Culvert collapses on workers

Grant Prior 6 years ago
Share

Two building firms have been fined after a man was seriously injured when a structure that allows water to flow under roads collapsed on him.

Maidstone Crown Court heard that Kent County Council appointed Enterprise to replace a damaged brick culvert under Tudely Lane Tonbridge.

Enterprise in turn appointed Topbond to do the majority of the work.

A culvert is an embedded structure, usually surround by soil and can be made from steel, brick or reinforced concrete or other material and is used to transport water underground from one side of a road or railway to another.

The HSE prosecuting told the court that on 27 January 2012 water was being pumped out of the work area when three workers including 63-year-old Michael Skitt of Kingsnorth, Ashford, entered the area between two culverts in order to clear a channel for the remaining water to flow toward the pump head.

They had begun to clear loose material, but had not started digging.

Shortly after they entered the area, the old brick culvert collapsed. One man jumped clear, another was hit but managed to release himself, but Skitt was trapped and injured.

Skitt suffered multiple injuries including shoulder blade breaks, an open shin break and a dislocated knee.

Ongoing issues with his foot may see him need further operations. Skitt spent 26 days in hospital and has now had to give up full time work and walks with a stick.

HSE said the stability of the structure was not assessed adequately, nor sufficient planning undertaken to ensure adequate control measures were in place.

Its investigation found that originally the old culvert was to be totally demolished early in the work, when this was changed the implications of uncovering half of the damaged culvert and therefore loading it unevenly and undermining it were not managed.

Although culvert repair/replacement is a relatively unusual construction job, the collapse of excavations and structures is common and the court heard the defendants in the case were made aware of the potential of collapse by the original designers/engineers several times.

The culvert could have been demolished early in the work, failing this, there are a number of commonly used ways to support structures during construction work.

Enterprise (AOL) Ltd of Halley Road, Oxford admitted safety breaches and were fined a total of £90,000 and ordered to pay an additional £22,876 costs.

Topbond PLC, of Sittingbourne, Kent also admitted safety breaches and were also ordered to pay £22,876.60 costs and were fined £70,000.

After the case, HSE inspector Nicola Wellard said: “This is a sad case that has changed at least one man’s life for ever. The culvert was being replaced because it had been damaged previously.

“Just this one piece of information should have been enough to ensure both contractors assessed the stability of the culvert throughout the work and took appropriate measures to ensure people were protected from the risk of collapse.

“These risks are well known and the fact that the two other men escaped without serious injury was just pure luck, this could easily have been a multiple fatality.”

Latest news

Construction leaders launch inflation busting taskforce

All sides of industry urged to work together rather than row over price hikes
13 hours ago

Track worker killed by train was controller of site safety

Distracted rail worker "lost awareness of his position relative to the line the train approached on"
11 hours ago

MechFS went down owing £9.5m to supply chain

Subcontractors left holding millions in worthless invoices
18 hours ago

HG Construction profit jumps 50% to £25m

Multi-storey homes and student accommodation jobs drive sales to record £243m
18 hours ago

Go-ahead for Newcastle’s largest build to rent project

Work to start on 14-storey flats complex in the autumn
17 hours ago

Contractors wanted for £288m Northumbrian Water frameworks

Ten lots up for grabs under latest major civils deal
18 hours ago

Plans in for 142-room Exeter net zero hotel

RED Construction to build first of hotel developer's planned chain of net zero hotels
17 hours ago

Rail workers vote to strike over maintenance job cuts fears

Network could grind to a halt next month
17 hours ago

Race for £100m Immingham ferry terminal job

AB Ports aims to start work in mid 2023
2 days ago

Sisk wins Stockport £60m Weir Mill restoration

Work to start next month on 250 flats scheme
2 days ago

Developer swoops for 1,000-flats landmark Leeds site

Revised plans to be submitted by the end of the year for start soon after
2 days ago

Dominvs seals £173m funding for 713-bed student job

HG Construction to start major Hammersmith student complex in November
2 days ago

Briefings start for £1bn Midland Mainline Electrification plan

Market engagement starts for next seven sections covering 139km route to Sheffield
2 days ago

Forterra pushes back £27m factory refurb plan

Supply chain shortages hit project as brick prices rose another 12% last month
2 days ago

Speedy Hire results slowed down by KPMG

Hire giant left "frustrated and disappointed" by delay request from auditor
2 days ago

London office starts set to surge over next 6 months

Deloitte Crane Survey predicts jump in starts in Capital despite high building costs
3 days ago

Fit-out firm BW Workplace slips into the red

£5.2m backdated R&D tax credit deal lifts after tax performance
3 days ago

Hinkley Point delayed another year as costs rise by £3bn

Covid blamed for construction delays and cost increases
6 days ago

Competition probe launched into Bouygues’ Equans takeover

Bouygues is hoping to finalise acquisition later this year
3 days ago

TfL seeks developers for trio of over-station sites

Plum sites at Bank, Paddington and Southwark come with consent for 600,000 sq ft
3 days ago

Underwater drone used to check offshore wind farm foundations

Underwater robots deployed for inspection and maintenance work
3 days ago

DfE to unveil plans for school procurement shake-up

Supply chain summit to be held next month in Birmingham on future of schools frameworks
6 days ago

Plan for £100m clifftop hotel and flats in Newquay

Developer Salboy's landmark scheme to go in for planning shortly
6 days ago

Top 30 M&E contractors set for growth – ranking

Major M&E firms prepare for work surge after riding out pandemic
6 days ago

Former Mace boss joins Taylor Wimpey board

Mark Castle takes on another non-exec role
6 days ago

ISG starts £28m duo of Yorkshire leisure centre jobs

Harrogate and Knaresborough leisure centre jobs get underway
6 days ago

HS2 workforce surges to 25,000 jobs milestone

Over 2,500 firms form the HS2 supply chain
6 days ago

Green light for 1.4m sq ft Yorkshire logistic hub

Work at the site, located 24 miles from Leeds city centre, is expected in September.
6 days ago

Contractors lift tender margins to 9% on bids in the Capital

Developer Landsec to press ahead with trio of London office schemes this year despite cost inflation
7 days ago

Fire safety work plunges Countryside to £182m loss

Countryside Partnerships forms dedicated division to handle retrofits on a 123 buildings
7 days ago

Contractor services