Balfour Beatty Rail Projects has been fined £350,000 after a Thameslink rail worker suffered serious burns in London.

The case was brought by the Office of Rail Regulation after the rail worker contacted a 25,000 volt overhead line near Cricklewood in March 2011.

Rail workers subcontracted by Balfour Beatty were installing high voltage cable next to overhead lines in North West London.

They were working at height on cherry-pickers, moving along the track and installing the cable alongside an existing overhead wire.

One of the high voltage overhead lines which crossed the site had not been isolated.

Those working on the site were unaware of this and the risk to their safety.

As a worker checked the distance between the newly installed cable and overhead wire, he made contact with the live wire and suffered 45% burns which required extensive skin graft surgery.

The sentencing at Harrow Crown Court follows an extensive ORR investigation which found Balfour Beatty had failed to properly plan the work, and had not provided sufficient instructions to workers or appropriate warning about the risk to their lives.

The court heard there was poor communication between the planning and construction teams, which meant Balfour Beatty did not request that Network Rail switch off the electric current from all relevant sections of the overhead wire.

Balfour Beatty had pleaded not guilty to charges brought in connection with the incident, but changed their plea to guilty after the fifth day of ORR’s evidence.

The firm was also ordered to pay £50,000 costs.

Ian Prosser, ORR’s Director of Railway Safety, said: “In this instance, an unacceptable management failure led to a rail worker suffering severe burns after coming into contact with the live overhead wire carrying 25000 volts, which could, and should have been switched off.

“ORR’s investigation revealed that Balfour Beatty’s arrangements fell well short of the standard expected for a construction company operating in a high risk environment.”

Latest news

Balfour Beatty fined £285,000 after scissor lift death

Court hears how crane pushed over platform killing one worker and seriously injuring another
8 hours ago

Timber roof dropped in flagship HS2 station design rethink

New Curzon Street aluminium panel design offers better fire safety and cheaper upkeep
4 hours ago

Plan in for 4,000 homes at Earls Court in London

£6bn scheme advances for London's largest development site
10 hours ago

Luton Town put in plans for new stadium

Construction to be completed by 2027 on new home for football club
8 hours ago

Henry Boot looking to new boss to boost construction

Construction turnover down as division behind schedule winning work
13 hours ago

Billington to expand Shafton works as order book swells

Low steel prices tempt clients to bring stalled projects to the market
13 hours ago

Network Plus Services doubles profit to £32m

Turnover at private equity-backed business tops £500m
13 hours ago

Coroner in training call after scissor-lift tragedy

Practical rescue training needed after worker crushed to death
1 day ago

Deal to re-start £37m Burnley flood defence job

VolkerStevin/Jacobs' Padiham scheme stalled when costs doubled
14 hours ago

Big public procurement shake-up put back to February

Government delays Procurement Act go-live date by four months
14 hours ago

Architecture boss joins Caddick as Design Director

Former DLA Architecture director Jason Clarke to boost contractor's design offering
23 hours ago

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
2 days ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
2 days ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
2 days ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
2 days ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
2 days ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
2 days ago

Bachy Soletanche rejigs business in new growth plan

Business split into two regional and a major projects division
2 days ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
5 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
5 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
5 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
5 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
5 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
5 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
6 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
6 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
6 days ago

Torsion to deliver £43m Leeds student scheme

Construction to start next month on latest project for joint venture
6 days ago

Go-ahead for London Barbican office to flats project

London developer Hub aims to create over 170 co-living homes
6 days ago

Traditional builders dominate £800m MMC framework

20 out of 22 places on modular housing deal go to local contractors
6 days ago

Contractor services