean viaduct, Small Dean’s enormous deck is made from weathering steel, which naturally ages to a characteristically dark russet finish to echo the natural tones of the surrounding landscape.

Both viaducts have innovative ‘double composite’ structures, with layers of reinforced concrete on the top and bottom to create a much more structurally efficient box-like span which dramatically cuts the amount of embedded carbon in the design.

In a nod to the great railway bridges of the Victorian age, the side of the Small Dean beam features prominent deck stiffeners which help to manage the structural forces while allowing for a more structurally efficient span.

The viaduct is being delivered by HS2 Ltd’s main works contractor, EKFB – a team made up of Eiffage, Kier, Ferrovial Construction and BAM Nuttall – working with their design partner, ASC (a joint venture between Arcadis Setec and COWI). They worked closely with a team from Network Rail to plan and deliver work close to the railway.

Martin Gamble, EKFB’s Senior Project Manager said: “The team at Small Dean Viaduct has worked tirelessly over a number of years to prepare for this momentous event. Through careful planning and by implementing time-saving measures, we’ve accelerated the bridge and support construction, bringing the launch date forward.

“The complexity of the interfaces with the road and railway have provided a real challenge which, with the assistance of Network Rail and Buckinghamshire Council, we have risen to and overcome, while keeping disruption to the surrounding area to a minimum.”

Latest news

Plan for 240 flats at Nottingham Station gateway site

Blocwork, Platform 4 and Grainger target station-side brownfield plot
3 hours ago

Watkin Jones clears Gateway 2 for Bristol student halls

201-bed Temple Quarter scheme starts on site
2 hours ago

Police swoop on site safety test centre

Four arrested after probe into suspected payments to pass safety tests
19 hours ago

Fit-out firm Artemis files administration notice

Court papers lodged by £21m-turnover specialist
10 hours ago

Former Carillion chief Richard Howson fined £237,000

Group chief executive fined for "misleading statements"
24 hours ago

£100m Eden Project Morecambe gets green light

Councillors back halved-size scheme with two domes and 2028 opening target
10 hours ago

Ferrovial bags £80m Slough sewage works revamp

JV with sister company Cadagua to start construction early next year
11 hours ago

Battersea Power Station masterplan reset for final 16 acres

Architect hired to unlock 3.2m sq ft in riverside redevelopment endgame
10 hours ago

Graham clinches £286m Manchester student scheme

Contractor to deliver 2,300-bed campus rebuild for MMU
1 day ago

Chippenham £50m town centre reset go-ahead

Emery Gate shopping centre to be transformed with 225 homes
1 day ago

Green light for Italian plaster factory in Derbyshire

Fassa Bortolo picks old Stanton Ironworks site for new UK headquarters
1 day ago

Gateway 3 delays leave legacy homes still empty

Decisions on 44 schemes containing 5,594 flats still outstanding
2 days ago

Contractors wanted for £75m coastal civils deal

Portsmouth city council to hold bidders day ahead of April tender race
1 day ago

MTX signs deal for health campus near Cardiff

Offsite construction specialist appointed under PCSA as work set to start on site later this year
1 day ago

HBC breaks ground on £24m Sheffield co-living scheme

Hive 100 studio flats project starts in Kelham Island
1 day ago

Cheshire M&E specialist Gilks files administration notice

Management tells staff firm will close days before salaries due to be paid
4 days ago

Severfield facing strike action next week

Industrial action to hit Bolton factory
5 days ago

Jackson wins race for £22m East Sussex bridge

Construction set-to start on Exceat Bridge replacement
4 days ago

Plans ramp-up for Wythenshawe £500m town centre revamp

Food hall latest phase of Manchester regen
4 days ago

Kier set to bag £35m Bristol station car park job

Seven-storey MSCP will free up land for homes at Bristol Temple Meads
4 days ago

Leeds £1bn Eastgate Quarter vision moves up a gear

Consultant team assembled for Leeds’ last big city centre site
5 days ago

Morgan Sindall eyes bumper 2026 on record workload

High-flying fit-out arm triggers another profit upgrade
5 days ago

Funding agreed for £220m Paddington overstation job

Mace lined-up to start main construction works next month
5 days ago

Salford set for record £525m wastewater reset

United Utilities alliance firms gear up to deliver twin wastewater works upgrades
5 days ago

Construction grew 1.8% last year despite sharp Q4 fall

Private housing slump behind 2.1% output fall in final quarter
5 days ago

Firms fined after two killed when MEWP overturns

Tragedy during testing of warehouse racking system
5 days ago

Hill bags £45m Kent high-rise flats job

Firm beats rival Higgins and Lovell to Springfield Library redevelopment
5 days ago

Willmott Dixon gets start date for £43m Kent leisure job

Spring start for Gravesend Cascades Leisure Centre
5 days ago

D-Day for £37bn NHS hospital framework

Winners due to be announced imminently for mega deal
6 days ago

Severfield hires ex-ISG finance chief to steer turnaround

New CFO Andrew Page joins at “pivotal time” for steel specialist
6 days ago