Landmark VAT ruling on student rooms projects

Aaron Morby 7 years ago
Share

Contractors should no longer be required to pay 20% VAT on subcontractors’ services on new build student accommodation after an important tax tribunal ruling.

Create Construction's new-build student project in Leicester
Create Construction's new-build student project in Leicester

HMRC’s VAT policy on new build student accommodation has been successfully challenged in a case taken to the Tax Tribunal by Glyn Edwards, VAT Director at MHA MacIntyre Hudson.

The case should bring significant cash flow savings for student accommodation contractors, although the application of the landmark judgement will depend on the precise circumstances of each development around the wording of planning consents.

The appeal concerned the VAT treatment of electrical services provided by Summit Electrical Installations, sub-contractors at a new build student site in Leicester.

Main contractor Create Construction had received a certificate from the developer claiming relief from VAT on the basis that the new building would be used for a relevant residential purpose  – communal building for students.

Usually subcontractors working on RRP buildings are not entitled to zero-rate their services.

This means VAT has to be charged at 20% which the main contractor must then reclaim on a VAT return.

Like most modern student blocks, the units were designed as self-contained living accommodation including kitchenettes and en-suite bathrooms.

Crucially while the building planning consent restricted use to students, there was no clause preventing each unit from being separately used or sold.

On the basis that the project was the construction of dwellings and should therefore be VAT zero-rated, Create Construction refused to pay VAT on Summit’s services.

HMRC argued that restricting occupation to students was a restriction on the separate use of each unit.

But the tribunal agreed that the student accommodation could be treated as ‘dwellings’ for VAT purposes.

The tribunal then considered HMRC’s published policy which is that subcontractors must charge VAT if a certificate has been issued to the main contractor claiming zero-rating under the RRP relief, even if the construction would also meet the definition of dwellings. The judge dismissed that policy as entirely wrong.

Glyn Edwards, VAT Director at MHA MacIntyre Hudson, said: “The tribunal’s decision was a welcome relief for Summit Electrical Installations, but the principal winner in the dispute is Create Construction.

“Create Construction has numerous sub-contractors in exactly the same position, and so faced the prospect of having to finance VAT payments to all of them on a multi-million pound development.

“We hope that HMRC will now acknowledge the inaccuracy in their published policy on this type of buildings, as it has created considerable uncertainty in the construction sector.”

Latest news

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
1 hour ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
1 hour ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
1 hour ago

Olympian Homes gets go-ahead for Bristol’s tallest building

Work on student and co-living towers to start this summer
50 mins ago

ISG gets nod to start £20m Glamorgan school job

Ysgol y Deri specialist needs school is to built at Cosmeston, near Penarth
56 mins ago

Walker Modular lands £5m bathroom pod contract

Specialist to work with Graham and Watkin Jones on major build-to-rent scheme

Banned building boss jailed for fraud

Court hears how disqualified director siphoned off cash from new housing company
1 hour ago

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
3 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
3 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
3 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
3 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
3 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
3 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
3 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
4 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
4 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
4 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
4 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
4 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
4 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
5 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
5 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
5 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
5 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
5 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
6 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
6 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
6 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
6 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
6 days ago

Contractor services