Completed buildings caught-up in Gateway 2 chaos

Grant Prior 3 weeks ago
Share

The backlog of Gateway 2 safety approvals stalling work across the country is also hitting some schemes where work is almost complete.

The Enquirer has been contacted by one developer who faces “losing millions” after the Building Safety Regulator (BSR) decided its scheme would need to go through pre-construction checks despite being almost structurally complete.

The firm has now been forced to write to buyers explaining why their flats are delayed and faces sales collapsing.

The residential block came under the control of the BSR last April after the original building control firm was found to be non-registered.

Construction was well advanced with most of the scheme structurally complete by the end of last year.

The developer said the BSR “took months” to acknowledge its scheme and only sent an adviser to the site last November when most of the structure was complete and the Building Warranty provider was already doing final sign-off inspections.

The developer said: “Despite that the BSR decided that we still needed to go through the regulatory process for Gateway 2 even though the job is at the point of buyers nearly moving in.

“We had quite rightly believed that we were in Gateway 3 as construction had completed and we were at the stage of Building Control sign-off.

“We have been ignored and messed around for months then hit with this and our construction team is totally confused how to get this project over the finish line.

“I’ve spoken to other developers in a similar  situation and it’s total chaos thanks to a system which just isn’t working at the moment.”

 

Latest news

Groundworks firm Corbyn goes under

£33m-turnover specialist now in hands of administrators
1 day ago

Home office says sorry to FP McCann after site raid

Precast concrete contractor wins damages over "entirely erroneous and unfounded allegation"
1 day ago

Race on for £60m London Gateway container yard job

Civils and M&E job up for grabs at Berth 5
18 hours ago

How Construction Enquirer can boost your business

Promote your business to a vast industry audience
18 hours ago

Plans in for 3m sq ft Warwickshire logistics park

Thrive Park to deliver £343m in construction investment
18 hours ago

Bouygues go-ahead for South London estate rebuild

Nearly 300 flats to be build in Tustin Estate phase two
18 hours ago

Court ruling opens floodgates for legacy defect claims

Barratt wins test case unlocking 30-year defect claims on sold buildings
2 days ago

Morgan Sindall wins Crystal Palace sports centre revamp

Major upgrade to iconic South London venue
2 days ago

Bowmer + Kirkland to build Manchester office block

Commercial scheme to kickstart Mayfield Park development
2 days ago

Design team named for £1bn rebuild of Airedale Hospital

Construction set to start in 2027 to 2028 on Keighley hospital replacement
2 days ago

Vistry secures 600-home Sunderland scheme

Work to start early next year on new Sheepfolds neighbourhood
2 days ago

Bilfinger bags National Gas compressor stations deal

Contract will create up to 100 jobs during construction phase
2 days ago

Saint Gobain to build new stone wool insulation factory

Construction to start next year at Melton Mowbray site
3 days ago

United Living acquires civils firm Peter Duffy

Contractor gears-up for AMP8 investment round
3 days ago

Wates calls for PFI reboot to unlock schools and hospitals

Firm sets out fresh model for private cash in public projects
3 days ago

Strabag targets £1bn UK turnover by 2028

Austrian civils contractor ramps up UK push with HARP and HS2 pipeline
3 days ago

Training reform row splits scaffolding sector

Changes planned to the Construction Industry Scaffolders Record Scheme
3 days ago

BBV gears up for big HS2 viaduct slide over M6

First 119m viaduct section set to slide into place in June
3 days ago

Council terminates Spencer bridge repair contract

Delays have hit restoration of Grimsby’s historic Corporation Road Bridge
3 days ago

Liverpool unveils £850m highways framework line-up

Graham, Sisk and Wright land spots on city road improvement deal
3 days ago

Tender price rise forecasts downgraded as market stalls

Schemes stall as clients drag feet on project starts
3 days ago

Westminster gears up for £500m housing repairs deal

Council eyes multiple strategic alliances for major housing overhaul
4 days ago

Henry Boot sets October start on £1bn cyber hub next to GCHQ

160,000 sq ft IDEA office building starts 10-year build plan
4 days ago

Cementation Skanska names new operations director

Emma Haddow now heads up UK-wide ground engineering services
4 days ago

Forterra fires-up kilns as house building demand returns

Materials giant boosts production of bricks and concrete floor beams
4 days ago

Plans in for £100m Church Wharf regeneration in Bolton

Developer Watson submits plan for over 400 homes and 130-bed hotel
4 days ago

McAvoy on the hunt for new subcontractors

Meet the Buyer event in Manchester next month: Register now
4 days ago

Ex-Lendlease boss seals £24bn Crown Estate mega sites JV

Crown Estate/Lendlease alliance to build out at Euston, Silvertown and Thamesmead sites
5 days ago

Brookfield gets green light for latest City office scheme

Retrofit-first approach will retain 70% of the original structure at 1 Moor Lane
4 days ago

Knauf commits £170m to build Deeside insulation plant

Work to start next year at former Shotton steelworks site
5 days ago

Contractor services