Raymond Harper, a sub-contracted plant operator, had a narrow escape when the raised arms of his 20-tonne excavator hit the live power line as he drove up a slope on the Scottish Water site in Bathgate.
The contact sent an 11,000-volt current through the excavator, the overhead cable split and the live cable landed on the ground close by other workers.
Had Harper made any efforts to leave the vehicle, he could have sustained serious or even fatal injury. Luckily he remained in his cab.
The incident, on 25 June 2011, happened on a site under the control of engineering firm George Leslie Ltd, which was responsible for carrying out emergency ground works and repairs to water pipes.
Livingston Sheriff Court heard that Harper had not been directed to the main site office where he would have received induction, and as a result he proceeded to operate on the site without having been made aware of any hazards, including the overhead power line.
The HSE investigation concluded that the company, as principal contractor, had:
- failed to properly assess the risks to drivers on the site
- failed to identify areas on site where vehicles could safely move, in particular when required to pass under live overhead electrical power cables
- failed to provide and maintain machinery and safe systems of work
- failed to isolate the overhead powerline, erect sufficient barriers or display warning notices providing cross bar clearance heights and directions to drivers
- failed to ensure that any vehicle needing to pass under live power lines had height restrictors fitted to any parts that could be elevated
- failed to ensure that workers visiting the site were provided with adequate instruction and supervision to ensure that they completed a site induction programme and were made aware of the presence of live overhead cables
The court was told that the company had previously been fined £25,000 after a prosecution in Feb 2004 relating to an incident where an employee was killed after falling from height.
George Leslie Ltd, of Barrhead, Glasgow, was fined £6,600 after pleading guilty to a safety breach
Following the case, HSE Inspector Ritchie McCrae, said: “This incident was entirely preventable and could easily have resulted in serious or fatal injuries.
“George Leslie Ltd was the principal contractor on site and, as such, had a duty of care to ensure the safety of all workers on site, including the sub-contrators.
“Regardless of the circumstances, there is no excuse for the inadequate level of planning and control which should have eliminated or controlled the risk of contact with an overhead power line and allowed the work to be completed safely.”