HS2 first as giant bridge slid across live motorway

Grant Prior 1 day ago
Share

HS2 engineers claimed a UK-first over the weekend when they successfully slid a 4,600-tonne viaduct across the M6 without closing the motorway.

The 17 hour-long operation was the culmination of an epic three-stage process to assemble and install the 315-metre East deck of the M6 South viaduct, which will carry high-speed trains heading to Birmingham and further north.

While the previous slide had required a weekend closure of the main carriageway, the team – led by HS2’s main work contractor Balfour Beatty VINCI (BBV) – worked closely with National Highways to develop the ‘fully restrained’ process which allowed them to safely slide the final section above the moving traffic.

It is thought to be the first time this technique has been used on a UK motorway.

To deliver this, they initially closed the M6 overnight between Junctions 4 and 5 on Thursday 11 December to shift the viaduct slightly forward by twelve metres. This was to ensure that both ends of the enormous beam were fully supported on concrete piers during this weekend’s slide.

The viaduct was then pushed the rest of the way across the busy motorway on Saturday at a speed of 13 metres per hour, with only the M42 slip closed during the weekend.

The successful operation means the project to construct the M6 South viaduct has reached the halfway point. Over the next year, the same process will be repeated, with a parallel West deck slid into position alongside the first one to carry trains heading south.

Caroline Warrington, HS2 Ltd’s Head of Delivery, said: “Along the HS2 route we are pioneering new approaches to engineering and construction in order to deliver more efficiently and with less impact on our neighbours.

“We believe this fully restrained slide was a first for the country, but most importantly it means we’ve been able to cut in half the number of times we’ve had to close the motorway. I’d like to thank everyone who worked so hard to make the operation a success.”

Mark Wild, HS2 Ltd’s Chief Executive, is currently leading a comprehensive reset of the programme – making sure the new railway is built as efficiently as possible and for the lowest reasonable cost. Over the last year, HS2 has focused on safely boosting levels of productivity across the construction programme.

The M6 South viaduct has been designed in stages to increase efficiency and reduce disruption for motorists. Each section is assembled to one side before being pushed out over the motorway, with the next section added behind it.

In the latest phase, the team moved the viaduct using a series of winches, known as strand jacks. To reduce friction, the structure was slid across non-stick pads, using a material usually found on the surface of a household frying pan.

Russell Luckhurst, the BBV engineer leading the delivery of the works, said: “We’re all feeling a huge sense of pride after sliding a 4,600-tonne viaduct into its final position this weekend. The third and final slide of the East deck viaduct was delivered over a live motorway for the first time in the UK, making this achievement even more special.

“Using this ‘fully restrained’ technique meant we were able to keep disruption to an absolute minimum. Our focus will now turn towards the neighbouring West deck viaduct, which will be launched in multiple phases throughout 2026, as well as the East deck finishing works.”

Each viaduct is formed of a hollow double-box structure made of weathering steel. The steel boasts a natural protective layer of oxidisation which gives it a characteristic ‘rusty’ appearance and reduces maintenance by eliminating the need for regular repainting.

Four pairs of concrete piers support the viaducts with the tallest one measuring 9.9m in height. A 4.5-metre-high parapet will be installed on the side facing Chelmsley Wood to reduce noise and disturbance from passing trains.

The viaduct was launched with 82 precast slabs already installed on top of the steel structure. This will further reduce the number of road closures in the future, to complete the viaduct deck works.

The structural design has been carried out by Balfour Beatty VINCI’s Design Joint Venture (DJV), made up of Mott MacDonald and SYSTRA, plus WW+P Architects.

Latest news

Springfield strikes deal to build homes for power workers

House builder signs first four-year lease deal to house workers on Scottish grid upgrade
8 minutes ago

Planning reboot could spare SMEs from Building Safety Levy hit

Government unveils new ‘medium site’ category of 10 - 49 homes with potential Levy exemptions
46 minutes ago

Hunt starts for Square Mile £4bn heat network developer

City of London aims to lock in single development partner for decades-long decarbonisation push
28 minutes ago

Steel fixer crushed by blockwork wall collapse

Contractor fined £100,000 after worker suffers life-changing injuries
19 hours ago

Conlon Chairman to retire after 38 years

Michael Conlon to hand over reigns to Guy Parker at Employee Owned Company
21 hours ago

Cala names industry veteran Tom Nicholson as new CEO

Former Crest and Linden boss to steer house builder through choppy 2026 market
16 hours ago

Yorkshire brickmaker saved in last-minute rescue deal

Private equity deal saves 20 jobs at York Handmade
19 hours ago

HS2 first as giant bridge slid across live motorway

Watch timelapse footage of pioneering 4,600-tonne viaduct installation
1 day ago

Gilbert Ash breaks ground on £120m Wilde aparthotel

Staycity’s biggest London scheme gets underway in Shoreditch
1 day ago

Bennett wins brace of retirement home deals

Contractor to build more than 200 apartments for investor Octopus Capital
1 day ago

Developer showed “total disregard” for site safety

Property firm fined £45,000 for failing to meet basic standards
1 day ago

Watkin Jones takes £8.7m hit but eyes brighter 2026

A £2bn pipeline and stronger deal flow help rebuild confidence after a year of impairments
1 day ago

Project manager caught running false invoice scam

Suspended sentence and ban for director after probe into offices to resi scheme
2 days ago

Cardo nails £52m Sussex council homes roofing deal

Firm beats 14 rivals to take Lewes and Eastbourne roofing programmes
2 days ago

Bachy turnover sinks by over £100m as HS2 surge fades

Piling specialist reports slow year as mega projects step down
2 days ago

Van Elle finds buyer for loss-making Canadian arm

Two-year North America foray ends with £2.6m exit deal
2 days ago

£100m student halls to replace derelict London Crown Court

IQ student project gets go-ahead at Blackfriars court building site
2 days ago

Safety green light for Newcastle student scheme

Gateway 2 approval process delays construction start by a year
2 days ago

Plans go in for next phase of Manchester Waters

New neighbourhood planned for island site
2 days ago

JRL names new fit-out lead to drive expansion

Graham Ardley steps up to drive next phase of commercial and residential growth
2 days ago

Construction output yo-yos as growth falters again

Quarterly output down 0.3% amid cautious investor sentiment
5 days ago

Free school build plans axed to fund £3bn SEND expansion

Education secretary scraps 28 free schools to plug SEND shortfall
5 days ago

McLaren seals £160m funding for Manchester student tower

737-bed Upper Brook Street student scheme forward funded by L&G
5 days ago

Former McAlpine boss lined up for Royal BAM board role

Paul Hamer to replace Paul Sheffield on Dutch group supervisory board
6 days ago

Plans go in for £650m retail park to resi scheme

Construction could start in early 2027 on new neighbourhood for Lewisham
6 days ago

Lovell launches Midlands refurb division

Renew Central to be headed by Carl Yale
5 days ago

M Group muscles into top five contractors after growth spurt

Private-equity backed infra giant builds £8.8bn work mountain
6 days ago

Plans in for first major build phase of £2bn York Central scheme

Developers table plans for nearly 1,000 homes, parkland and York’s new western station gateway
6 days ago

Lords push for staged Gateway 2 approval to aid design and build

Inquiry warns BSR’s over-detailed Gateway 2 demands are freezing D&B process
6 days ago

CITB wage bill tops £52m as staff numbers jump 13%

Accounts show 182 people at training body earn £60,000+ a year
6 days ago