Amec appeal refused over £94m costs on submarine job

Aaron Morby 14 years ago
Share

Amec’s legal battle to reduce the amount it must pay of a £93.6m cost overrun on a nuclear submarine jetty contract at Faslane has failed.

Now Amec and partners Morgan Sindall face a huge bill as they hammer out with the Ministry of Defence what proportion of cost overruns were properly incurred on the troubled project.

A costly legal battle has been running as both firms struggle to finish the Faslane SSN Berthing Project, first revealed in the Enquirer, more than four years late and at an expected final cost of £235.7m.

When the project was first awarded Amec was sole contractor for the jetty. But after Morgan Sindall acquired Amec’s construction arm for £26m back in 2007, the job became a 50:50 joint venture between the two firms.

Under the terms of the contract, the contractors are liable to pay the first £50m of overruns on the agreed maximum target price for the job, which has itself already risen from £89m to £142m.

This element was not challenged in the latest legal contest, but Amec held that the remaining £43.6m cost overrun should be split between client and contractor, with Amec due any costs howsoever incurred.

An arbitration panel rejected this saying the only costs payable were the actual costs reasonably and properly incurred within the contract.

A High Court judge has now refused Amec’s attempt to appeal this decision in a written ruling this week upholding the arbitration decision.

Latest news

Multiplex gets start date for City Road 36-storey tower

Main construction to get underway this quarter
16 hours ago

Trade credit insurer could cut cover for Vistry suppliers

Allianz Trade reportedly reduces credit limits as house builder battles to cut £800m net debt
19 hours ago

M&E specialist ACES files administration notice

Avon Combined Electrical Services expanded into the capital last year to win larger jobs
21 hours ago

Portsmouth picks ECF for 2,300-home city centre regeneration

Council finally advances ambitious City Centre North regen plan
21 hours ago

Newcastle office block plan unveiled

12-storey scheme to be latest addition to One Founders Place
21 hours ago

Eric Wright to start £65m Tebay-style M56 services

Yates starts groundworks on Cheshire motorway services
22 hours ago

Plans in for retrofit of London Charing Cross office icon

Major retrofit plan keeps 90% of iconic 1990s office building
1 day ago

Higgins lands Brentford estate revamp

Construction to start this autumn on 182-home scheme
21 hours ago

Kier bags biggest sewage treatment job yet

Firm signs ECI deal on £265m Thames Water AMP8 treatment works upgrade
4 days ago

Plan in for 53-storey Birmingham build to rent tower

42 High Street tower near the Bullring could be Birmingham's tallest building
4 days ago

HG seals hat-trick of Gateway 2 project approvals

Bristol, Manchester and London schemes will deliver 664 homes and student beds
4 days ago

Farrans to build new Stansted skylink walkways

Sections to be built "offsite" in vacant airport hangar
4 days ago

Ceiling specialist Zentia went down owing suppliers £5.6m

Unsecured creditors left holding worthless invoices
4 days ago

Mears secures £4.2bn pipeline after contract winning spree

Housing upkeep giant lands £1.4bn of work as Birmingham deal leads bumper order book
5 days ago

Construction buyers see first signs of a turnaround

July data shows construction market starting to stabilise
5 days ago

£90m bid race for iconic Foster museum revamp

UAE's Sainsbury Centre museum to get new envelope and low-carbon building services
5 days ago

Persimmon sharpens axe on costs as inflation threat grows

Builder targets procurement savings as inflation clouds outlook
5 days ago

Multiplex tops contracts league with £400m office job

July order haul among Top 50 contractors edges up 3.5% in July
5 days ago

Forshaw Demolition goes into administration

Bolton based specialist worked on packages up to £2m across the country
5 days ago

Panattoni submits plans for 1m sq ft Kent scheme

70-acre site to become major industrial and logistics scheme
5 days ago

Public work bidders face 20% jobs and skills hurdle

Firms chasing government work face tougher job creation and pay scoring from January
5 days ago

Orbit unveils £1.4bn long-term housing works pipeline

Bid race for five regional lots covering planned maintenance, remediation and major projects
6 days ago

Yorkshire Water sounds out market for £3bn AMP9/10 plan

Early market engagement begins for decade long £330m a year programme
6 days ago

Ibstock makes £27m loss as brick demand dives

Mothballed plants lead to large impairment charges
6 days ago

Gatwick second runway cleared after court challenge fails

Final legal challenge dismissed as £2.2bn build moves towards site start
6 days ago

Magrock lands £16m David Lloyd deal

Contractor signals move into leisure sector
6 days ago

Construction arm lifts Muir Group back to profit growth

Muir builds on strong year with £114m turnover and £21m cash
6 days ago

Tribe lodges twin Greenwich student tower scheme

Developer seeks consent for 27 and 23-storey towers beside Silvertown Tunnel
6 days ago

Swindon groundworks firm files administration notice

£20m turnover specialist Avtar Construction files court papers
7 days ago

Formation wins Gateway 2 for Hyde Greenwich homes

Wembley contractor clears hurdle on first phase of Charlton Riverside regeneration
7 days ago