Civils contractors are calling for a procurement revolution to halt “unsustainable” increases in bidding costs.

Contractors are pointing the finger at the growing use of open tenders, disproportionate quality bid requirements and poor tender documents.

The Civil Engineering Contractors Association has now identified nine key problem areas:

  • Poor engagement with bidders
  • Too many bidders/use of open tenders
  • Poor tender documents
  • Disproportionate quality bid requirements
  • Frameworks that deliver less than forecasted revenue
  • Secondary competition in frameworks
  • Poor management of the procurement process
  • Quality of post tender feedback
  • Lack of enforcement of tender commitments

Open tenders allow any company to submit a bid for a project, without going through an initial prequalification process.

CECA said that although this saves on the administration associated with PQQs it runs the risk of very large tender lists which deters some contractors from bidding.

CECA is calling for open tenders to solely be used where doing so can be demonstrated to be the most effective way of engaging suppliers.

Head of External Affairs Marie-Claude Hemming said: “The way in which infrastructure is procured in the UK is in crisis with the costs of bidding for work challenging for the construction industry as a whole.

“Our research has found that the cost of tendering for a project is a significant proportion of any potential profit arising from its successful completion. This is not sustainable.

“To this end, we have worked closely with our membership to address the challenges faced, and we want to work with our customers to eliminate the costs associated with this bureaucracy, helping to support better outcomes for everyone and help meet the Government 2025 ambitions of 33 per cent lower cost.

“While there may be a case for open tendering in some circumstances, we want to ensure that the costs and potential pitfalls of this approach are well known prior to any decision by a customer to use this route to procure infrastructure.”

Latest news

£500m house building framework opens for bids

17 firms face fight to retain places on north west housing consortium list
16 mins ago

Sellafield awards £95m industrial services framework

Kaeffer seals new access, asbestos and insulation deal
6 mins ago

Government faces £49bn estate maintenance backlog

Spending watchdog calls for urgent action to save crumbling public estate
10 mins ago

Plasterer in court for Covid loan fraud

Fraudster spent £50,000 Bounce Back loan on gambling, groceries and fantasy football
5 mins ago

Industry’s best construction managers revealed

Full shortlist for CIOB Construction Manager of the Year award
19 hours ago

Government to signal backing for London airports expansion

Chancellor growth plan speech to give nod to Heathrow, Gatwick and Luton plans
17 hours ago

Hospital building plan extended by a decade – full list

All planned projects retained with fresh start dates for industry certainty
1 day ago

Kier launches £20m share buyback as debt cut

Steady first-half trading shrinks average month end debt to £38m from £137m
24 hours ago

Plans unveiled for £365m Heathrow data centre

Distribution centre developer moves into data centre market
24 hours ago

Plan for 6.5m sq ft Greater Manchester industrial zone

Russell LDP and Harworth to submit ambitious Northern Gateway plan this Spring
23 hours ago

Building boss sold diggers still on HP

Court hears how building director sold rented machines to fund sports car and gambling habit
2 days ago

Wates names new hard FM chief

Jack Prady joins from Thermic Technical FM
2 days ago

Council steps-in at sites where developer failed

First Endeavour LLP went under while building new homes across Fife
2 days ago

Mace confirmed for £93m weather centre HQ

Work to start on weather scientist hub at University of Reading
2 days ago

Council starts £200m hunt to replace Balfour Beatty

Tender race begins after Herefordshire Council parts ways with contractor
2 days ago

St William gets go-ahead for 245-home Stratford scheme

Planning approved for Stratford Gasworks regeneration
2 days ago

Balfour Beatty to sell Omnicom to Hitachi Rail

Digital rail monitoring business employs over 100 engineers
2 days ago

Van Elle partners with Wood on power transmission jobs

Ground investigation and piling deal worth over £30m
2 days ago

Former Balfour regional MD dies before taking up new role

Lindsay McGibbon struck down by cancer
5 days ago

One of Wales’ oldest contractors delivers record profit

Andrew Scott chairman says clients are now looking beyond lowest bids for jobs
5 days ago

Henry administrators chase £10m director payment

Cash frozen as legal action continues
6 days ago

Warning after scammers pose as plant hire bosses

Flannery targeted by fraudsters trying to con customers
5 days ago

Carey co-founder Tom Carey passes away

Contractor confirms death of second of three founding brothers
6 days ago

Robertson and Balfour win £333m schools deal

Contractors land work for five schools in Scotland
5 days ago

Go-ahead for £125m Ealing leisure centre and homes scheme

Council seeks contractor to deliver flagship Gurnell development
5 days ago

State of Englands local roads a ‘national embarrassment’

Spending watchdog urges Govt to tackle £15bn repair backlog
5 days ago

Worker loses three fingers at timber frame factory

Construction supplier fined after panel saw accident
5 days ago

Three in race for £20bn fusion power station

Balfour Beatty, Kier and Ferrovial head consortia in chase for 'star power' reactor
6 days ago

Office work drives 0.4% uptick in construction output

Activity in November grew four times faster than the UK economy as a whole.
6 days ago

Plans in for 34-storey Manchester student tower

Developer Vita plans 861-room tower in First Street district
6 days ago

Contractor services