The start of Phase 1 of the scheme follows nine months of pre-construction works undertaken in close collaboration with developer Freshwater, which included the demolition of the existing 11-storey building and extensive enabling activities to prepare the site for the redevelopment.
Hunt’s latest package includes the construction of a single basement together with public realm improvements, including a new plaza and associated hard and soft landscaping running to January 2027.
Paul Bland, Chief Executive Officer of John F Hunt Limited, said: “The start of piling marks the next stage in the delivery of the Tenter House development.
“Having completed the pre-construction programme, our focus is now on progressing the works while continuing to coordinate closely with developers Freshwater, project managers Buro Four, cost consultants Exigere and the wider project team.”
McLaren signed a PCSA for the main construction contract for the 21-storey scheme last year.