Safety Regulator misses deadline to clear Gateway 2 backlog

Aaron Morby 2 weeks ago
Share

The Building Safety Regulator has missed its target to clear the backlog of Gateway 2 approvals by April, stalling the start of dozens of high-rise residential projects across the country.

Latest figures reveal that over two-thirds of Gateway 2 applications transferred to the BSR last autumn remain unapproved, despite earlier assurances from officials that the logjam would be resolved by now.

The delays are beginning to impact project financing, with banks pulling back from the high-risk building sector.

One bank told the Enquirer it had been forced to reassess its exposure to schemes stuck in the approval process.

“With these delays holding up projects, we’ve reassessed our risks and, like other banks, are stepping away from the high-rise residential market,” a spokesperson said. “There are simply easier, less risky investment options elsewhere.”

The backlog stems from the withdrawl of private building control firms Assent Building Control and AIS Surveyors last autumn, which resulted in 45 in-flight applications being handed to the BSR.

These complex schemes were blamed for creating the bottleneck in Gateway 2 approvals needed to start construction.

In February, Philip White, HSE Director of Building Safety, told the Enquirer that the backlog would be cleared by April. However, more than six months later, only 14 of the 45 projects have been approved.

A further 10 projects seek Gateway 3 approval—required before occupation—but just one has been cleared.

Gateway 2 applications transferred

  • 45 applications
  • 14 approved

Gateway 3 transferred

  • 10 applications
  • 1  approved

A spokeswoman for HSE said: “We acknowledge there have been delays to processing approvals for building control applications and we are working to put this right.

“A backlog of complex in-flight higher risk projects which came into BSR after the collapse of private registered building control approver AIS Surveyors initially drove up processing times.

“However as of February, following increased resourcing and new processes, processing time for new more complex, higher-risk building projects under Gateway 2 has decreased to an average of 16/17 weeks.

“Handling time for lower-risk category B projects is also now down to around 10 weeks. “

She added: “Outside of the backlog there are a small number of highly-complex ‘in build’ transitional cases which are not yet of a sufficient standard to be approved.

“We are taking a pragmatic approach to these cases to make sure building work can continue.

“We are confident that all the operational contingency measures we’ve put in place, including dedicated support from industry will also allow us to clear the applications in the backlog as we head into the new financial year.

“We also expect the handling time for new applications to continue to reduce as the operational contingency measures have impact.”

Latest news

Willmott Dixon wins Great Yarmouth waterfront deal

North Quay 10.5 acres mixed-use scheme to advance
18 hours ago

Care home fire trial collapses

Prosecution withdrawn against four firms including Morgan Sindall Property Services
18 hours ago

Eight take key spots on £250m Prosper framework

Housing and public building upkeep deal for North East awarded
18 hours ago

McLaren storms April contracts league with flurry of wins

Cardiff Bay Arena job headlines a series of big contract wins
22 hours ago

Balfour Beatty lifts cash forecast after strong first quarter

Contractor set to hit £1bn average monthly net cash in 2025
22 hours ago

Goldman Sachs-owned Adler & Allan buys 180-strong civils outfit

West Country's Glanville Environmental gets new owner
22 hours ago

Caddick lands first contract for £200m Skelmersdale revamp

Developer gets green light for masterplan
23 hours ago

Van Elle sells HGV fleet to haulage firm

WS Specialist Logistics pays £2.9m to take on fleet and drivers
22 hours ago

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
2 days ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
2 days ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
2 days ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
2 days ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
3 days ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
2 days ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
2 days ago

Early call-out for Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
2 days ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
3 days ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
3 days ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
3 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
3 days ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
3 days ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
3 days ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
1 week ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
1 week ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
7 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
7 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
1 week ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
1 week ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
1 week ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
7 days ago

Contractor services