Fire door warning following fatal tower block blaze

Grant Prior 8 years ago
Share

Housing manager Lewisham Homes has been fined £40,000 for breaking fire safety laws following a fatal blaze in a Deptford tower block in which two women died.

Security door: This image shows the steel security door fitted to the flat where the fire started (image ©London Fire Brigade)
Security door: This image shows the steel security door fitted to the flat where the fire started (image ©London Fire Brigade)

Lewisham Homes were sentenced at Woolwich Crown Court after pleading guilty at an earlier hearing to failing to properly maintain fire doors and failing to review an existing fire risk assessment.

Sentencing the housing manager, His Honour Judge Justice Christopher Hehir said the prosecution should act as a “wake up call” to the risks of not maintaining fire safety features in residential high rise buildings.

He also stated that had Lewisham Homes been a profit making company and not a not-for-profit organisation the fine would have been considerably higher.

Lewisham Homes is an Arms Length Management Organisation, which manages a significant proportion of the housing stock owned by the London Borough of Lewisham.

The prosecution was brought by the London Fire Brigade following the blaze in February 2011.

More than 100 firefighters were called to the fire at Marine Tower on Abinger Grove in Deptford which started in a flat on the 16th floor.

Crews rescued two women from another flat on the same floor but  both were pronounced dead at the scene.

The fire was started deliberately and in 2012 Sandra Clarke, a resident in the flats, was prosecuted and convicted of two counts of manslaughter at Woolwich Crown Court.

An investigation by fire safety officers revealed serious safety failings relating to the failure to maintain fire doors, which directly contributed to the spread of the fire.

The flat in which the fire started was fitted with a metal security door which prevented  the existing fire door behind it from being closed.

The severity of the fire and the lack of protection between the flat where the fire started and the building’s communal areas meant fire and smoke rapidly entered the lobby and also the adjacent flat in which the two women who died were trapped.

Speaking after the sentencing Assistant Commissioner for Fire Safety Neil Orbell said: “Living in a high rise building is not more dangerous than living in a house but this tragic incident is a stark reminder of the potentially lethal consequences of failing to maintain the vital safety features, such as fire doors, which are built into them to give you protection from fire.

“Sadly in the case of Marine Tower, this life saving engineering was not maintained, causing fire and smoke to spread rapidly into the lobby area and ultimately into a flat where two women, trapped by the fire, tragically died.

“I absolutely agree with the Judge. This prosecution should act as a ‘wake up call’ and send an urgent message to all housing providers to ensure the fire safety features in their buildings are properly maintained.

“If they are not, housing providers, managers, landlords and building owners should all be warned that we will not hesitate to prosecute if we find they are putting people’s lives at risk.”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
14 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
10 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
21 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
21 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
21 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
21 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
20 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
21 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services