70-year-old brickie breaks back in fall

Grant Prior 10 years ago
Share

A Lincoln builder has been handed a four-month suspended prison sentence after a self-employed bricklayer broke his back in two places after falling three metres from faulty scaffolding.

Robert Wilkin, 70, of Lincoln, was left paralysed from the waist down and confined to a wheelchair for the rest of his life following the incident at a warehouse in North Hykeham in February 2013.

Wilkin spent five months in hospital and has had to have his home especially converted so he can live on the ground floor.

An HSE investigation identified serious safety failings in the construction of the scaffolding by Rodney Foyster, who had subcontracted Wilkin to carry out the bricklaying work.

Lincoln Magistrates’ Court heard that Foyster was not trained in building scaffolding. He failed to check it was safe for use and failed to ensure the safety of workers once it was in use.

Foyster was hired to fix a wall that had been damaged at the warehouse after a lorry had reversed into it and had sub-contracted Wilkin for the bricklaying.

Foyster bought and erected the second-hand scaffolding before Wilkin was appointed.

Scaffolding towers were positioned both on the inside and the outside of the warehouse.

Wooden boards were removed from the tower on the inside and used to form a makeshift bridge between the two towers.

When the incident happened, Wilkin’s son, Damien, climbed the ladder to the top of the scaffold tower inside the building and successfully made it across the makeshift bridge to the outside scaffold tower.

But when Wilkin climbed the ladder, he fell from the wooden boards onto the concrete floor three metres below, suffering life-changing injuries.

Foyster, 56, of Lincoln, was sentenced to four months in prison, suspended for 18 months, ordered to carry out 200 hours worth of unpaid community work.

He was also ordered to pay £2,941 in costs after pleading guilty to safety breaches.

Speaking after the hearing, HSE inspector Martin Waring said:

“Our investigations revealed a catalogue of errors made by Mr Foyster in the assembly of this scaffolding – something he was neither qualified for nor competent in doing.

“There were numerous defects such as no edge protection, poor ladder safety and insufficient access onto the scaffolds.

“Mr Wilkin has unfortunately paid for this lack of care with his health, having been left paralysed for the rest of his life.”

Wilkin said: “I don’t remember much about what happened after I fell. Lots of people were rushing about and it took the ambulance crew about 20 minutes to get me onto a back board because I had fallen in an awkward place between pallets of bricks.

“I had an operation to fuse together my spine which was fractured in two places. I remember being in a lot of pain and was on morphine and sleeping tablets.

“Within a couple of days I was told it was unlikely I would ever walk again and I’ve been in a wheelchair ever since.

“My hobbies used to be collecting antiques, walking and gardening but I can’t do these things anymore. I find this all very difficult as I used to be very active.

“My life has been ruined because I can no longer do the things I used to do. I can’t go out on my own or drive. I feel my freedom has been taken from me and it’s been really hard on my family.”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
10 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
7 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
17 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
18 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
18 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
18 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
17 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
18 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
3 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services