Subcontractor hit by £2.8m Costain retention row

Aaron Morby 11 years ago
Share

A major row on Costain’s £400m Greater Manchester waste facilities contract over retentions and work defects has left a specialist fighting for survival.

Preston waste engineering specialist TEG has suspended trading in its shares on the AIM market as it tries to negotiate further financial backing.

The firm said it had been in talks with Costain for two years to release a £2.8m retention held by the main contractor.

TEG won a £38m contract back in 2009 to provide four specialist composting facilities by 2011 as part of Europe’s largest waste PFI.

But alleged design faults have delayed completion of the facilities which are due to handle 175,000 tonnes per annum of green and food waste.

TEG has carried out remedial works for Costain in a programme of works to finish the contract.

A statement said: “As previously announced, whilst PI insurers have responded in relation to certain remediation costs, the company continues to bear the cost of its own EPC Division required to manage the conclusion of the contract.

“TEG has engaged recently in discussions with Costain in relation to the group’s overall financial position, the release of the retentions monies owed and TEG’s ability to continue to provide the requested remedial work under the contract.”

The company has been in talks with Costain regarding its financial position but was told on Monday that it would be unable to negotiate an exit from the contract.

Both firms remain in talks about the execution of the contract.

TEG said it now believed that there was no prospect of any retentions being released in the near future which would impact significantly on its working capital requirements.

In August, Costain revealed it had decided to exit the waste sector after it suffered losses from extra costs on the complex job.

Costain’s Natural Resources division suffered a £5m loss due to provisions to complete the legacy Greater Manchester Waste PFI contract awarded in 2007.

Of the forty-six waste facilities under the contract, at the time of its statement, thirty-six had reached final acceptance, three were seeking to obtain final acceptance, six were currently in the post-completion period and one remained to be completed.

Costain said design faults had been identified at four sites, including the site that remained to be completed and remedial work and testing was on-going in respect of that site which was expected to be completed in the second half of 2014.

Latest news

Plans unveiled for 70-storey Liverpool tower

Liverpool's tallest building will rise to 727ft
6 hours ago

FRC probes accountants over Vistry South division reporting

Accounting watchdog probes conduct of two former Vistry after profit warnings
13 hours ago

Costain builds record £7bn order book as profit jumps a third

Stronger margins and cash generation offset lower revenue as transport slows
16 hours ago

Bid race starts for £3bn West Midlands framework

Firms fight for 20 spots on third generation building framework
16 hours ago

North East Mayor to pump cash into arena and film studio jobs

Kick-start funding for Sunderland film studios and Gateshead arena schemes
16 hours ago

Persimmon brick factory working 24/7 to meet demand

In-house materials investment helps boost profits
16 hours ago

Two firms and site manager fined after asbestos blunders

HSE steps-in at demolition site riddled with asbestos
16 hours ago

Market sounding starts on £46m Mid Wales school

Bids to be invited at end of May for for new Ysgol Bro Hyddgen campus
17 hours ago

£150m Cambridge to Cambourne busway job heads for tender

Construction is expected to start in early 2027
2 days ago

Manchester city council JV to build 1,600 homes

Pension fund backs city housing push on seven sites
2 days ago

Graham set for £100m Cardiff Crossrail phase one

City council to rubberstamp deal this month for Summer start
2 days ago

Go-ahead for 2,300-home scheme at former GSK London HQ

Reuse-first strategy to save 34,500 tonnes of embodied carbon in construction phases
2 days ago

Muse gets green light for office-to-apartments conversion

Latest stage of £500m regeneration of Wythenshawe.
2 days ago

Habiko submits first 240-home scheme in Warrington

PIC, Muse and Homes England partnership lodges plans for twin affordable housing blocks
5 days ago

Probe launched after Falcon tower crane collapse

Luffing jib tower crane collapsed on Hill Group housing site
5 days ago

McLaren tops contracts league on data boom

Mega datacentre deal drives firm to pole position in February rankings
5 days ago

MTX wins £33m Welsh modular hospital revamp

Work is due to start on site in the next few weeks
5 days ago

North West landlord unveils £428m contractor panel

Morgan Sindall, Robertson and Seddon among major lot winners
5 days ago

Housing drags down fledgling construction recovery

Buyers report return to accelerated downturn but still hopeful for year ahead
6 days ago

Taylor Wimpey to spend £150m this year on safety defects backlog

House builder reveals cavity barrier defects behind most of £222m jump in provisions
6 days ago

Near-1,000 homes approved for Isle of Dogs site

42-storey co-living tower and 27-storey affordable housing block backed
6 days ago

Tower crane collapses in London

Site photos show aftermath of failure
6 days ago

Go-ahead for Preston 500-home plan at shopping precinct

St Johns shopping centre to be demolished in city centre regeneration plan
6 days ago

Keltbray lays foundation for HS2 Curzon Street station

Vast 2,011-pile operation finished as Birmingham build powers on
6 days ago

John F Hunt wins Euston Tower demolition

Specialist will take-down 36-storey tower in technically challenging contract
6 days ago

GMI confirmed for green Manchester office scheme

35 Fountain Street will feature cross‑laminated timber
7 days ago

Trio bag £1bn concrete road replacement deal

Kier, Graham and Sisk win 6-year legacy concrete road framework
7 days ago

Former Balfour chief to become Barratt Redrow CEO

Dean Banks to take helm at house builder later this year
7 days ago

Galliford Try lifts full-year outlook after 20% profit surge

Margins strengthen across Building and Infrastructure as order book hits £4.1bn
7 days ago