An international construction firm has been sentenced after admitting multiple safety issues at a Manchester site where it was carrying out a shop refurbishment. 

Betcat International Limited is based in Seville, Spain, but has offices in locations around Europe, including London.

The firm was hired by high street clothing chain Mango to carry out refurbishment and alteration works at its store on Market Street, Manchester.

The project involved the full refurbishment of the multi-storey retail unit, including structural alterations to facilitate the installation of two new staircases, the installation of a lift shaft, and the removal and infilling of an existing stairway.

The site manager was employed by Betcat, and all of the operatives on site were subcontractors.

On 29th July 2014, an HSE inspector visited the site to investigate safety concerns raised by a member of the public and to carry out an inspection of the construction works.

A number of issues were identified during the visit:

–           Two operatives were seen using tower scaffolds which had not been properly erected with full edge protection. One of the tower scaffolds was also balanced at an angle on some steps so that the working platform was not level.

–           Another operative was observed walking up the new steel staircase from the ground floor to the 1st floor. The staircase had no handrails or any form of edge protection to prevent falls from height.

–           On the 2nd floor of the building, a man was observed standing on a structural steel beam which was spanning the large lift shaft opening in the concrete floor. There was nothing to stop this man from falling through to the floor below. The standard of guarding around the opening was poor on each floor and access was not prevented. There were also materials being stored in the area, indicating that operatives were approaching the opening frequently to retrieve materials.

–           The site was heavily congested with materials, waste and other debris. There seemed to be no clear walkways and the lighting levels were very low.

–           The toilet had been removed and there was no other toilet on site; nor were there any washing facilities. No other arrangements had been made regarding the provision of welfare facilities whilst the bathroom was being re-tiled and re-plumbed.

–           An operative was seen using a small mitre saw which had no guard over the blade and he was pushing timber floor boards through the exposed blade by hand.

–           A wood saw which was set up for cutting timber products had no dust extraction system fitted and there were piles of dust on all surfaces and large amounts of dust in the air.

–           There were no fire alarms on site and the only fire extinguishers were out of date, having been left over from the previous shop.

The HSE inspectors served six Prohibition Notices and two Improvement Notices, along with a Notification of Contravention.

Trafford Magistrates’ Court heard all the issues were satisfactorily addressed by the company following HSE’s intervention.

Betcat International Limited of London SE1 pleaded guilty at Trafford Magistrates Court to safety breaches and was fined £40,000 with £3,761 costs.

HSE inspector Laura Moran said after the case: “Betcat International Limited completely failed in its duty to protect its workers, its subcontractors and visitors to its site from harm.

“Given the range of serious breaches identified, it is very fortunate that nobody was injured or even killed while working on this site.

“I’d therefore like to thank the member of the public who alerted us to the work, and may well have prevented a serious injury.”

Latest news

Coroner in training call after scissor-lift tragedy

Practical rescue training needed after worker crushed to death
2 hours ago

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
10 hours ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
10 hours ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
10 hours ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
11 hours ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
11 hours ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
11 hours ago

Bachy Soletanche rejigs business in new growth plan

Business split into two regional and a major projects division
13 hours ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
3 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
3 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
3 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
3 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
3 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
3 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
4 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
4 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
4 days ago

Torsion to deliver £43m Leeds student scheme

Construction to start next month on latest project for joint venture
4 days ago

Go-ahead for London Barbican office to flats project

London developer Hub aims to create over 170 co-living homes
5 days ago

Traditional builders dominate £800m MMC framework

20 out of 22 places on modular housing deal go to local contractors
5 days ago

Dubai contractor sells 15% stake in Costain

ASGC sells stake for £38m after investing £25m in fund raise four years ago
5 days ago

Amazon to invest £8bn in hyperscale datacentres

Data centre sector heats up as cloud computing giant AWS unveils big expansion plans
5 days ago

Plan lodged for Square Mile’s fifth tallest tower

54-floor 99 Bishopsgate tower will provide 1 m sq ft of office space
5 days ago

Morgan Sindall pulls off contracts league double

Firm swoops to top monthly and 12-month contracts league rankings
6 days ago

Hadden Construction goes into administration

66 jobs lost at £30m turnover Perthshire contractor
6 days ago

McAleer & Rushe wants to meet subcontractors across Scotland

Register now for Meet the Buyer event: Full list of suppliers wanted
5 days ago

Construction output slide in July ends two-month growth spurt

Recovery stutters along as construction activity dips 0.4%
5 days ago

Laing O’Rourke finance chief to join plastic products firm

Rowan Baker to join Essentra in November
5 days ago

Tight cost control returns Laing O’Rourke to profit

Group margin back to 1.9% as orders swell to record £10.8bn
6 days ago

Kier to noise-proof 20,000 homes around Heathrow

Eight-year programme will involve new windows, doors, loft insulation and upgrade ceilings
6 days ago

Contractor services