McAlpine takes plaudits as 2012 Stadium completed

Grant Prior 13 years ago
Share

Sir Robert McAlpine has been hailed for its performance completing the 2012 stadium on time and under budget without any major accidents.

Olympic Delivery Authority chairman John Armitt laid the last piece of turf yesterday marking completion of the main construction phase which has lasted nearly three years.

He said: “To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry.

“I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

Over 240 UK businesses have won contracts for the construction of the Stadium and over 5,250 people have worked on the project over the past three years.

Construction facts and figures

Construction started in May 2008 and has been completed in just under 3 years.

The design and construction team has been led by Sir Robert McAlpine, with Populous as the Architect and Buro Happold as the designer of the civils, structural and building services work. Hyland Edgar Driver were the Landscape Architects. The Planning Consultant was Savilles Hepher Dixon

Over  5250 people have worked on the project over the past 3 years with the operatives workforce peaking at 650

Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.

More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure

112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place

The roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.

The cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.

To ensure that the sporting action is illuminated and to meet high definition TV standards, the Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70 metres above the field of play.

Each of the 14 lighting tower weighs 34 tonnes and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.

There will be around 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000 sq m of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.

The turf for the field of play was grown in Scunthorpe and was laid over a period of 3 days in March 2011.

The track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.

The black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.

The toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

Latest news

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
5 hours ago

Wates-owned SES restructure delivers record profit and revenue

Building services contractor revenue soars to almost £300m
4 hours ago

25 groundworks firms win £100m Places for People deal

M&J Evans, Carmac and Churngold Construction feature in housing association's line-up
5 hours ago

Energy efficiency firms angry at lack of CITB support

SME contractors funding bid "does not meet the current criteria for supporting productivity or EDI"
5 hours ago

£400m South Cambridge science park approved

Outline approval allows former sewage treatment works to be demolished
5 hours ago

McLaren gets green light for 45-storey Leeds tower

Landmark Wellington Square scheme will see 464 flats built with 360,000 sq ft of offices
3 days ago

Heavy rain causes 1.9% construction output fall

Hopes remain undampened of a resi-led recovery this summer
3 days ago

Taziker restruture to return to profitability after £1.2m loss

Founders bought the business back from private equity after last year's loss
3 days ago

£220m London wharf homes scheme approved

285 homes to be built beside protected Albert and Swedish Wharves in Wandsworth
3 days ago

Major project veteran named civils director for Sizewell C

David Speight previously worked on Hinkley, Heathrow and HS2 client teams
3 days ago

Morgan Sindall lands £19m Milton Keynes hospital job

Crane lifts to be carefully co-ordinated to ensure air ambulance remains active
4 days ago

Clancy bolsters civils leadership team

Daniel Tonkin and Simon Hyams join as operation directors of water and infrastructure
4 days ago

Balfour names new project boss for HS2’s super-hub station

Steve O’Sullivan replaces Nigel Russell who was promoted to CEO of Balfour's HS2 ops
4 days ago

Buckingham Group supply chain hit doubles to £256m

Total owed to unsecured creditors soars as surety providers finalise claims
4 days ago

Builders demand an end to police plant bans

Call to suspend all embargoes on moving mobile cranes and large site kit
4 days ago

Green light for £65m Blackpool multiversity campus

Education campus of 350,000 sq ft will be delivered in phases
4 days ago

Vinci signs £138m Sheffield steel forge expansion deal

Sheffield Forgemasters signs landmark contract after two years of pre-construction works
5 days ago

McAlpine hires HS2 programme boss to head defence arm

Armed forces logistics expert Mike Hickson takes role as MD of defence
5 days ago

£200m carbon capture plan for Deeside site

Energy from waste operator enfinium looking to invest in North Wales plant
4 days ago

McAleer & Rushe promotes five staff to contracts directors

Design and build contractor targets £500m revenue next year
5 days ago

Consultant quartet win Government estate upgrade deal

Government Property Agency selects Arcadis, Tetra Tech, AtkinsRéalis and McBains
5 days ago

Resi towers pioneer to transform Liverpool site

Beetham founder Hugh Frost to help develop 1,200 new homes
6 days ago

Construction Manager of the Year crowned

Galliford Try's Barry Kingscote wins coveted prize: Full list of winners
5 days ago

Landsec £250m London terraced office job approved

Skanska tipped for 20-storey Hill House scheme near Fleet Street
6 days ago

Lendlease tops March contracts league

BAM and ISG rank third with big contract wins
5 days ago

Vistry strikes deal with Homes England for 1,000 units

Firm's timber frames factory will supply most of the Midlands houses
5 days ago

Morgan Sindall go-ahead to build 23-storey Salford resi job

Funding deal with CBRE allows latest project on bank of River Irwell to proceed
6 days ago

Unite Students gains planning for London and Bristol schemes

RG Group will build landmark Stratford tower and Freestone Island projects
6 days ago

Rolls-Royce gets go-ahead for 1.1m sq ft expansion in Derby

Major expansion of Raynesway campus planned to met submarine fleet orders
6 days ago

GMI Construction edges back into profit

A year of controlled consolidation helped generate £0.9m profit but cash at bank dropped to £10m
6 days ago

Contractor services