Subcontractor hit by £2.8m Costain retention row

Aaron Morby 10 years ago
Share

A major row on Costain’s £400m Greater Manchester waste facilities contract over retentions and work defects has left a specialist fighting for survival.

Preston waste engineering specialist TEG has suspended trading in its shares on the AIM market as it tries to negotiate further financial backing.

The firm said it had been in talks with Costain for two years to release a £2.8m retention held by the main contractor.

TEG won a £38m contract back in 2009 to provide four specialist composting facilities by 2011 as part of Europe’s largest waste PFI.

But alleged design faults have delayed completion of the facilities which are due to handle 175,000 tonnes per annum of green and food waste.

TEG has carried out remedial works for Costain in a programme of works to finish the contract.

A statement said: “As previously announced, whilst PI insurers have responded in relation to certain remediation costs, the company continues to bear the cost of its own EPC Division required to manage the conclusion of the contract.

“TEG has engaged recently in discussions with Costain in relation to the group’s overall financial position, the release of the retentions monies owed and TEG’s ability to continue to provide the requested remedial work under the contract.”

The company has been in talks with Costain regarding its financial position but was told on Monday that it would be unable to negotiate an exit from the contract.

Both firms remain in talks about the execution of the contract.

TEG said it now believed that there was no prospect of any retentions being released in the near future which would impact significantly on its working capital requirements.

In August, Costain revealed it had decided to exit the waste sector after it suffered losses from extra costs on the complex job.

Costain’s Natural Resources division suffered a £5m loss due to provisions to complete the legacy Greater Manchester Waste PFI contract awarded in 2007.

Of the forty-six waste facilities under the contract, at the time of its statement, thirty-six had reached final acceptance, three were seeking to obtain final acceptance, six were currently in the post-completion period and one remained to be completed.

Costain said design faults had been identified at four sites, including the site that remained to be completed and remedial work and testing was on-going in respect of that site which was expected to be completed in the second half of 2014.

Latest news

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
13 hours ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
16 hours ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
21 hours ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
21 hours ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
21 hours ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
20 hours ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
20 hours ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme
21 hours ago
Walker Modular Limited

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
21 hours ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
4 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
4 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
4 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
4 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
4 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
4 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
4 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
5 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
5 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
5 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
5 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
5 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
5 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
6 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
6 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
6 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
6 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
6 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
7 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
7 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
7 days ago

Contractor services