The 132kV Laleham to Twickenham replacement project involves the removal of 45-year-old gas compression cables and replacement with pipe type cables utilising the existing steel ducts.
It will ensure improve electricity supplies to around 150,000 customers fed from Twickenham Grid substation.
Work on the 11.5km stretch is due for completion in September 2011.