Two tonne temporary roof blown off scaffold

Grant Prior 10 years ago
Share

Specialist contractor Pyeroy has been fined £10,000 after the roof of a temporary extension at Lynemouth Power Station was blown off in high winds.

A 25-metre span of the roof, that was around six metres long and weighed two tonnes, was blown off its eight-metre high scaffolding end supports on 23 December 2012.

It struck the roof of an adjacent biomass shed before landing 50 metres away beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians.

Fortunately the timing of the incident just before Christmas meant that the normally busy road was deserted.

Bedlington Magistrates’ Court heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

In 2011 Pyeroy Ltd had been instructed by the owners of the power station to build a temporary extension to the biomass shed that was designed by an external scaffold design company.

This was dismantled in August 2011 once it was no longer required.

Then in May 2012, Pyeroy was asked to install another temporary extension, this time designed by its in-house design team. Although similar to the first structure, it was to be shorter and lower.

It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. But poor communication resulted in an incomplete design plan being used.

HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

Magistrates were told that on 22 December it was noted that the weather was worse than normal, with the winds picking up. This meant some of the sheeting on the structure needed to be re-tied.

The temporary roof was blown off its end supports early the following morning. It ended up straddling a safety barrier and a dry riser pipeline between the main delivery access road and the legs of an adjacent conveyor.

HSE inspectors concluded that Pyeroy had failed to ensure those involved in the construction of the extension had the necessary knowledge and experience to do the work.

The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

Pyeroy of Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to safety breaches.

After the case, HSE inspector Andrew Woodhall said: “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

“It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

“Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof.

“As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

Latest news

Balfour Beatty terminates Danny Sullivan labour deals

Around 500 workers on HS2 will be moved to alternative agencies or be taken on direct
21 hours ago

Trio face prosecution after Hinkley site death

Main contractors and client to face charges over death of site supervisor
21 hours ago

Buyers see recovery in house building sector

But civil and commercial work still in the doldrums
1 day ago

Apprentice saws-off thumb on hotel refurb site

Court hears how digit was reattached and teenager continued training with another firm
1 day ago

Laing O’Rourke tops June contracts league

£919m animal super lab dominates new orders
2 days ago

TSL turnover smashes £500m as profit almost trebles

Data centre and logistics contractor rises high on surging demand
2 days ago

Gleeson Homes chief exec leaves business after restructure

Management revamp after "challenging" year
2 days ago

Green light for 1,600-home Oldham town centre overhaul

Plans for over 1,600 homes across six regeneration sites approved
2 days ago

DSM wins Norwich city centre clearance job

Anglia Square shopping centre clearance for £300m scheme
2 days ago

13-year-old becomes UK’s youngest qualified digger driver

Grandson of Gallagher Group chairman sets industry record
2 days ago

Cubby reborn in £12m Svella-backed takeover

£50m revenue target set as 14 firms combine under new Cubby Group banner
3 days ago

North East NHS trusts plot £3bn health estate overhaul

Market engagement begins for major construction push across four trusts
3 days ago

HG goes green on cranes in £1.2m switch to battery power

Diesel-free crane drive cuts fuel bills by 94%
3 days ago

Developer fined £165,000 for fire safety failings

Firm ignored fire safety orders on apartment job in Preston
3 days ago

Bidding to start for £1.8bn North West framework

Contractors invited to bid for latest Procure Partnerships deal
3 days ago

Hill hits record £90m profit as homes pipeline swells

Build-to-rent push and £4.8bn contracting book to fuel next growth phase
3 days ago

Rayner unveils £39bn plan to build 300,000 social homes

Council building revival and rent reform feature in social and affordable homes plan
4 days ago

Keltbray bounces back with £3.2m profit

Tighter controls and smarter project selection fuel strong turnaround
4 days ago

VINCI JV wins 500-home twin town centre revamps

Chester Northgate phase 2 and Northwich Weaver Square schemes move to delivery stage
4 days ago

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
5 days ago

How to see your stories on the Enquirer

Join our Suppliers and Buyers directory to get your news published
4 days ago

Henley lands Midland Mill revamp on Leeds tower scheme

Restoration of 18th-century mill kicks off on South Bank regeneration project
4 days ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
4 days ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
5 days ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
5 days ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
5 days ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
5 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
5 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
5 days ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
5 days ago