See how the Tube was built 150 years ago

Grant Prior 9 years ago
Share

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

Akela Group moves into England with new Leeds hub

Scottish civils contractor looks to boost business by 10% with move south of the border
3 hours ago

Three brickies fall through stairwell on St Modwen Homes site

House builder fined £200,000 after trio suffer serious injuries falling 2.5metres through temporary cover
4 hours ago

Sellafield plans £3bn infrastructure delivery partnership

Morgan Sindall/Arup alliance to be replaced by three delivery partners
11 hours ago

Billington cheered by big shed and infrastructure job surge

Steelwork specialist reports challenging market as main contractor clients squeezed by inflationary pressure
10 hours ago

Bid race starts for £1.6bn Pagabo civils framework

New civils framework will be split into four project-size lots
1 day ago

SEGRO to start £300m futuristic food production hub

Advanced 1.8m sq ft food growing facility planned near Derby
11 hours ago

First contractor fined after 316,000 HSE Covid spot checks

One prosecution so far following blitz of workplace Covid spot checks during pandemic
1 day ago

Ten fire crews tackle blaze at Hinkley

Temporary building on giant construction site goes up in flames
11 hours ago

Fusion21 refreshes consultants framework

Firms expected to support around 100 projects a year
10 hours ago

Builders’ merchants merge to create 123-branch chain

Independent Builders Merchant Group territory now extends from Corwall to Kent
1 day ago

Digger topples into trench on Costain M6 job

Driver in lucky escape after 13t excavator upends in central reservation drainage trench
1 day ago

Inquiry starts into construction of Scottish hospitals

Focus on construction problems at two major hospital sites
1 day ago

Thompsons blow down iconic Dorman Long tower – video

Controlled explosions bring down four Redcar steelworks structures at once
1 day ago

Manchester crane driver rescued after falling ill in cab

Emergency services lower stricken operator in a stretcher from tower crane cab
1 day ago

Taylor Wimpey MD joins Weston Homes

Peter Gore to oversee delivery of £2bn work pipeline
1 day ago

Henry Construction to build £32m Ealing resi scheme

Financing deal paves way for start on 14-storey scheme
5 days ago

Bourne hires new engineering director

Steelwork contractor appoints Denis McNelis to broaden its reach
1 day ago

50 firms win £3.6bn National Highways renewals deal

Morgan Sindall, Eurovia and Osborne win super regions civils
5 days ago

McLaren wins new Aston Martin F1 factory race

£200m development near Silverstone will take 18 months to complete
4 days ago

Kent Council seeks four partners for £500m pipeline

Council drops 17-supplier framework to partner with just four contractors
4 days ago

Robertson set to seal £150m Cardiff Arena deal

Cabinet to sign off contractor and business case for construction start next spring
4 days ago

VolkerFitzpatrick wins £82m Hull turbine blades factory

Deal to upgrade and build two more factories follows on from job five years ago
5 days ago

Lorne Stewart battles to return to profit

Harrow-based M&E group begins to curb losses
4 days ago

Kier returns to profit after two-year turnaround

Contractor makes £5.6m after £225.3m loss last time
5 days ago

Galliford Try returns to profit with margin at 2%

Order book swells to £3.3bn with 90% of work in place for 2022
5 days ago

Fire hits £120m Tolent Milburngate site

Blaze breaks out behind cavity wall as site evacuated
6 days ago

Roof tile maker Marley to float on stock market

Private equity firm unveils plan to take Britain's largest roof tile maker public
5 days ago

Plans in for Lancashire 1,700 inmate prison

Seven houseblock HMP Wymott 2 planned near Leyland
5 days ago

Michael Gove named new housing secretary

Gove replaces Robert Jenrick in Cabinet reshuffle
6 days ago

Redrow happy for staff to keep working from home

House builder says staff can work "where they are most efficient"
6 days ago

Contractor services