See how the Tube was built 150 years ago

Grant Prior 11 years ago
Share

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

HS2 viaduct blunder over wonky concrete segments

Align JV now drilling out concrete joint as part of week-long remedial work
9 hours ago

City of London hots up as 9m sq ft under construction

Investors return to City as "10 Cheesgraters" of floorspace under construction
2 hours ago

Four arrested in £140m property fraud probe

Serious Fraud Office investigating collapse of property developer Signature Group
10 hours ago

London £3bn housing framework out to tender

SMEs allocated slots on London Construction Programme housing framework refresh
16 hours ago

BAM wins first major RAAC school rebuild

Contractor seals £46m deal for St Leonards school in Durham
16 hours ago

Failed strip out specialist owes £1.5m to supply chain

More than 100 subcontractors and suppliers left with unpaid bills by Type Ten Limited
17 hours ago

Councils to turn screw on building owners over fire safety upgrades

Government tells councils to step up legal action against rogue building owners
17 hours ago

Green light for £300m Fenland energy from waste scheme

Wisbech incinerator will generate 50MW from half a million tonnes of waste
1 day ago

Multiplex starts on 50-storey Thames tower

Developer green lights construction of latest phase of £3bn Bankside Yards scheme
2 days ago

McLaren lodges fresh Reading Broad Street Mall plan

Town centre scheme will deliver 600 homes in four towers
2 days ago

Beard bags £24.5m Bristol office revamp

Construction to start in April
16 hours ago

SMEs star in £3.2bn social housing upkeep deal

Around 85% of Efficiency North's framework winners are local firms
2 days ago

Scottish NHS new building projects delayed for two years

Spending clampdown hits over a dozen planned projects
2 days ago

Balfour M25 workers hold strike ballot

Motorway maintenance crews unhappy with 3.4% pay rise offer
2 days ago

Rainsford Contracts acquires M&E specialist

Expanded contractor will have turnover of £45m
2 days ago

Statom expands with launch of Northern HQ

RC frames specialist now targeting jobs in Scotland and north of England
2 days ago

High Court dismisses Stonehenge tunnel challenge

Judge quashes legal challenge against Government consent for £1.7bn job
2 days ago

£1.5bn Teesside carbon capture scheme consented

Final investment decision expected this year for construction start
3 days ago

First viaduct steel section installed at HS2’s complex junction job

Victor Buyck Steel Construction install first 300t viaduct section
3 days ago

Sister scaffold firms file administration notices

BCM Scaffolding Services and Scaffteq West employ 100 people between them
3 days ago

McLaughlin & Harvey suffers £8.6m loss

Cost inflation and Scottish landfill tax legislation hit Antrim-based group
3 days ago

Regulator opens probe into National Highways delivery

ORR concerned about 'dip in performance' on capital projects
3 days ago

Sir Robert McAlpine chief Paul Hamer exits

Hamer replaced as CEO by former Lendlease Europe boss Neil Martin
6 days ago

Unite Students to build £250m Newcastle scheme

Work to start this summer on revamp of Castle Leazes site
3 days ago

Britcon poaches Tilbury Douglas business development chief

Don Stewart joins Britcon board as strategic director
3 days ago

Building control system on verge of collapse

Calls to delay new registration scheme
6 days ago

Go-ahead for UK’s largest mass timber structure neighbourhood

Visionary 685-home sustainable village will be built in Lewes, East Sussex
6 days ago

£90m Manchester zig-zag library approved

Work to start this summer on iconic city centre building
6 days ago

Mace clear to start £34m weather-watching HQ job

Planning granted for European Centre for Medium-Range Weather Forecasts
6 days ago

Ford Dagenham site revamp to hit nearly 4,000 homes

Latest phases approved for £1bn Beam Park redevelopment
6 days ago

Contractor services