Crossrail tunnel bids offer hope of big savings

Aaron Morby 15 years ago
Share

Big savings in estimated tunneling costs are expected to help Crossrail save hundreds of millions from its £15.9bn budget.

Today Crossrail highlighted the progress made on the project ahead of sending its latest delivery cost estimates to Government before the end of the year.

Crossrail also confirmed that the value management exercise did not involve scrapping stations or reducing the lines planned between Maidenhead and Heathrow in the west and Shenfield and Abbey Wood in the east.

Over the coming twelve months all the major station and tunnel contracts will be awarded and work will get underway at other sites along the Crossrail route.

The firm said that bids for two of the three main tunneling contracts were being evaluated and contained “some innovative proposals that could deliver increased value for money”.

Nearly £2bn has been invested in the Crossrail project to-date including the costs of getting Parliamentary approval for the Crossrail Bill.

Now over 2,500 people are now employed on the Crossrail project – 300 directly by Crossrail.

Up to 14,000 people will be employed at the height of construction between 2013 and 2015.

Terry Morgan, Crossrail Chairman said: “Crossrail and its delivery partners recognise fully that Crossrail is a significant investment.

“Crossrail is bearing down on its whole cost base, while ensuring delivery of a new railway that is fit for purpose and delivers the capacity improvements required.

“We are looking at every aspect of Crossrail to identify where efficiencies can be made and understanding what cost saving lessons can be learned from other global infrastructure projects.”

The latest Crossrail business case shows that Crossrail is now more important to the UK economy than ever before – delivering a boost of up to £42bn.

Previous estimates were that Crossrail would be worth up to £36bn to the UK economy.

Cost control measures so far

  • Whitechapel station completely redesigned to deliver a far better station, £30m below original estimates.
  • Canary Wharf station redesigned to drive down costs.
  • Crossrail is closely studying latest demand forecast numbers to ensure the new stations are appropriately sized. It is essential that savings are not made that turn out to be false economies decades later
  • Crossrail has let a design contract to ensure that common components such as light fittings and platform indicators are used wherever possible on central route stations
  • To deliver the Crossrail branch to Abbey Wood, a major part of construction work reuses old rail infrastructure including the Connaught Tunnel on the former North London Line branch to North Woolwich
  • New Crossrail trains will be based on tried and tested designs

Latest project news

Willmott Dixon starts £30.5m Derbyshire police cell-block

Three-storey Chesterfield custody suite will contain 36 cells
4 months ago

McLaren confirmed for £250m Cardiff arena

Robertson Property secures planning green light for 16,500-capacity venue
5 months ago

Green light for £10bn data hub prep works in Northumberland

Enabling works to roll out over 16 months on former Blyth Power Station site
5 months ago

B+K to start £50m rebuild of Northumberland school

Cramlington Learning Village redevelopment contract signed off
5 months ago

Strabag seals financial close for £3bn HARP project

Work to start next year on North West's Haweswater aqueduct upgrade
5 months ago

Latest contract winners in military living revamp

First phase sites allocated under new approach to Single Living Accommodation
5 months ago

Cruden gets green light for Edinburgh housing job

Construction to start later this year to transform vacant 1950s building
5 months ago

Plans in to transform former GSK London HQ with 2,300 homes

Landmark 13-acre scheme set to transform Brentford Great West Road campus
5 months ago

Farrans to build new £59m Paisley bridge

Work to start soon on transport project for Renfrewshire Council
5 months ago

Henry Boot gets green light for 2,500 new homes

Hallam Land division sees signs planning system is speeding-up
5 months ago

Wates inks £100m deal on first new-design prison houseblocks

HMP Onley expansion leads roll-out of new standardised design
5 months ago

McLaren lands Heathrow logistics deal

1.6 hectare airport site to be transformed into modern warehouses
5 months ago

Mace lands latest 30-storey City of London tower

85 Gracechurch Street near Leadenhall Market to be transformed
5 months ago

Oxford United win green light for £150m all-electric stadium

Planners back 16,000-seat Kidlington ground with hotel, plaza and community hub
5 months ago

Hitachi Energy named for EGL3 converter station deal

Firm to build major HVDC converter stations in Aberdeenshire and West Norfolk
5 months ago

Vistry to deliver 2,300 homes at Rugeley power station site

139-acre brownfield site has already been extensively remediated
5 months ago

Andrew Scott wins role on Swansea’s next big office build

Contractor appointed for detailed design of 800-desk city centre hub.
5 months ago

Knights Brown to start £29m Poole flood wall job

1.5km barrier to protect homes and unlock regeneration plans
5 months ago

Kier lands £16m first ECI job with Southern Water

Design deal covers nitrogen cut and UV upgrade at Hampshire wastewater sites
5 months ago

Watkin Jones seals deal on 200-bed student scheme

Bristol project will involve four brick buildings rising to seven storeys
5 months ago

Kori lands latest £17m care home contract

Work to start on site in south west London next month
5 months ago

£70m Bristol student job finally gets Gateway 2 approval

Student developer Unite to progress two big schemes
5 months ago

McLaren lands London School of Economics £100m revamp

Central London job will be largest Passivhaus retrofit building in the UK
5 months ago

Clegg wins car park to flats conversion contract

Work to start this autumn on transforming multi-storey car park into flats
5 months ago

Go-ahead for major retrofit of former London De Beers office

Mace advised on pre-planning construction plan for Hatton Garden gateway scheme
5 months ago

Mace wins £1.1bn British Library extension

Work to start on site next year after construction manager contract awarded
6 months ago

Sisk set for £52m civils works on Wirral garden village

£52m infrastructure works to pave way for 1,600-home Hind Street regeneration
6 months ago

McLaughlin & Harvey scrubs in for £100m Guy’s surgical hub

Eight-storey London elective surgery hub secures government approval
6 months ago

Breheny bags Kent road upgrade contract

Work to start later this month on Maidstone site
6 months ago

Caddick breaks ground on £28m Bilston logistics park job

166,500 sq ft logistics hub to be built at Foundry Business Park
6 months ago