Queensferry Crossing to open five months late

Aaron Morby 7 years ago
Share

The Scottish Government has admitted the £1.4bn Queensferry Crossing will now open in May 2017 – five months later than planned.

Forth Crossing Bridge Constructors, the consortium building the bridge, has told ministers that ongoing effects of weather on construction mean it will require more time to complete the bridge.

The joint venture of Dragados, Hochtief, American Bridge International and Morrison Construction said the new opening deadline remained challenging but achievable.

Since last September the downtime due to strong winds has been 40% compared to the 25% anticipated by the contractor.

Until May, the bridge builders thought they could make up lost time.  But in April and May an unprecedented 13 days and 12 days were lost to bad weather scuppering plans to deliver the December 2016 target.

FCBC has taken on an extra 100 workers, increased working hours, altered construction methodologies where possible and challenged critical construction sequences to identify where any programme efficiencies could be found.

But the contractors are now warning they have now reached the stage where further extra resources will not bring the delivery date forward due to the complex technical nature of the construction work.

Screen Shot 2016-06-08 at 17.23.32

Specifically the bridge deck and the cable installation process, which began in September 2015, is particularly sensitive to wind and this increases as the cables used become longer and are installed at a greater height .

FCBC have confirmed this creates an unavoidable knock-on effect for subsequent activities, road surfacing and wind barriers which will now take place in wet and cold conditions during autumn and winter 2016/2017.

The builders contract runs until June 2017, meaning the project will still technically be on time even though completion was brought forward to December this year.

Cabinet Secretary for Economy, Jobs and Fair Work Keith Brown said: “We will continue to work closely with the contractors and I will personally ensure that every pressure and every resource is brought to bear to deliver or even better the revised target date of May 2017

“Going forward, in order to ensure that this project remains on track, I have implemented enhanced governance procedures from Transport Scotland senior management and will receive twice weekly updates from the project team.

“We have always been ambitious about this project and have always worked towards a deliberately ambitious target. However, It is important to recognise that FCBC still fully expects the project to complete within the timeframe of their contract. This project is not late and there will be no impact on the public purse.”

“The December 2016 target date was set to address concerns about the long term condition of the Forth Road bridge where it was originally believed that it would be restricted as early as 2017.

“These concerns have proven to be less immediate and the recently installed structural health monitoring system is providing assurance on the ability of the FRB to sustain traffic.”

Latest news

Lonsdale went down owing £65m to supply chain

More than 600 firms owed money as reduced credit rating sinks M&E giant
2 hours ago

Hunt for delivery partner to revive New Hospital Programme

Programme delivery partner to get £600m fee to get plans back on track
13 hours ago

Green light for new £780m Essex garden village

3,700 homes and four new schools to be built at Dunton Hills
10 hours ago

Laing O’Rourke makes a £288m loss

Rampant inflation on fixed-price jobs and problem contracts blow hole in accounts
18 hours ago

Keltbray, OCU and Clancy clinch £1bn electricity network upgrade

Scottish and Southern Electricity Networks awards biggest ever deals for central southern England
2 days ago

G&T enlisted for commercial review of HS2 main civils contracts

Phase 1 Main Works Civils Contracts to come under cost scrutiny
16 hours ago

TClarke order books doubles to top £1bn for first time

M&E specialist on track to exceed £500m turnover this year
17 hours ago

Wates signs Government safety remediation pact

Private builder belatedly signs fire safety developer remediation contract
18 hours ago

Liverpool all-electric industrial park approved

McLaren and Caddick in chase for Sefton 800,000 sq ft Atlantic Park scheme
1 day ago

Former Buckingham Group MD to join John F Hunt

Simon Hyams is new Managing Director for Contracting
2 days ago

Three in race for retendered £150m A9 dualling job

Bidders take another look after client takes on more risk
2 days ago

Clancy tops £300m revenue in fifth year of growth

Civils contractor delivers £13.5m pre-tax from water and energy sector work
2 days ago

Tower crane collapses on Edinburgh resi site

Jib falls onto apartment block under construction: Video
3 days ago

Salboy drops office space from Viadux Phase Two

Developer to focus on Manchester residential towers of 76 and 23 storeys
3 days ago

Warwick Uni plan for science and engineering campus

370,000 sq ft science and engineering precinct submitted for planning
2 days ago

Morgan Sindall chalks up Greater Manchester schools treble

Bury, Stockport and Wythenshawe school jobs will create 1,600 pupil places
2 days ago

Plans in for £65m Blackpool multiversity campus

Council leads plan for Talbot Gateway learning campus
2 days ago

Laing O’Rourke wins first phase of £700m Oxford R&D district

Landmark Red Hall and two labs to be built in phase 1a of Oxford North scheme
4 days ago

Ardmore wins retrofit deal on £200m Chancery Lane office

Building will be transformed to provide 105,637 sq ft of office space
3 days ago

Construction’s “Leading Lights” recognised

More than 50 winners in latest Considerate Constructors Scheme awards
3 days ago

Balfour Beatty clinches £20m Norfolk coastal defence jobs

Firm will install rock armour at Cromer and Mundesley
3 days ago

Architects join construction union Unite

Section of Architectural Workers forms official branch
4 days ago

Boot to build £20m lightweight aviation composites factory

Work starts on Sheffield University's COMPASS R&D facility
3 days ago

GMI secures £27m Leeds City College job

Site clearance underway for new Mabgate campus
4 days ago

Balfour signs deal with Koreans for UK power transmission jobs

Contractor strengthens large-scale onshore power transmission capability
4 days ago

36 storey south London build to rent flats tower approved

Construction to start next year on £220m Croydon scheme
4 days ago

Hunt for firms for £400m volumetric offsite deal

Procurement for Housing aims to expand its pool of firms on major offsite framework
4 days ago

Graham wins £87m Jock’s Lodge junction upgrade

Spring start for East Riding A164 improvement scheme near Beverley
7 days ago

Giant concrete pour at HS2 Curzon Viaduct: Video

Over 2,000 cubic metres create the first two 90 metre viaduct deck structures,
4 days ago

Cladding safety contractors told to wear body cameras

Insurance giant AXA to record remedial work
4 days ago

Contractor services