See how the Tube was built 150 years ago

Grant Prior 10 years ago
Share

Pictures of construction work on the London Underground have been released to celebrate the Tube’s 150-year anniversary.

The images form part of a major new exhibition at the Museum of London detailing how work first began under London’s streets in the 1860s.

Early labour-intensive “cut and cover” techniques soon gave way to a technique named “the shield”, as engineers looked to build tunnels deep beneath Victorian London.

Transport for London’s design and heritage manager, Mike Ashworth, told the BBC: “The cut and cover method was to dig a trench, build back the side and roof it over.”

It was a simplistic approach to tunnel building, with work happening just below the surface, Mr Ashworth said.

“There was so much disruption caused by demolition through a very crowded city.

“Most roads were already full of gas mains and other utilities and there would have been enormous upheaval as they had to shut roads.”

When Tube engineers adopted the more successful shield method it heralded the transformation of London’s transport network which now serves 270 stations on a service spanning 250 miles.

Ashworth said: “It is highly unlikely that our system would have developed to such an extent if it hadn’t left cut and cover.”

The shield, which was the technique used as the Underground expanded, was first successfully used in 1825 to excavate what is now the Wapping – Rotherhithe tunnel, which was one of the first underwater tunnels in the world.

Modifications by James Greathead and mechanised forms of the shield helped form the basis of Crossrail’s tunnel boring machines (TBM).

At the front of the original design there was an iron frame and within each pocket was a man with a spade.

Once each section was dug out, timbers were put up to support the earth before hydraulic jacks pushed the frame forward and a row of bricks was built inside the tunnel they had created.

Workers dug by hand in the pockets of the shield

But Tim Shields, curator at London Transport Museum, said: “The shield offered the workers some protection but it would have been claustrophobic and very hot.

“They would often have been bare-chested but some pictures show them working in a jacket and shirt which is quite surprising.”

Andy Alder, project manager at Crossrail for the western tunnels, explained: “It was called the shield because it shields the men from the ground.

“The story goes that it is based on observing how worms bore through wood and this was pretty much the foundation for the main tunnelling work we are doing.

“All we’ve done is put a steel rotating cutter head with a motor at the front.

“There’s still then men digging, the jacks are still the same, then building the precast concrete sections behind and we have a railway that takes the ground out.”

Alder said the men digging the Tube could make the same progress in a year that the team behind Crossrail make in a week.

Latest news

Squibb confirms appeal against bid rigging fine

Demolition specialist joins Keltbray in appealing against CMA penalty
7 hours ago

Bigger projects help Wates hit record turnover

Size of average construction contract taken on hits £43m
10 hours ago

12 firms in fight to renew £1bn North West Construction Hub deal

Race starts for medium value building framework covering projects between £3m-£8m
10 hours ago

Former Inland Homes chief to invest £2.5m in cash raise

Cash-strapped developer hopes to raise £4.6m in share sale closing today
19 hours ago

Ten firms sign £3bn L&Q homes upgrade deal

15-year deal will include fire safety, energy retrofits, bathroom and kitchen upgrades
11 hours ago

Groundworks firm Conlon saves piling specialist

Work restarts on Abbey Pynford sites after acquisition
1 day ago

BAM Farrans JV installs Great Yarmouth bridge leaves: Video

Watch civil engineering feat in action as 770 tonne bridge leaves lowered into place
1 day ago

Gove invites Kingspan for talks on fire safety compensation

Insulation firm urged to pay for its part in cladding crisis after unveiling record profits
1 day ago

Galliford Try and Midgard bag 350 homes deal at Brent Cross

Galliford Try will build 249 BtR flats and Midgard 107 flats for sale
1 day ago

Sizewell C project gains key environmental permits

Waste permits allow client NNB Generation Company to move to site investigation and construction environmental approvals
1 day ago

Cost of Robertson school contract soars to £100m

Construction to start next month after cost jumps from original £60m
1 day ago

House building cost inflation eases as build out rates fall

Housing cost inflation expected to grow by 1.4% this quarter
1 day ago

Modular builder ilke Homes hires Deliveroo chief to drive profit push

David Scott charged with making business profitable
1 day ago

£500m Leeds South Bank scheme gets green light

Leeds City Council approves plan for 1,350 flats in mixed-use South Bank development
3 days ago

Galliford Try takes rebid £150m Carlisle Southern Link Road

Main construction works are due to start on 8km road in June
3 days ago

Arup takes stake in graphene-enhanced concrete venture

New concrete additive Concretene™ promises 30% savings in CO2 emissions
2 days ago

Winners revealed on £1.42bn materials framework

Thirteen builders merchants land places on huge procurement deal for social landlords
2 days ago

Travelodge eyes plans for another 300 hotels

Hotel giant writes to local councils offering partnership deals with a £3bn investment target
2 days ago

Balfour Beatty to invest £60m in pop-up EV chargers

New Urban Fox JV will roll out 35,000 charge points across the UK over the next decade.
3 days ago

Leading Channel Isles builder goes bust

Jersey-based construction firm Camerons placed in liquidation
2 days ago

HS2 Euston needs full design reset as costs set to double

Spending watchdog warns Euston stop-start delay will simply inflate already ballooning costs
4 days ago

Worker dies on major warehouse site in Stafford

Main contractor Glencar halts work while tragedy is investigated
3 days ago

Sellar switches London flats/hotel plan for 444 student rooms

Southwark's King’s Place scheme will comprise five buildings of up to 11 storeys
3 days ago

Bid race starts for Norfolk £30m Long Stratton Bypass

Council hopes to start work on 3.9km bypass in April 2024
3 days ago

GMI to build first warehouse at £200m Teesside business park

Work to start early next month on first shed at airport business park
3 days ago

Skanska Costain Strabag JV sets up own rebar plant

HS2 team now running on-site manufacturing facility to avoid supply chain issues
3 days ago

Bid rigging: Keltbray to appeal and so could Squibb

Both contractors "disappointed" with level of fines
6 days ago

Ten demolition firms fined £60m for bid rigging

Full details of fines with Erith and Keltbray hardest hit
1 week ago

Retail contractor J M Scully files administration notice

£23m turnover Dorset based contractor lodges court notice
6 days ago

Civils specialist M Lambe delivers record performance

Housing civils specialist seeks to diversify in face of challenging housing market
6 days ago

Contractor services