Nine shortlisted for £12bn HS2 civil engineering works

Aaron Morby 10 years ago
Share

HS2 has shortlisted nine consortia to bid for civil engineering packages worth a total of £7.1bn – £11.8bn between London and Crewe.

Phase one work has been divided into seven packages covering the 140-mile route from London to Birmingham.

Shortlisted bidders will be invited to bid for a maximum of four packages but will be limited to two contract wins.

Most bidders have opted to chase three or four work packages, although Bechtel, bidding alone, has limited its hunt to the £600m-£900m Brackley to Long Itchington Wood Green Tunnel South Portal (lot c3) as has the Acciona/Sisk/Lagan consortium.

HS2 civils package bidders
Tenderer Name Consortium Tender List(s)
Align Joint Venture Bouygues Travaux Publics, VolkerFitzpatrick, Sir Robert McAlpine, Lots: S2, C1, C2, C3
ASL Acciona Infraestructuras, John Sisk & Son, Lagan Construction Group Lot C3
Balfour Beatty VINCI BeMo (BBV) Balfour Beatty, VINCI Construction Grands Projets, VINCI Construction UK, VINCI Construction Terrassement, BeMo Tunnelling Lots: C1, C2, N1, N2
Catalyst Bechtel Lot C3
Carillion-Eiffage-Kier (CEK) Carillion Construction, Eiffage Genie Civil ,(previously Eiffage TP) Kier Infrastructure and Overseas Lots: S1, S2, C2, C3
Fusion Morgan Sindall Construction and Infrastructure,BAM Nuttall, Ferrovial Agroman (UK) Lots: S1, S2, N1, N2
LFM Laing O’Rourke Construction, FCC Construccion,J. Murphy and Sons Lots: C1, N1 ,N2
Momentum Infrastructure Dragados, Hochtief Infrastructure, GallifordTry Infrastructure Lots: S1,C2, C3, N2
SCS Skanska Construction (UK),Costain, STRABAG Lots: S1, S2, C1, N1
  • Lot S1 – ‘Euston Tunnels and Approaches’ (£600m – £900m)
  • Lot S2 – ‘Northolt Tunnels’ (£850m – £1.4bn)
  • Lot C1 – ‘Chiltern Tunnels and Colne Valley Viaduct’ (£800m – £1.3bn)
  • Lot C2 – ‘North Portal Chiltern Tunnels to Brackley’ (£800m – £1.3bn)
  • Lot C3 – ‘Brackley to Long Itchington Wood Green Tunnel South Portal’ (£600m – £900m)
  • Lot N1 – ‘Long Itchington Wood Green Tunnel to Delta Junction / Birmingham Spur’ (£900m – £1.5bn)
  • Lot N2 – ‘Delta Junction to West Coast Main Line Tie-in’ (£800m – £1.3bn)

All the packages will be let as two-part design and build contracts, to encourage innovation and flexibility in construction and design, with awards being made in 2017 for start on site the following year.

Firms that deliver the best results in terms of value and efficiency will be eligible to bid for work on an additional 40 miles between Birmingham and Crewe, due to open in 2027.

The announcement of shortlists came as the HS3 Hybrid Bill passed its crucial final reading in the House of Commons. It will now go to the House of Lords before receiving royal assent, putting the project on course for construction to start in 2017.

HS2 chief executive Simon Kirby said: Collaboration will be at the heart of everything we do.

“Together with our suppliers, we will create these opportunities while continuing to push for the best value and long term efficiency that will be essential to delivering this transformational project on time and on budget.”

He  also confirmed that HS2 has invited seven joint ventures to formally tender for enabling work, preparing sites for the start of construction and carrying out essential pre-construction activity such as utilities diversions and archaeological surveys.

In a further milestone for the wider project, HS2 also published details of engineering design work worth up to £500 million for developing the detailed plans for Phase Two, including Crewe to Manchester and Birmingham to Leeds, ahead of a formal route decision on Phase Two, expected in the autumn.

Applicants are expected to be shortlisted in the summer with the successful bidders appointed once the route has been announced.

Additional work covering stations and railway systems will follow over the course of the next year. 

Latest news

Skanska seals £273m delayed Broadgate office overhaul

Retained frame and six-storey extension to transform One Appold Street
14 hours ago

JRL lands £68m North London housing tower job

Long-stalled Brent 30-floor housing block job moves into delivery
14 hours ago

School building winners to give apprentice guarantees

Contractors called on to create 13,000 new training places
14 hours ago

DfT tests market for privately financed HS2 Euston station job

Market engagement opens on design, build, finance and maintain deal
1 day ago

Barhale secures hat-trick of Thames Water sewer schemes

Firm bags Brent Cross, Benson and Basingstoke development-led sewer upgrades
13 hours ago

Muse go-ahead for 1,600-home Solihull town centre reset

Demolition to start for Mell Square transformation
14 hours ago

Subcontractors wanted across the Midlands

Work available at latest Constructionline event
14 hours ago

Robertson Construction bounces back into the black

Contractor shakes off previous £13m loss year with £31m profit comeback
2 days ago

Glencar tipped for latest London data centre

Contractor to build next phase of £1bn Brent Cross campus
2 days ago

Muse to lead redevelopment of Wakefield shopping centre

Council moves to demolish The Ridings for 1,000-home quarter
2 days ago

Long-empty Southend HMRC tower set for 557-flat rebirth

Section 106 agreement paves way for construction start
2 days ago

RED starts revamp of Lincoln’s Inn Fields

First phase of refurbishment work at historic London site
2 days ago

Developer Salboy opens construction division to wider market

Salboy Construction will focus on time-critical and distressed housing schemes.
4 days ago

Balfour powers back to top of contracts league

World-first carbon capture power station lifts contractor up the rankings
5 days ago

Ardmore turns corner after bruising two years

Group forecasts £11m profit in 2025 after £41m loss and ACL administration
5 days ago

£3bn early works plan to kick-start major Parliament restoration

Seven-year phase one programme keeps rebuild options alive to 2030
5 days ago

15 firms bag £175m works Cumberland works deal

Up to £6m schemes to flow through three-lot structure to 2029
5 days ago

Hinkley MEH contractors ordered to fix fire safety failings

Safety inspectors issue enforcement orders against five contractors
5 days ago

Buyers believe construction has “exited its tailspin”

Industry confidence for this year on the rise
5 days ago

Caddick wins first deal on Wolverhampton city centre regen

Contractor lands first 331 homes on Smithgate site
5 days ago

£1bn London Cancer Hub expansion gets green light

Sutton approval unlocks 1m sq ft of labs near the Royal Marsden
6 days ago

ECO funding cliff edge sinks insulation contractor

92 jobs axed as South Coast Insulation falls into administration as policy pause hits installers
6 days ago

£17m reboot planned for Manchester One tower

Bruntwood SciTech plans to extend and modernise 1960s landmark
6 days ago

Octavius cleared to start £113m A46 Walsgrave junction job

Consent paves way for Autumn start on Coventry upgrade
6 days ago

Muck away firm fined after digger bucket hits worker

Grab hire specialist failed to prop tipper body properly during repair work
6 days ago

Data centre drain ramps-up M&E labour costs

London rates rising as contractors try to lure workers from data centre jobs
6 days ago

Government puts firms on alert for mega framework renewal

Eight-year deal for all Government major works given £120bn maximum spend
7 days ago

HG Construction starts £73m Wembley student rooms job

Gateway 2 approval unlocks start on 27-storey 609-bed project
7 days ago

Taylor Wimpey managing director jumps ship to Vistry

James Lidgate handed group development director brief
7 days ago

Green light for huge industrial scheme on old colliery site

Parkside scheme will contain 2.4m sq ft of logistics and manufacturing space
7 days ago