BAM Nuttall docked £10m from bus job in Cambridge

Grant Prior 13 years ago
Share

BAM Nuttall has been docked £10m for being two years late completing construction of  its £87m Cambridgeshire Guided Busway contract.

Cambridgeshire County Council confirmed it has been deducting almost £14,000 a day in late delivery damages from BAM Nuttall since February 2009.

The dispute is understood to essentially boil down to whether extra works needed on the tram project are variations to the contract or defects.

A council cabinet meeting last week heard senior councillors describe BAM Nuttall’s latest delays as “unnecessary”.

The contractor has told council bosses all their major work is now complete.

But the council claims Nuttall has left the submission of construction and design certificates until the last minute.

Both design and construction certificates are essential for the council to be confident that the scheme has been built correctly.

The Project Manager, who is independent of both the Council and Nuttall, cannot certify the contract as complete until the most important certificates for the main structures have been received and are satisfactory.

Nuttall has been accused by the council of not yet submitting five construction and design certificates. A further 47 construction certificates, that had been previously been rejected also need to be resubmitted, and accepted, before the contract can be certified as complete.

Once Nuttall complete the Busway contract they will have 28 days to fix all notified defects on the route.

The council is lining up a new contractor to fix the defects if Nuttall misses the deadline. The costs of the work will be deducted from Nuttall.

Roy Pegram, Cabinet member for Growth, Infrastructure and Strategic Planning, said: “The Busway is not any longer, any wider or any higher than when the contract was awarded so it is clearly unacceptable that BAM Nuttall have taken two years longer than they should to build the route.

“Residents and everyone at the council would have rightly expected to see buses running a long while ago, but the contractor’s delays have directly resulted in £10m in damages being stripped from the firm.

“Although the timescale for BAM Nuttall completing the contract is in their hands, I would like to reassure people that the Council has plans in place to get the route open as soon as possible once they finally achieve that. Clearly correcting the defective work is part of this process, which will take a number of weeks.”

Council claim problems with the contract include:

Maintenance track – some areas of the track have been built at too low level which means rain water has collected and the maintenance track is flooded. These areas of the track need to be raised without affecting the flood balance in the area.

Beam expansion gaps – The County Council requires the contractor to show that the gaps between the beams will allow for expansion of the beams during periods of hot weather while giving a smooth ride for passengers.

Foundations – The County Council requires the contractor to show that the use of shallow pad foundations on some short sections of track where deeper piled foundations were originally planned is appropriate. The County Council need calculations to show the track will not move over time reducing the ride quality.

St Ives Park & Ride car park – the car park has been built with less than the specified gradient and water is ponding on the surface of the car park.

River Great Ouse Viaduct – rain water is leaking through an unsealed expansion joint onto the steel below. If this was not fixed now council taxpayers would pick up future bills for additional maintenance costs.

Latest news

McAlpine pulls out of £55m Carlisle Citadels project

University of Cumbria starts hunt for replacement contractor
3 days ago

Strabag UK suffers further big trading loss

Austrian contractor is gearing up for major presence in the UK market
2 days ago

Durham Uni picks UPP for £130m student scheme

Firm will deliver 1,000 self-catered bed spaces
2 days ago

Architects now upbeat after 10-months of work gloom

Larger practices see rising workloads in next three months
2 days ago

Motorist dies after collision with road paver

Police Scotland investigating fatal crash
3 days ago

McLaren Living appoints HG Construction for £69m scheme

Build to Rent scheme will transform former vacant car park site in Leeds city centre
3 days ago

Squibb liquidator probes £2m of “missing” plant

Machinery, cars and scrap metal have disappeared at demolition specialist
3 days ago

Galliford Try to re-enter affordable homes market

Contractor sets out new five-year plan to build margin to 4%
3 days ago

Former Sellar chief to lead civils contractor Kilnbridge

Owen Dannatt joins as new CEO as founder Dermot McDermott becomes Chairman
3 days ago

Hunt starts for nuclear fusion plant construction partner

Fusion energy plant to be built at West Burton coal power station site.
3 days ago

National Grid raises £7bn for big infrastructure upgrade

Rights issue to fund a major round of capital investment in energy infrastructure
3 days ago

Grenfell police probe to last at least until end of 2025

19 companies and 58 individuals could eventually face charges
4 days ago

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
4 days ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
4 days ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
4 days ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
4 days ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
4 days ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
4 days ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
5 days ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
5 days ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
5 days ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
5 days ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
5 days ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
5 days ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
5 days ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
5 days ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
5 days ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
5 days ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
6 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
6 days ago

Contractor services