Plans will go on show this week for the long-awaited £600m refurbishment of Battersea Power Station.

Designs from Wilkinson Eyre Architects focus on opening up the turbine halls to public use from 2019.

Key features include:

• Open, unobstructed turbine halls
Both turbine halls are to be left largely unobstructed internally so that visitors experience the cavernous presence of each turbine hall. This has been achieved by proposing that the cafes, shops and restaurants are recessed off the sides of the turbine halls.

• A full height void (to provide views of chimneys from inside)
The creation of a full-height void space behind the southern wall of the Boiler House giving visitors the visual impact of views from the ground floor all the way up the internal wall and out to the chimneys above.

• A central atrium

The creation of a new central atrium in the Boiler House, in place of the eight smaller atria, enabling more natural light to penetrate the central part of the Power Station allowing visitors to see up to the sky from inside the building.

• A public viewing platform
The addition of a concealed lift to provide access to a public viewing platform at the top of north-west chimney, which will enable visitors to enjoy panoramic views of London at a height of 110m.

The site will contain a state-of-the-art new events space; shops, restaurants and cafes; large open-plan office spaces; and homes on the top around a garden square in the sky, as well as to either side of the Power Station.

The proposals comprise 40,000 sq m of shops, cafes and restaurants; 58,000 sq m of offices and 248 homes.

Mace is currently managing the complex enabling works to rebuild the shell of the power station including the mammoth task of dismantling and then rebuilding the four chimneys to the original design.

The painstaking process of cutting down the chimneys will begin in February.

Mace will also oversee the extensive brick repair package of work to the existing shell, which has been left shored up by temporary works for more than 20 years.

The firm beat rivals Sir Robert McAlpine, Lend Lease, Brookfield and ISG to take the package, making it a strong bidder for the main revamp of the old power station.

Tenders for this will be invited next year with a start planned in early 2015.

Rob Tincknell, Chief Executive Officer for Battersea Power Station Development Company, said: “It’s really important to everyone involved in this incredible project that we get the restoration and future use of the Power Station exactly right.

“We feel that what we are proposing retains and respects the integrity of this historic landmark whilst also creating vibrant living, working and recreational space that this part of London needs. The scheme that we are proposing will see the building restored, opened up to the public and safeguarded for future generations.”

Jim Eyre, Director of Wilkinson Eyre, said: “We wanted to ensure that the proposed designs were consistent with and sympathetic to Sir Gilbert Scott’s masterpiece, with the chimneys and turbine halls remaining the dominant features of the building.

“It was important to us to retain the Power Station’s sense of scale and visual drama, which is achieved through design features such as the full-height glass void behind the southern wall and the vast, central atrium.

“It was also really important to restore a sense of energy to the building so that people have a rewarding experience each and every time they visit.”

560x0_1383554509_chimney

Turbine-Hall-A-422-x-347px

Latest news

Berkeley holds profit forecast despite global turmoil

Middle East tensions, inflation risk and BSR delays cloud outlook
14 hours ago

Framework orders lift Tomlinson turnover to £93m

Derby contractor banks steady pipeline of education and civic schemes
15 hours ago

Wet winter and nervous clients hit construction workload

Commercial proved the only new work sector to grow in January
18 hours ago

Cardiff clears path for Wales’ tallest tower

50-storey build-to-rent skyscraper planned beside Central Station
19 hours ago

VolkerFitzpatrick wins Didcot Science Bridge

Latest award under £332m infrastructure improvement scheme
19 hours ago

Former facade boss Lee Marks joins Skanska

Experienced exec has had stints at Permasteelisa, NG Bailey, Laing O'Rourke and nmcn
2 days ago

Mace and Arup land roles for UK’s first small modular reactor

Team named for early engineering and programme strategy for Anglesey reactor
1 day ago

Vistry eyes summer start for Camden estate rebuild

Planning decision paves way for 480-home Juniper Crescent regeneration
19 hours ago

Green light for Sheffield Cole Brothers store revival

Grade II listed department store set for comeback as leisure and office hub
1 day ago

Morgan Sindall starts delayed £29m Newcastle leisure centre

Ground broken on West Denton scheme six years after old pool closed
1 day ago

UK’s biggest AI data centre plan approved

North Lincolnshire scheme to cost £7.5bn to build
2 days ago

Vistry boss buys £893k shares after stock slide

Outgoing chief Greg Fitzgerald snaps up shares after brutal market sell-off
2 days ago

CITB accused of cutting cash for small contractors

More changes to how training body hands levy funds back to contractors
2 days ago

£25m Dartford town centre housing job heads for tender

Council pushes ahead with former Co-op site 69 home redevelopment
2 days ago

Galliford back in affordable housing with £28m Chester job

Contractor returns to partnership housing after 6-year break
2 days ago

Morgan Sindall submits Crystal Palace refurb plans

Major revamp unveiled for iconic south London sports centre
2 days ago

Data centre sites to jump queue for grid connections

Consultation starts on what schemes get priority for power
3 days ago

Balfour Beatty construction margin hits 3.5%

Power generation projects drive record order book to nearly £23bn
3 days ago

Plans unveiled for 70-storey Liverpool tower

Liverpool's tallest building will rise to 727ft
3 days ago

Birmingham sets out high-rise city centre vision

5,000 homes and major commercial quarter planned around HS2 station
3 days ago

Forterra ‘insulated’ from Iran war gas price shocks

Materials giant has short-term energy supplies secured
3 days ago

Keepmoat and Cussins to complete £200m South Shields site

Construction starts on final phase of Holborn regeneration
3 days ago

FRC probes accountants over Vistry South division reporting

Accounting watchdog probes conduct of two former Vistry employees after profit warnings
4 days ago

Costain builds record £7bn order book as profit jumps a third

Stronger margins and cash generation offset lower revenue as transport slows
4 days ago

Bid race starts for £3bn West Midlands framework

Firms fight for 20 spots on third generation building framework
4 days ago

North East Mayor to pump cash into arena and film studio jobs

Kick-start funding for Sunderland film studios and Gateshead arena schemes
4 days ago

Persimmon brick factory working 24/7 to meet demand

In-house materials investment helps boost profits
4 days ago

Two firms and site manager fined after asbestos blunders

HSE steps-in at demolition site riddled with asbestos
4 days ago

Market sounding starts on £46m Mid Wales school

Bids to be invited at end of May for for new Ysgol Bro Hyddgen campus
4 days ago

£150m Cambridge to Cambourne busway job heads for tender

Construction is expected to start in early 2027
5 days ago