Kier quits £170m London Ram Brewery job

Aaron Morby 5 years ago
Share

Kier has become the third contractor in a week to walk away from a major project after failing to agree a final contract sum with the client amid rampant cost inflation.

Construction of the new river wall and basements are complete with work on the first three concrete cores now underway
Construction of the new river wall and basements are complete with work on the first three concrete cores now underway

The firm has been working on the £170m first phase of The Ram Quarter, a major flagship regeneration scheme in the London Borough of Wandsworth, since securing the project last summer.

At present it is completing enhanced enabling works on the site for Chinese developer Greenland, which aims to redevelop the old Young’s brewery site and build luxury flats over three phases.

Faced with spiralling cost inflation in the capital, Kier has struggled to get its price down, quoting just below £200m for phase one.

In an attempt to drive down costs further Shanghai-based developer and builder Greenland called on Kier to abandon its supply chain in favour of sourcing as much of the project as possible from China, according to project sources.

It is understood Greenland explored using Chinese suppliers for cladding, drylining and even kitchens and bathrooms.

But now after detailed consideration Kier has decided to walk away and is expected to leave the site in April.

The firm follows Morgan Sindall and Bouygues which have also decided to walk away from jobs for major blue chip clients at Cambridge University and Great Ormond Street Hospital respectively after contract negotiations faltered on price.

At the Ram Brewery, specialist contractor J Reddington is carrying out concrete works, which are now proceeding to forming three building cores for the housing element.

A source told the Enquirer: “It’s a real shame. Kier must have had around 50 personnel on the job. They were working hard to get a keen price because of the prospect of winning future high-rise phases.

“But they have clearly decided the risks are too high and it can’t be delivered to the client QS’s target cost.”

A Kier spokesperson said: “Client and contractor partners always have their own fixed points that cannot be breached in a moving market, but Greenland has been an excellent client to work with and we will support them until an alternative contractor is in place.”

A spokesperson for Greenland confirmed that Greenland and Kier had been unable to agree terms for ongoing work and Kier would now be concluding its involvement in the project in the coming months.

“We appreciate the work that Kier has done on The Ram Quarter project and we anticipate that works will be completed as scheduled with our new construction partner,” said Greenland.

The project has been complicated by section 106 agreements, which require that the old brewery is repaired and restored before flats can be occupied on the site.

Work has not advanced on this part of the project, which could cost up to £30m to complete.

dev11

Phase 1 is due for completion in early 2017

home11

Latest news

Campaigners win court fight to block £1.7bn Stonehenge tunnel

High Court judge quashes development consent granted by Transport Secretary Grant Shapps
22 hours ago

£350m Manchester twin skyscraper plan approved

Twin 56-storey residential towers to join Great Jackson Street cluster
2 days ago

Ballymore strikes deal for 2,800-home West London site

Partnership deal with Sainsbury's for 18-acre canalside site at Ladbroke Grove
1 day ago

Utilities firm Fulcrum plunges to £11.5m loss

Firm hit by second wave lockdowns delaying contract awards and mobilisations
1 day ago

Green light for £100m UK Holocaust Memorial building

Work to start later this year on large memorial building next to Parliament
1 day ago

Government pledges another £81m for cycle lanes

Highway Code to be revamped to prioritise cyclists
1 day ago

Long Scottish Covid lockdown cost Robertson £11.5m

Private building group plunged into £6.1m trading loss by 3 month lockdown
2 days ago

Funding deal green lights £40m modular student scheme

Financier Maslow Capital backs Audley Modular Student Living’s latest scheme in Edinburgh
1 day ago

North East contractor stops work on sites

Kapex Construction staff confirm they are no longer working for the company
2 days ago

Construction Manager of the Year finalists revealed

Full list of 77 of the industry's brightest talents
2 days ago

Record £860m pumped into 1,000 flood schemes this year

New six-year flood and coastal erosion investment plan commits to record £5.2bn spend
2 days ago

Forterra to spend £27m on high-end brick factory

Brick and block producer closes Bison precast site in face of margin pressure on 'grey concrete' products
2 days ago

Scottish retention reform plan put to Government

Government working group recommends ringfenced accounts and automatic retention release
2 days ago

Scaffolder hits overhead power line with pole

Contractor fined £333,333 after accident at commercial glasshouse site
2 days ago

Contractor hunt starts for Thames flood scheme

Contracts worth £275m up for grabs
3 days ago

CBRE pays £960m for 60% stake in Turner & Townsend

Deal values consultant at £1.6bn
4 days ago

Tetra Tech buys M&E consultant Hoare Lea

More than 900 staff to switch over to fast-growing US consulting group
3 days ago

Tideway breakthrough links all three tunnel sections

Key 75m connector tunnel breakthrough joins all tunnels for first time
3 days ago

Demolition and groundworks £1.6bn framework launched

Pagabo to hold webinar next month for interested companies: Register now
4 days ago

Go-ahead for £18m revamp of Army & Navy warehouse

Architect SPPARC redesigns historic Westminster site
3 days ago

Student rooms developer to strip HPL cladding from 22 buildings

Unite says cladding retrofit to cost £96m over next three years
4 days ago

House builders start to flesh out net-zero plan

Industry commits to first zero-carbon ready homes by 2025
4 days ago

John Sisk doubles cash pile to £62m despite profit fall

Profit almost halves to £2.8m as margin squeezed to 0.7% last year
4 days ago

Plans go in for £48m Derby arena

Construction set to start early next year
5 days ago

Costain to lead “electric road” trial for HGV charging

Electric lorries could be charged on the move by overhead power lines
4 days ago

Willmott Dixon gets go-ahead for Oldham secondary school

Work to start on £22m town centre school immediately
4 days ago

Mobile crane hirer Cadman joins vegetable oil revolution

Whole fleet to be converted to diesel alternative by end of this year
4 days ago

Go-ahead for 27-storey tower next to Shard

Edge London Bridge hailed as first of a new generation of office towers in London
5 days ago

Firms primed for £50m Hertfordshire police HQ

Contest to start in October for Welwyn Garden City blue light job
5 days ago

Construction to grow 6.3% next year as rebound persists

Infrastructure and private house building to continue to drive growth despite materials and labour shortages
5 days ago

Contractor services