Northern Line Tube Extension cost to soar by £240m

Aaron Morby 8 years ago
Share

The developers of Battersea Power Station and Transport for London are locked in talks about who will foot an extra £240m bill for design changes to the Northern Line Extension station.

Original designs for over-station developments have been significantly revised
Original designs for over-station developments have been significantly revised

One of two new tube stations will be located on the Battersea Power Station redevelopment site within phase three of the scheme.

The Malaysia developers, who have already agreed to pay £200m towards the £1bn tube extension, now have decided to significantly increase the over-station development.

This has necessitated a far stronger station box design, which could add up to £240m to the final cost, according to a report in the London Evening Standard.

Last month, the Enquirer exclusively revealed the main tunnel drive starting date within the Battersea station box had been put back by six months.

At the time TfL said the programme had drifted because of some modifications to the work schedule but said the extension would be still be completed in 2020 as originally planned – although the date is understood to have slipped within the year.

Now it has been revealed that the delays have come from a major redesign of the station box to carry one of five major new buildings designed by architect Frank Gehry.

David Hughes, director of major programme sponsorship at London Underground, said: “Changes have been made to the proposed development at Battersea and to the new Tube station beneath.

“We are now working with Battersea Power Station to agree the necessary changes to the contractual arrangements between us to reflect these revised designs.

“These design changes will lead to an increase in the overall cost of the project and we are in constructive discussions with the developer about how this cost will be attributed.

“We are also working to deliver the project even more efficiently, further bearing down on costs.  But any suggestion that we are about to go to arbitration over this is incorrect.”

The change will also see joint venture contractor Ferrovial Laing O’Rourke’s £500m contract, awarded back in 2015, revised to cover increased work.

Under the original masterplan the station was due to have a modest station entrance over-site development. But the new plan is to fully incorporate the station into Ghery’s Prospect Place building complex, delivering passengers direct into one of its most striking buildings.

captures-17013-870x420

Frank Gehry’s striking Prospect Place design for phase three of the £9bn Battersea Power Station development

These enhancements include separating the station entrance to provide a western and an eastern entrance at ground level with the main building sitting above the station box.

A Battersea Power Station spokeswoman said: “Provision for design changes was made at the outset, given the scale and complexity of this major infrastructure project. TfL and BPS are working collaboratively on those designs and any related costs.”

Battersea-station-section_web

Original design for station box, without major oversite building

Battersea Northern line station station

Revised plan with Gehry designed building sitting above the station

 

 

Latest news

McAlpine pulls out of £55m Carlisle Citadels project

University of Cumbria starts hunt for replacement contractor
2 days ago

Strabag UK suffers further big trading loss

Austrian contractor is gearing up for major presence in the UK market
1 day ago

Durham Uni picks UPP for £130m student scheme

Firm will deliver 1,000 self-catered bed spaces
1 day ago

Architects now upbeat after 10-months of work gloom

Larger practices see rising workloads in next three months
1 day ago

Motorist dies after collision with road paver

Police Scotland investigating fatal crash
2 days ago

McLaren Living appoints HG Construction for £69m scheme

Build to Rent scheme will transform former vacant car park site in Leeds city centre
2 days ago

Squibb liquidator probes £2m of “missing” plant

Machinery, cars and scrap metal have disappeared at demolition specialist
2 days ago

Galliford Try to re-enter affordable homes market

Contractor sets out new five-year plan to build margin to 4%
2 days ago

Former Sellar chief to lead civils contractor Kilnbridge

Owen Dannatt joins as new CEO as founder Dermot McDermott becomes Chairman
2 days ago

Hunt starts for nuclear fusion plant construction partner

Fusion energy plant to be built at West Burton coal power station site.
2 days ago

National Grid raises £7bn for big infrastructure upgrade

Rights issue to fund a major round of capital investment in energy infrastructure
2 days ago

Grenfell police probe to last at least until end of 2025

19 companies and 58 individuals could eventually face charges
2 days ago

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
3 days ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
3 days ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
3 days ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
3 days ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
3 days ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
3 days ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
4 days ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
4 days ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
4 days ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
4 days ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
4 days ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
4 days ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
4 days ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
4 days ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
4 days ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
4 days ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
5 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
5 days ago

Contractor services