East West Rail reset plan to speed up construction

Aaron Morby 7 hours ago
Share

East West Rail has unveiled a major delivery reset to accelerate its £5bn–£6bn construction programme by switching from a traditional sequential build to parallel delivery across multiple sections.

Bedford station rebuild to be delivered earlier than first planned
Bedford station rebuild to be delivered earlier than first planned

The move, revealed in its latest consultation, will see key packages of work brought forward and delivered at the same time rather than waiting for earlier phases to complete – a shift designed to cut programme risk and bring earlier benefits to passengers and developers.

Under the previous model, the railway would have been delivered in stages linking Oxford to Cambridge in sequence. The new approach instead breaks the route into live construction packages that can progress independently and open as they are finished.

Key packages being accelerated


Marston Vale line upgrade
Track, electrification and infrastructure works between Oxford and Stewartby will be brought forward to enable four trains an hour by the early 2030s. This section becomes the first major operational spine of the route.

Bedford station rebuild
A full redevelopment including new platforms, a western entrance and transport hub upgrades will now be delivered earlier to create a central interchange and unlock onward phases.

Tempsford new station and interchange
The proposed East Coast Main Line interchange will start around 2030 – five years earlier than planned – supporting a new town and future east-west and north-south connectivity.

Cambridge upgrades and new stations

Works including Cambridge East station and network enhancements will be accelerated to integrate with existing services ahead of full route completion.

Stewartby station for Universal resort

A new station on the Marston Vale line will be prioritised to support the proposed theme park and drive early passenger demand.

Crucially, parts of this work will be delivered ahead of the full Development Consent Order, allowing enabling works, station upgrades and track improvements to start earlier and run in parallel with the main consent process.

The reset also locks in higher capacity from day one, with provision for up to five trains an hour and longer trains, alongside hybrid battery-electric rolling stock to reduce upfront electrification costs and simplify delivery.

Chief executive David Hughes said: “These updated proposals mark a major step forward for East West Rail to help ensure communities see the benefits of the project sooner as we finalise the design. Faster delivery, more frequent services and new stations will help unlock housing, support new jobs and attract investment.

“By bringing forward key elements of the railway and planning for increased demand, we are helping to ensure the infrastructure is in place to support future growth and opportunities for our communities.”

Rail minister Lord Peter Hendy added: “East West Rail will unlock the potential of the Oxford-Cambridge Growth Corridor, providing greater connectivity across the region and delivering on our Plan for Change mission to drive economic growth, jobs and homes.”

Consultation on the reset runs until June 9 ahead of a Development Consent Order submission in 2027, with early works expected to begin ahead of phased openings through the 2030s.

Latest news

Vistry agrees deal for next 1,000 homes at Northstowe

Contract with Homes England for next phase of new community
21 minutes ago

East West Rail reset plan to speed up construction

Delivery plan switches from sequential build to parallel construction packages
7 hours ago

Muse installs national ops chief to deliver £6.3bn pipeline

North West boss steps up as firm shifts focus from pipeline to construction
7 hours ago

MCS Group lands £22m Walsall warehouse deal

Speculative scheme to start in May
7 hours ago

Avove hits 6.9% margin as growth streak continues

Utility contractor profit hits £17m in 4th year of growth
8 hours ago

Apex lands £15m Medway Council HQ overhaul job

Council presses ahead with HQ rescue after RAAC shut sections
7 hours ago

Network Rail lines up £450m Scotland electrification deal

Single contractor sought to deliver OLE, power and design work across eight-year programme
8 hours ago

Eurotunnel fined £2.25m after surveyor hit by lighting

115kg lighting carriage fell during winching operation
1 day ago

Willmott Dixon final sign-off on Forest of Dean leisure job

New builder gets start date after BAM exit from Five Acres community hub project
8 hours ago

Bovis swings back to profit after Atlas takeover reset

£35m provision cover drives turnaround following carve-out from Lendlease
1 day ago

McAvoy go-ahead for £65m Bradford hospital overhaul

Modular specialist to start Lynfield Mount mental health hospital rebuild
1 day ago

Vistry promotes from within to succeed Greg Fitzgerald

Adam Daniels to lead house builder
1 day ago

Renaker profit climbs after bumper year of tower completions

Manchester tower builder completes 2,796 beds and flats in record handover year
1 day ago

Rolls Royce signs small nuclear plants contract

Deal inked to deliver next generation of Small Modular Reactors
1 day ago

MPB builds £160m pipeline as public sector pivot pays off

Cash and margins up as private market exposure cut
1 day ago

Downing Construction sinks deeper into loss

Liverpool contractor hit by falling workload and mounting Building Safety Act provisions
1 day ago

Mace tops March contracts league after big office win

London South Bank office project lifts firm to pole position
4 days ago

Barratt Redrow and PfP team up for 8,500-home garden town

JV lines up six-village garden town at Gilston in Hertfordshire
5 days ago

Government gives £380m grant to Agratas gigafactory

Public money towards construction of UK’s largest electric vehicle battery manufacturing facility
4 days ago

Guildmore hires United Living retrofit chief

Ben Whiterod joins London builder to drive growth in housing decarbonisation
4 days ago

Plans go in for first phase of 1.6m sq ft Mix Manchester

First submission at UK’s first airport-based science, innovation, and manufacturing campus
5 days ago

Strabag swoops to buy piling specialist Van Elle for £59m

Board of Van Elle backs takeover offer at 59% premium to share price
5 days ago

Red revamps group structure in push for growth

New London and East divisions plus luxury hotel business
6 days ago

Plans in for 814-home Salford waterfront scheme

Manchester developer Forshaw lodges triple resi tower Irwell plan
5 days ago

Guildmore in line for £60m London leisure and flats job

Bromley builder beats Morgan Sindall to deliver Tower Hamlets rebuild
5 days ago

Building safety regulator moves to unblock cladding fix backlog

New taskforce and lower caseloads aim to speed delayed high-rise remediation approvals
6 days ago

Erith lifts turnover as staff bonus pool tops £6.4m since 2017

Employee-owned demolition firm balances growth with margin squeeze
6 days ago

Manchester tower deal finally unlocked after four-year stall

£860m public-private fund steps in to kickstart 107-flat Ferrous scheme
6 days ago

Buyers report construction cost surge

Output down and material costs up shows latest survey
6 days ago

United Infrastructure exits housing with MBO of homes arm

Group severs long-standing house building link to double down on energy and infrastructure
6 days ago