BAM Nuttall docked £10m from bus job in Cambridge

Grant Prior 14 years ago
Share

BAM Nuttall has been docked £10m for being two years late completing construction of  its £87m Cambridgeshire Guided Busway contract.

Cambridgeshire County Council confirmed it has been deducting almost £14,000 a day in late delivery damages from BAM Nuttall since February 2009.

The dispute is understood to essentially boil down to whether extra works needed on the tram project are variations to the contract or defects.

A council cabinet meeting last week heard senior councillors describe BAM Nuttall’s latest delays as “unnecessary”.

The contractor has told council bosses all their major work is now complete.

But the council claims Nuttall has left the submission of construction and design certificates until the last minute.

Both design and construction certificates are essential for the council to be confident that the scheme has been built correctly.

The Project Manager, who is independent of both the Council and Nuttall, cannot certify the contract as complete until the most important certificates for the main structures have been received and are satisfactory.

Nuttall has been accused by the council of not yet submitting five construction and design certificates. A further 47 construction certificates, that had been previously been rejected also need to be resubmitted, and accepted, before the contract can be certified as complete.

Once Nuttall complete the Busway contract they will have 28 days to fix all notified defects on the route.

The council is lining up a new contractor to fix the defects if Nuttall misses the deadline. The costs of the work will be deducted from Nuttall.

Roy Pegram, Cabinet member for Growth, Infrastructure and Strategic Planning, said: “The Busway is not any longer, any wider or any higher than when the contract was awarded so it is clearly unacceptable that BAM Nuttall have taken two years longer than they should to build the route.

“Residents and everyone at the council would have rightly expected to see buses running a long while ago, but the contractor’s delays have directly resulted in £10m in damages being stripped from the firm.

“Although the timescale for BAM Nuttall completing the contract is in their hands, I would like to reassure people that the Council has plans in place to get the route open as soon as possible once they finally achieve that. Clearly correcting the defective work is part of this process, which will take a number of weeks.”

Council claim problems with the contract include:

Maintenance track – some areas of the track have been built at too low level which means rain water has collected and the maintenance track is flooded. These areas of the track need to be raised without affecting the flood balance in the area.

Beam expansion gaps – The County Council requires the contractor to show that the gaps between the beams will allow for expansion of the beams during periods of hot weather while giving a smooth ride for passengers.

Foundations – The County Council requires the contractor to show that the use of shallow pad foundations on some short sections of track where deeper piled foundations were originally planned is appropriate. The County Council need calculations to show the track will not move over time reducing the ride quality.

St Ives Park & Ride car park – the car park has been built with less than the specified gradient and water is ponding on the surface of the car park.

River Great Ouse Viaduct – rain water is leaking through an unsealed expansion joint onto the steel below. If this was not fixed now council taxpayers would pick up future bills for additional maintenance costs.

Latest news

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
18 hours ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
3 hours ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
19 hours ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
19 hours ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
18 hours ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
2 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
2 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
18 hours ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
1 day ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
2 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
2 days ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
2 days ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
2 days ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
2 days ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
2 days ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
2 days ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
5 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
5 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
5 days ago

Developer Breck to transform former Ibstock brick factory

Ravenhead works to become 300-home development
5 days ago

SP Energy Networks awards contracts worth £1.4bn

First round of awards under £5.4bn national electricity grid upgrade programme
6 days ago

Travelodge to convert Liverpool Street office building

Office-to-hotel conversion in City of London
5 days ago

Plans lodged for 1m sq ft City of London office

Barbican landmark building will reuse 40% of existing structure
5 days ago

PTSG acquires roofing specialist HD Sharman Group

Premier Technical Services Group expands building maintenance division
5 days ago

Balfour Beatty lands £833m carbon capture power plant job

Work to start later this year on Teesside carbon capture gas-fired power station
6 days ago

Svella agrees deal to save Cubby Construction

Solvent purchase set to save 214 jobs and protect supply chain
6 days ago

J Coffey holds line on margins despite £52m revenue slide

Pre-tax profit down 14% but firm eyes strong pipeline to bounce back
6 days ago

Consultants called up for £2.3bn NHS SBS panel reboot

Market asked for views ahead of next-gen procurement rollout
6 days ago

Hochtief launches new UK data centre division

German business model to be introduced for UK construction
7 days ago

Construction skills body launches with 100,000 worker target

Industry to work closer with Jobcentres to find new talent
6 days ago