First strike threat hits Hinkley construction work

Aaron Morby 9 years ago
Share

Hinkley Point nuclear power station project faces industrial disruption and delay after unions declared plans to ballot construction workers over a simmering row about bonus pay.

The GMB and Unite unions claim the Bouygues/Laing O’Rourke joint venture overseeing main construction has failed to pay the bonus rate predicated in the site industrial relations agreement.

An industrial relations flare-up so early in the project is a set back for the HPC Civil Construction agreement, which set out a clear framework to avoid costly disputes.

The first concrete pours for the main station foundations only just got underway at the end of March.

Now unions plan to hold a consultative ballot of the 700-strong workforce preparing the groundworks at the Somerset site. The ballot will run between 2-5 May.

Union officials argue that the bonus rate offered by the BYLOR consortium is insufficient to attract the quality of workers needed to ensure that that the civil works phase of the £18bn project is completed on time.

The Enquirer revealed earlier this month that construction workers are aiming for £60,000 packages on site, but it is understood current offers are a long way south of this figure.

Unite regional officer and chair of the HPC joint union committee Rob Miguel said: “The project has already suffered delays and to achieve the 2025 start date for electricity generation a skilled construction workforce is required.

“If the consultative ballot eventually leads to full-scale industrial action ballot, we could be looking at delays to the construction at Hinkley Point, which will be very expensive for the employers as hired-in plant and machinery will be lying idle.

“We would urge the employers to get back around the table with senior union officials to achieve a fair settlement, so building can continue to the highest standard, safely and on schedule.”

An EDF spokeswoman said: “We are committed to a continuing dialogue on this issue with our contractor and trade union partners. Discussions are ongoing and our intention is to reach a mutually acceptable outcome.

“We have a strong partnership in place with the trade unions based on a set of landmark agreements that include pay and productivity.

“We share a commitment with them and our contract partners to provide high quality employment standards, alongside the best standard in health, safety, quality and productivity.”

 

 

Latest news

Van Elle finds buyer for loss-making Canadian arm

Two-year North America foray ends with £2.6m exit deal
3 hours ago

£100m student halls to replace derelict London Crown Court

IQ student project gets go-ahead at Blackfriars court building site
3 hours ago

Safety green light for Newcastle student scheme

Gateway 2 approval process delays construction start by a year
3 hours ago

Bachy turnover sinks by over £100m as HS2 surge fades

Piling specialist reports slow year as mega projects step down
2 hours ago

Plans go in for next phase of Manchester Waters

New neighbourhood planned for island site
2 hours ago

Cardo nails £52m Sussex council homes roofing deal

Firm beats 14 rivals to take Lewes and Eastbourne roofing programmes
3 hours ago

JRL names new fit-out lead to drive expansion

Graham Ardley steps up to drive next phase of commercial and residential growth
3 hours ago

Construction output yo-yos as growth falters again

Quarterly output down 0.3% amid cautious investor sentiment
3 days ago

Free school build plans axed to fund £3bn SEND expansion

Education secretary scraps 28 free schools to plug SEND shortfall
3 days ago

McLaren seals £160m funding for Manchester student tower

737-bed Upper Brook Street student scheme forward funded by L&G
3 days ago

Former McAlpine boss lined up for Royal BAM board role

Paul Hamer to replace Paul Sheffield on Dutch group supervisory board
4 days ago

Plans go in for £650m retail park to resi scheme

Construction could start in early 2027 on new neighbourhood for Lewisham
4 days ago

Lovell launches Midlands refurb division

Renew Central to be headed by Carl Yale
3 days ago

M Group muscles into top five contractors after growth spurt

Private-equity backed infra giant builds £8.8bn work mountain
4 days ago

Plans in for first major build phase of £2bn York Central scheme

Developers table plans for nearly 1,000 homes, parkland and York’s new western station gateway
4 days ago

Lords push for staged Gateway 2 approval to aid design and build

Inquiry warns BSR’s over-detailed Gateway 2 demands are freezing D&B process
4 days ago

CITB wage bill tops £52m as staff numbers jump 13%

Accounts show 182 people at training body earn £60,000+ a year
4 days ago

Peterborough electrical specialist files administration notice

EML Electrical Contractors lodges court notice
4 days ago

Ant Yapi UK lands latest Chelsea Barracks deal

Fit-out work on Building 7 will last until summer 2027
4 days ago

Go-ahead for plan to level Cambridge retail park for life-science hub

Minister overturns council refusal as Railpen’s scheme promises £600m economic uplift
5 days ago

Subcontractor competition keeps build costs flat at Berkeley

"Highly competitive tendering" expected to continue next year
5 days ago

Industry calls grow to scrap the CITB

Latest training cuts final straw for a lot of contractors
6 days ago

Green light for major Oxford Circus mixed use scheme

Construction to start in 2029 on revamp of BHS and London College of Fashion site
5 days ago

Coventry to back build of Very Light Rail street pilot

Council set to approve 800m twin-track route in push for rapid-build transport revolution
5 days ago

Willmott Dixon on blocks for £35m Surrey leisure centre

Cranleigh leisure centre will be the third in the UK built to Passivhaus-standard
6 days ago

Benniman bags latest DIRFT next-gen logistics job

DC11 shed to raise sustainability bar at rail-linked logistics park
6 days ago

Vinci wins funding sign-off to begin main £70m St Helens rebuild

Early 2026 start confirmed as council signs off biggest investment in decades
6 days ago

£175m Trafford Stretford Mall resi job out to bid

Trafford Council starts hunt for contractor for 249-home first phase
6 days ago

CITB cuts more training funds despite £79m cash pile

Training body imposes another round of sudden cuts on contractors
7 days ago

Mace design director joins McLaren

Lucy Craig appointed design director at Construction Management and Specialist Projects division
6 days ago