Two contractors are facing huge fines after a worker was left with severe brain injuries after being hit with a scaffold pole being used as makeshift plumb line.

Richard Chodkiewicz, 53, now needs 24-hour care for the rest of his life after the pole fell 15 storeys down a lift shaft and hit him in the head in July 2008 at the Radisson Blu hotel site in Bristol.

Bristol Magistrates’ Court heard that the 7lb pole was being used to measure the shaft when a line holding it – made of either plastic or piano wire – broke and it fell to the shaft pit.

Chodkiewicz, who was wearing a hard hat at the time, suffered a “catastrophic brain injury” that required part of his skull to be removed.

The Bristol Evening Post said he spent six weeks in intensive care and was then transferred to a brain injury rehabilitation unit.

Prosecuting on behalf of the health and safety executive, Dale Collins said the accident had completely changed the lives of Chodkiewicz and his family, who are receiving counselling.

He said: “This has had a devastating effect on Mr Chodkiewicz and also his five children and grandchildren. He now requires 24-hour care and is unable to work.”

Reading a statement from his family, Collins said: “Richard can’t be left alone because he is always at risk, and he needs help with all aspects of daily living. Richard is very childlike in his abilities and needs prompting for all basic skills.”

Yesterday Hoistway Limited, Mr Chodkiewicz’s employer, pleaded guilty to failing to ensure the health and safety of an employee.

Main contractor Miller Construction also pleaded guilty to failing to ensure that a person was not exposed to risks while undertaking the installation of lifts.

Collins told magistrates that Hoistway had failed to provide adequate risk assessments and did not identify hazards; that using a piece of scaffolding was not standard equipment checked by a competent person and was improvised; that there was inadequate site management and supervision, and that there was inadequate protection against people or objects falling.

He said that Miller Construction had carried out insufficient risk assessments, had left openings unguarded and at risk of falling objects, and had not fully checked and failings in Hoistway Limited’s risk assessment.

Defending Hoistway Ben Compton said it “accepted unequivocally” failings in a duty to its employees.

He added: “The offence was not a deliberate breach of the law. It was not reckless, but careless.”

Simon Antrobus, for Miller, said the company’s role was of “overview and monitoring”, adding that its culpability in the case was “relatively low”.

Magistrates said the two companies had failed in their duties “to a significant degree” and ordered the pair be sentenced at Bristol Crown Court, saying that their own powers, to impose a maximum fine of £20,000, were insufficient to adequately punish the firms.

Latest news

Groundworks firm Hiretest files administration notice

Specialist worked a lot with collapsed contractor Readie
6 hours ago

Siemens Mobility to build £100m Chippenham factory

New factory will build the next-generation of rail signalling and control systems
5 hours ago

Acquisitive RSK tops £1.2bn turnover

Pre-tax losses double to £81m after year of 34 buy-outs
5 hours ago

Winners revealed for £700m new build housing deal

EN:Procure selects 27 contractors for new framework: Full list of winners
5 hours ago

Morgan Sindall seals £39m deal for Newcastle academy deal

Work on Callerton Academy job to start after two delay caused by Caledonian Modular failure
5 hours ago

GF Tomlinson edges back into profit

Midlands builder avoids staff layoffs despite revenue fall
5 hours ago

M&S wins appeal over Gove refusal to demolish flagship store

Retailer claims victory in planning row over Marble Arch building
3 days ago

Plans expand for “new city district” at Bristol airfield

Malaysian firm YTL gets green light for bigger Brabazon development
3 days ago

NG Bailey chief to step down

David Hurcomb to retire in May after 14 years at the helm
4 days ago

Hundreds to be rehoused in Aberdeen over RAAC fears

Engineers exploring whether to condemn 500 homes or carry out remedial works
4 days ago

Plan in for North London 620-bed student scheme

Student rooms and affordable homes scheme to be built in Wood Green
3 days ago

Stantec lands design role on £4bn battery factory

First main construction award due shortly on Somerset mega-project
4 days ago

Utilities and civils specialist Ferns returns to profit

Kent-based firm grows to £81m revenue as telecoms work takes off
3 days ago

Go-ahead for 316 bed Stratford student scheme

Construction to start by end of year on site next to Pudding Mill Lane station
3 days ago

Equans suffers £146m loss and quits new build housing

Losses hit £99m on housing association new build work
4 days ago

Job cuts at modular house builder TopHat

Offsite housing specialist acts in response to "challenging market"
4 days ago

Graham wins £85m Milton Keynes Lakes Estate revamp

Enabling works start ahead of building 200 council homes
4 days ago

Go-ahead for London’s largest estate £1bn rebuild

Spring start for first job at Stratford's Carpenter Estate scheme
5 days ago

Costain trials electric vans on major civils sites

Green vans meet "tight budgetary requirements" in pilot scheme
5 days ago

Green light for major mixed-use scheme in Ealing

Scheme will provide 10,915 sq ft of industrial workspace alongside 140 new homes
4 days ago

Taylor Wimpey sees tender inflation fall to 1%

House builder retenders site work as build costs slide
5 days ago

Careys back in profit after £47m turnaround

Contracting division back in profit ahead of three-year growth plan
6 days ago

Rye Demolition goes into administration

Another specialist contractor goes under
5 days ago

Historic breakthrough for HS2’s longest tunnel drive

TBM Florence ends her 10 mile journey under the Chilterns
6 days ago

Volumetric builder Tide seals deal to start London tower

32-storey North Acton tower will consist of 462 co-living units
5 days ago

Costain moves HQ to London’s Can of Ham

Contractor makes return to London from Maidenhead base
6 days ago

Former Keltbray highways MD joins McAlpine

Vip Gandhi takes lead role at Transport division
6 days ago

Willmott Dixon exits stage left from Essex theatre contract

Contract re-tendering shines spotlight on growing schism between contractors and clients
6 days ago

Purpose build student schemes to surge again

Unite assembles record £1.3bn pipeline as fall in HMO supply boosts PBSA sector
6 days ago

Bidding starts for £1.4bn Midlands Rail Hub Alliance

Alliance will deliver upgrades to rail lines and stations around Birmingham and nearby towns
6 days ago

Contractor services