Platform collapses as crane lift goes wrong

Grant Prior 11 years ago
Share

Concrete frame specialist J Reddington Ltd has been fined £70,000 after a formwork carpenter was seriously injured when a temporary platform collapsed at a landmark development in south London.

Noel Doyle, 32, from Hammersmith, suffered a shattered right elbow, broken vertebrae, fractured pelvis and ribs, and damage to internal organs in the incident at St George Wharf in Vauxhall on 10 February 2009.

He fell almost ten metres from a platform when it gave way, landing on a concrete staircase below.

Southwark Crown Court heard that on the day of the fall Doyle was helping two other JRL employees, one of whom was a foreman, to raise a temporary work platform inside a concrete shaft to house a stairwell within a building under construction.

The platform was lifted from one floor to another by a crane using four lifting chains before being locked in place in the shaft to enable the next level to be constructed.

It had been raised from the fourth to the fifth floor level when the crane operator was inadvertently instructed by the foreman to take the chains away while one of them was still attached.

Because the platform was lifted by only one corner it disintegrated.

Of the three workers standing on the platform at the time, two managed to jump to safety but Doyle was unable to do so.

He fell into the shaft beneath with parts of the platform and equipment that had been stored on top raining down on him.

Doyle required extensive treatment and physiotherapy, and has been left with limited movement in his right arm because of the elbow injury. He is no longer able to work in construction.

An HSE investigation identified that the incident was caused by the failure of the foreman, who was also acting as a banksman, to ensure that all the lifting chains had been properly disconnected from the platform before instructing the crane driver to take them away.

JRL failed to plan, manage and monitor construction work carried out under its control in a way that ensured that, so far as was reasonably practicable, it was carried out without risks to health and safety.

The company also failed to manage the design, construction, maintenance and use of the temporary core platforms throughout Block A.

J Reddington Ltd, of Borehamwood, Herts, was fined £70,000 and ordered to pay £22,193 in costs after pleading guilty to safety breaches.

After sentencing HSE Inspector Loraine Charles said: “Noel sustained serious injuries as a result of a fall that was entirely preventable had work involving temporary platforms been better planned and managed by JRL.

“He fell a significant distance and could easily have been killed, as could his two colleagues who were with him on the platform.”

Latest news

Taylor Wimpey chief honoured with CBE

Jennie Daly recognised in King's Birthday honours
10 hours ago

Geoffrey Osborne supply chain hit for £26m

More than 500 suppliers and subcontractors left holding unpaid bills
1 day ago

SME contractors agree 4% pay rise for site workers

Workers will also get an extra day of holiday
1 day ago

Labour to mothball £320m A27 job to fix potholes

Manifesto confirms Arundel Bypass canned as "poor value for money"
2 days ago

Lendlease’s £1.9bn Smithfield Birmingham scheme approved

Initial work to start later this year despite questions over Lendlease's degree of involvement
2 days ago

Crest Nicholson rejects £650m Bellway bid

Second Bellway approach rebuffed
2 days ago

Hill submits £800m East London estate rebuild plan

Over 1,900 homes to be built in five phase at Teviot Estate in Poplar
2 days ago

Plan approved for 8,500-seat Edinburgh indoor arena

Construction expected to start next year once a contractor is appointed
2 days ago

Statom starts on £25m Bristol Airport precast car park

Major work package on transport upgrade being overseen by Griffiths Farrans JV
2 days ago

Build problems plunge Crest Nicholson to a £31m loss

House builder unearths more defects on completed sites
3 days ago

Rebooted Amey lifts contract win rate to 1 in 3 bids

Amey chief says firm exceeded expectations in first year under new owners
3 days ago

BAM Nuttall fined £2.3m after worker drowned

Court hears how series of safety failures led to tragedy
3 days ago

OCU buys Scottish civils contractor RJ McLeod

Deal takes multi-utility infrastructure specialist revenue to over £800m
4 days ago

£220m plan to restore secret wartime tunnels approved

Tunnels under High Holborn to become cultural exhibition space
3 days ago

Galliford Try wins £69m Scottish school job

Deal sealed on Paisley Grammar School project in Renfrewshire
3 days ago

Balfour wins design for £690m Skye transmission job

Main work contract for 137km power line to be awarded later this year
4 days ago

Student and resi developer Fortis goes under

Cheshire based developer follows construction arm into liquidation
4 days ago

Construction output falls for third month running

Heavy rain and strong winds blamed for sharp fall in activity in April
4 days ago

Plan in for Leeds 27-storey block of flats

390 flats planned at former Morgan Sindall office site
4 days ago

Firms readied for £1.5bn Parliament estate upkeep deal

Invitation to tender due to go out next month
4 days ago

Amey switches kit supplier

Deal with HSS was worth £24.5m a year to rental specialist
4 days ago

Track workers scatter to avoid runaway rail trolley

Track trolley careers 1km towards work site
4 days ago

Direct delivery model pays off as Murphy profit soars to £67m

Group operating margin jumps from 3% to 5% in record year
5 days ago

Ex-Galliard boss to lead Battersea next building phase

Don O’Sullivan joins as plans advance to start phase 3C of power station redevelopment
5 days ago

£100m Digbeth 33-storey flats job out to bid

483 flats will be delivered for Clarion housing association
5 days ago

Van Elle fined £233,000 after piling rig kills driver

Court hears how tragedy was caused by poorly maintained plant
5 days ago

Renew buys utilities contractor Excalon

Infrastructure giant expand into electricity transmission market with £26m deal
5 days ago

Planning for new homes plunges to record low

Home builders call for urgent action from incoming government
5 days ago

JTRE starts £400m 21-floor London tower scheme

Office block and 64 affordable homes to be built at 220 Blackfriars Road site
6 days ago

R G Carter construction profits up despite 24% revenue fall

Selective client choice help profit jump to £6m from £1m previously
6 days ago

Contractor services