Balfour exits £75m north west rail upgrade

Aaron Morby 10 years ago
Share

Balfour Beatty has pulled out of a planned project to electrify the railway line between Preston and Blackpool.

The decision to drop out of the remaining phases of the £75m northern hub electrification programme came after a review found work was unlikely to be delivered on time and to budget.

Balfour Beatty had worked on two completed phases of electrification to lines in the North West, with five others yet to be finished.

Its job to upgrade the Preston to Blackpool line was scheduled to be completed by May 2016.

A Network Rail spokesperson said: “Network Rail has carried out a review to ensure we have the most efficient deployment of resources to deliver the next phases of this key improvement.

“By mutual agreement Balfour Beatty will be leaving the partnership delivery of North West electrification.

“This is the appropriate time following the completion of phase two between Manchester, Liverpool and Wigan.

“We will be retaining Balfour Beatty’s design services and a new contractor will be appointed shortly.”

Balfour was awarded the seven-year framework deal back in February 2014 for the design and installation of all electrification equipment for routes between Manchester-Preston-Blackpool and Manchester-Stalybridge.

The work packages were estimated to be worth more than £75m and followed on from Balfour’s involvement in Phases 1 and 2 of the programme covering the Liverpool-Manchester route.

Balfour said: “In the first half, phase 2 of the North West electrification project reached practical completion.

“However following a review of future schemes in the North West, it was concluded that the proposed alliance was unlikely to meet its stated objectives of delivering the scope of the work on time and to budget.

“In July, it was agreed with Network Rail that Balfour Beatty would not continue with the alliance framework for phases 3-7.

“We are working closely with Network Rail on the transition.”

Network Rail’s ambitious electrification plans came under scrutiny earlier this year as the Government became gravely concerned about out-turn costs

In June, it was announced electrification of the Midland Mainline and TransPennine routes would be paused amid soaring costs and missed targets.

The Government also said Network Rail would now review at least one fifth of the planned projects in the five-year plan in an attempt to control future spending.

But is said it remained committed to electrification projects for the more politically sensitive Northern Powerhouse.

A Department for Transport spokesperson said: “We are clear that we expect Network Rail to deliver electrification to Blackpool as planned so that passengers can benefit as soon as possible.

“It is for Network Rail to manage its relationship with contractors as necessary.”

 

Latest news

Cubby reborn in £12m Svella-backed takeover

£50m revenue target set as 14 firms combine under new Cubby Group banner
42 minutes ago

North East NHS trusts plot £3bn health estate overhaul

Market engagement begins for major construction push across four trusts
36 minutes ago

HG goes green on cranes in £1.2m switch to battery power

Diesel-free crane drive cuts fuel bills by 94%
22 minutes ago

Developer fined £165,000 for fire safety failings

Firm ignored fire safety orders on apartment job in Preston
13 minutes ago

Bidding to start for £1.8bn North West framework

Contractors invited to bid for latest Procure Partnerships deal
3 minutes ago

Hill hits record £90m profit as homes pipeline swells

Build-to-rent push and £4.8bn contracting book to fuel next growth phase
16 hours ago

Rayner unveils £39bn plan to build 300,000 social homes

Council building revival and rent reform feature in social and affordable homes plan
24 hours ago

Keltbray bounces back with £3.2m profit

Tighter controls and smarter project selection fuel strong turnaround
24 hours ago

VINCI JV wins 500-home twin town centre revamps

Chester Northgate phase 2 and Northwich Weaver Square schemes move to delivery stage
24 hours ago

80 energy projects unlocked as Ofgem backs grid expansion

£24bn energy networks deal gets green light from regulator
2 days ago

How to see your stories on the Enquirer

Join our Suppliers and Buyers directory to get your news published
24 hours ago

Henley lands Midland Mill revamp on Leeds tower scheme

Restoration of 18th-century mill kicks off on South Bank regeneration project
23 hours ago

New boss at Eric Wright Civil Engineering

Gavin Hulme takes top job as Diane Bourne moves to group role
1 day ago

Pinewood submits £1bn data centre plan

Studio giant adds green and learning spaces to tech hub blueprint
2 days ago

Record results after TClarke goes private

Britain's biggest M&E contractor flourishes after de-listing
2 days ago

Dalkia lands £200m nuclear maintenance deal

1,000 nuclear FM staff to join M&E contractor
2 days ago

Construction comeback to outpace wider economy

Arcadis forecast fueled by spending review optimism
3 days ago

First steel goes up on giant car battery site

Severfield gets to work on McAlpine Somerset site
3 days ago

Permasteelisa wins cladding deal on Bovis city tower

Facade specialist lands package at 60 Gracechurch Street
2 days ago

Fox buys recycled asphalt specialist Fisher

Acquisition adds major recycled asphalt capacity in north west
3 days ago

Major Building Safety Regulator shake-up to end tower delays

HSE stripped of control and top fire chiefs brought in to fast-track stalled schemes
3 days ago

Hinkley trio sign Sizewell civils deal

Balfour,Bouygues and Laing O'Rourke form Civil Works Alliance for new power station
3 days ago

£3.9bn data centre plan for Ravenscraig steelworks

Green energy to power massive new steel to silicon AI campus
3 days ago

Breakthrough on HS2’s second longest tunnel

8.4 mile Northolt to Old Oak Common drive completes
3 days ago

Neilcott on fast-track to debt-free employee ownership

£22.5m loan nearly paid down after big profit year
3 days ago

TfL kicks off race for £700m Tube station upgrade

South Kensington and Elephant & Castle top the pipeline list
3 days ago

Corbyn Plant Hire fleet goes under the hammer

Kit to be sold off by sister firm to collapsed groundworks contractor
3 days ago

Government wields procurement stick on late payment

New rules would block slow payers from bidding on big public jobs
6 days ago

Hercules buys power line labour firm for £15.7m

Labour supply specialist snaps up Advantage NRG to tap booming electricity upgrade market
6 days ago

Universal bid to fast-track planning for theme park

Entertainment giant eyes 2026 start at Bedford site
6 days ago